|
|
|
April 2006 |
|
![]() |
FHWA-HRT-06-024 | ||
|
![]() The Bowman Road Bridge in Defiance County, Ohio, was constructed using geosynthetic reinforced soil technology (GRS) for the abutments. |
The innovation of using GRS paid off, as Defiance County realized a cost savings of nearly 25 percent on its first bridge support project. The bridge was also built in 6 weeks, versus a typical construction time of several months for a conventional bridge. "Significant savings were realized in both time and costs," says Adams. The construction time for the bridge could have been reduced even more, to less than 3 weeks, if two separate labor crews had been used to build both abutments simultaneously.
For the Bowman Road Bridge, instead of using cast-in-place concrete for the abutment walls, split-face cinder blocks (modular concrete blocks) were used to face the abutment. Building a GRS mass is as easy as 1-2-3: a row of blocks, a layer of compacted fill to the height of the facing blocks (20 cm (8 in)), and then a layer of geotextile. Each layer of geotextile is extended between the rows of blocks to connect the block to the GRS mass. The 1-2-3 process is repeated until the wall height is reached. "There are two necessary factors to assure good performance of a GRS mass: good compaction with quality granular fill and close reinforcement spacing," says Adams.
Precast concrete box beams were placed directly on the GRS abutments without a concrete footing; the bridge structure has no cast-in-place concrete. The bridge also does not have an approach slab, but rather GRS was compacted directly behind the bridge beams to form the approach way and to create a gradual transition from the roadway to the bridge. Asphalt pavement was placed on the bridge and approach without a conventional joint system at the bridge ends. The intent was to allow the bridge and the adjacent road to settle together, providing a bump free, smooth ride for drivers traveling on and off the bridge.
![]() Above: Concrete box beams are placed directly on the GRS abutments. Below: Construction of the GRS abutments. ![]() |
FHWA instrumented the bridge so that performance monitoring can be conducted over the next 2 to 3 years. "It is performing very well," says Schlatter. "There has been very little movement or settling, and no pavement cracking."
Defiance County is planning to build seven more abutments this year using GRS. "One of the biggest advantages for us is convenience," says Schlatter. "There are many construction advantages over using concrete, including the ability to build the abutments in all kinds of weather conditions." Other States that have expressed interest in using GRS for abutments include Illinois and Massachusetts.
To learn more about GRS technology or the Bowman Road Bridge, contact Mike Adams at FHWA, 202-493-3025 (email: mike.adams@fhwa.dot.gov). Additional information on the Bowman Road Bridge is also available from Warren Schlatter of Defiance County, 419-782-4751 (email: dce@defiance-county.com).
..................................................
Articles in this issue:
Building the Bridge of the Future with GRS Technology
Geotechnology Increases Roadway Safety in Great Smoky Mountains National Park
..................................................