|
|
|
December 2004 |
|
![]() |
FHWA-HRT-05-022 | ||
|
![]() |
![]() |
![]() |
| Work performed under the DC Streets contract has included snow removal (top and bottom) and clearing trees and other debris after Hurricane Isabel hit the city in September 2003 (middle). |
Simon Rennie, DDOT project manager for DC Streets, notes that change can be difficult in public agencies, and welcomes the injection of innovation that this type of contract allows. According to Rennie, the greatest advantage to such a contract is the ability to address unforeseen maintenance without the need for an additional appropriation process and the corresponding delay. For example, when Hurricane Isabel struck the District in September 2003, resulting in downed trees and submerged highways, Rennie had already consulted with VMS to arrange standby crews to address the damage. As a result, the roadways were restored within 72 hours, a feat that Rennie does not believe would have been possible before the DC Streets initiative was in place.
Rennie places a high value on this responsiveness to emergencies and citizen complaints. "Now, when someone calls our office with a report of an asset needing repair, I can call VMS, report the problem, get the schedule for when it will be fixed, and call the citizen back and tell them when the problem will be addressed, all in a short time," he says.
Despite its successes, the DC Streets program has not been without a few lessons learned on how to do a better job in future initiatives. According to Mark Robinson, program manager for Science Applications International Corp. (SAIC), which provided management consulting services for the DC Streets initiative, the contract has been a success, but some of the actual contract language should be adjusted in future contracts of this nature.
"Because this was the first time that such a contract was drafted for an urban area, some of the demands it stipulates were not achievable with reasonable effort," says Robinson. "For example, a few of the maintenance categories are still not up to par because there is not a well defined line between what is rehabilitation, which is covered in the contract, and what is reconstruction, which is not. So some actions required to satisfy the performance standards fall outside the scope of the contract. We've resolved these issues through a combination of general partnering agreements and item-by-item negotiations. Because this is a hybrid of a construction and a services contract, we need to better define the rehabilitation/reconstruction criteria in the future."
Herlich agrees that criteria and definitions need to be clarified in future agreements. "Some of the standards were contradictory," he notes. "For example, there is a standard for curb conditions. In some cases, tree roots have displaced the curb slabs, and the only way to fix this is to remove the trees. But another standard says that these trees should be preserved. We resolved the conflict through mediation and consultation, and kept the trees."
Rennie would like to see language in future contracts tying the meeting of performance standards to the incremental payment of the contract. Currently, VMS receives a monthly payment regardless of asset conditions. He would also like to see a greater sampling of assets to determine if performance standards have been met. The current sampling percentage is 10 percent.
Looking beyond the contract's completion in July 2005, Sheldahl expects the District to opt for smaller, follow-on asset management contracts focusing on specific types of assets, such as tunnels or bridges. He expects to see four to five such contracts, addressing the most vital components of the NHS, and possibly expanding to other District arteries that are not a part of the NHS. However, funding may not be available to issue contracts for all of the components of the DC Streets program. VMS would pursue a contract similar to DC Streets in the future without question, says Herlich, and might pursue smaller contracts if they make sense for the company.
"Performance-based contracts, when closely monitored, are definitely a good way to go," adds Rennie.
For more information about the DC Streets initiative, contact Edward Sheldahl at FHWA, 202-219-3514 (email: edward.sheldahl@fhwa.dot.gov), Simon Rennie at DDOT, 202-671-4666 (cell: 202-438-8607; email: Simon.Rennie@dc.gov), or Mark Robinson at SAIC, 703-676-2384 (email: MARK.D.ROBINSON@saic.com).
..................................................
Articles in this issue:
Prefabricated bridges deliver quality, safety, and savings
DC Streets: Innovation yields results
Highway quality takes center stage at summit
Concrete Pavement Technology Program introduces new and improved tools for pavements
..................................................