Project #___________________
Date:_____________
Inspector:__________________
Verification that the paint has not exceeded its shelf life. ___
Comments:
Verification that the paint is not stored in areas subject to temperatures
beyond the recommended limits. ___
Comments:
Verification that the paint has not exceed its pot life. ___
Comments:
Documentation of any use of thinner. Do not exceed recommended maximum. ___
Comments:
Verification of curing time. After painting, inform the contractor of the estimated
time that should be allowed for the paint to cure. Do not allow another coat
to be put on until the appropriate amount of time has elapsed per the existing
weather conditions. ___
Comments:
U.S. Department of Transportation