Inspecting the Enclosure
Project #___________________
Date:_____________
Inspector:__________________
Verify adequacy of the containment system. ___
- Containment built according to the approved plan.
- Tarps free of holes with seams overlapped and securely fastened.
- No visible dust escaping from containment.
- No signs of surrounding ground or water contamination.
Comments:
Evidence of proper air movement within the containment. ___
Comments:
Proper storage of debris. ___
- On-site storage of waste should not exceed 90 days.
- Contaminated waste is not accessible to the public and is not subject to traffic collision.
Comments: