|


| |
Publication
Nos. FHWA-RD-98-155, -156, -171, and FHWA-RD-99-059
- December 1998
|
|
What Are Performance-Related Specifications? |
 |
 |
Over the past 25
years, there has been a growing interest in the development of performance-related
specifications (PRS) for highway pavement construction. PRS are
similar to quality assurance specifications; however, the measured acceptance
quality characteristics (or AQCs, which include concrete strength,
slab thickness, initial smoothness and others) are directly related to
pavement performance through mathematical relationships. Performance
is defined by key distress types and smoothness and is directly related
to the future maintenance, rehabilitation, and user costs of the highway.
This link between measured AQCs and future life-cycle costs (LCCs)
provides the ability to develop rational and fair contractor pay adjustments
that depend on the as-constructed quality delivered for the project (figure
1 illustrates these concepts).
Figure
1. Basic concepts of the LCC-based PRS method used to establish
contractor pay adjustments.

The State highway agency (SHA) must define
the as-designed or target levels of quality for which it is willing to
pay 100 percent of the bid price. Prior to bidding, the contractor
is made fully aware of this desired level of quality and the price adjustments
to be applied when this level is not obtained. Contractor pay for
a lot is based on the difference between the as-designed target LCC and
the as-constructed LCC, subjected to specified limitations by the SHA.
The clear and rational approach of PRS, with
well-defined SHA quality levels that are understandable to the contractor,
are expected to lead to significantly improved highway construction quality,
improved pavement performance and a reduction in LCC. PRS also offer
the opportunity to optimize the design and construction process to provide
acceptable performance for lower LCCs.
A prototype PRS, using this methodology, was
first developed under a previous Federal Highway Administration (FHWA)
project conducted during the early 1990s.(1,2,3)
Under the current FHWA project, the prototype PRS were revised and expanded
to make them more practical. Three different implementation levels
(Level 1, Level 2, and Level 3) were defined, with the first (Level 1)
being a simplified PRS that should be reasonably compatible with current
SHA sampling and testing procedures.
|
Key Products of This Research |
 |
 |
- Definition of the three levels of PRS development and implementation
for jointed-plain concrete pavement (JPCP) highways and full development
of a simplified Level 1 PRS approach for JPCP highways. This Level
1 PRS is implementable and does not normally require major changes to
an SHAs current sampling and testing procedures.
- Complete stand-alone specifications for the Level 1 and Level 2 PRS
(included as appendix A in volume I), along with user-friendly software
(PaveSpec 2.0) to assist in PRS implementation and usage (see volume
IV). SHAs and contractors can readily utilize PaveSpec 2.0
to demonstrate the PRS and to determine the risks and consequences of
varying levels of quality.
- Practical guide to developing and implementing the revised Level 1
and Level 2 PRS. This practical guide (included as volume I)
not only provides guidelines and recommendations for making the required
PRS-related decisions, but also includes step-by-step procedures to
using the PRS.
- Successful field investigations into the practicality and implementability
of both the Level 1 and Level 2 PRS approaches (see volume II).
The following three investigative methods were used: (1) shadow field
demonstrations, (2) demonstration of the development of PRS for three
functional classes of highways in a given SHA, and (3) comparing PRS-based
vs. actual SHA price adjustments using historical project data.
The PaveSpec 2.0 Software and
The Practical Guide |
 |
 |
The PaveSpec 2.0 software was created to demonstrate and apply all aspects
of the current PRS methodology (both Level 1 and Level 2). Some
of the programs specific capabilities include:
- Simulation of pavement performance (key distresses, smoothness).
- Application of a user-defined maintenance and rehabilitation (M &
R) plan; computation of lot LCCs; simulation of Level 1 AQC pay
factor charts (an example of which is presented in figure 2).
- Computation of contractor lot pay factors (pay adjustments) based
on actual measured AQC data. Simulation of the consequences and risks
of achieving different levels of quality for a project.
- The ability to conduct sensitivity analyses on a given developed specification.
The PaveSpec 2.0 software is an invaluable tool for demonstrating and
clarifying the revised PRS concepts to both the SHA and the contractor.
It is also an excellent technology transfer tool for SHAs and contractors.
Figure
2. Example of a Level 1 pay factor chart for concrete strength.
(Similar charts are developed for each AQC included in the PRS.)

|
Implementation of the Level 1 PRS |
 |
 |
It is recommended that an SHA interested in implementing a PRS for the
acceptance of JPCP highway pavements begin with the implementation of
the simplified Level 1 PRS. The Level 1 approach is explained in
table 1.
Table
1. Summary of the basic steps used to develop Level 1 PRS.
|
1.
|
Define the general project information |
This information includes items such
as project location, lane configuration, starting and ending stations,
and lane widths. |
|
2.
|
Define pavement performance |
Pavement performance is defined in
terms of distress indicators. The following distress indicator
models (shown with their associated AQCs) are available:
- Transverse cracking (fatigue)function of concrete
strength and slab thickness.
- Transverse joint faultingfunction of concrete strength,
slab thickness, and percent consolidation around dowels (optional).
- Transverse joint spallingfunction of air content
and concrete strength (both are optional).
- Pavement smoothness over time (Present Serviceability Rating
[PSR] or International Roughness Index [IRI])function
of initial smoothness and other predicted distress indicators.
|
|
3.
|
Select the AQCs to include in
the PRS |
Include one or more of the following
AQCs: concrete strength, slab thickness, entrained air content,
initial smoothness, and percent consolidation around dowels. |
|
4.
|
Define the required constant variables |
A number of design-, climatic-, and
traffic-related variables must be defined for the project. These
required constant inputs correspond to the variables included
in the distress indicator models. |
|
5.
|
Define the AQC acceptance sampling
and testing plan |
The SHA must define the acceptance
sampling and testing procedures used to measure the included AQCs
in the field. This plan not only defines the actual required
sampling and testing methods to be used, but it also defines the
number of samples per sublot and the methods for determining random
sampling locations. |
|
6.
|
Determine the required AQC target values |
The SHA must select as-designed target
means and standard deviations for each of the included AQCs.
(Note: The selected target values are dependent on the
selected sampling and testing plan.) The target values identify
the quality for which the SHA is willing to pay 100 percent. |
|
7.
|
Define lots and sublots |
Lots and sublots must be clearly defined
for the project. A lot is typically chosen as one days
paving (or less). Each lot is divided into approximately
equal area sublots. The target sublot length must be defined
so that all included AQCs can be sampled from each sublot. |
|
8.
|
Define the maintenance and rehabilitation
plan |
The selected M & R plan defines
the type and frequency of application for maintenance and rehabilitation
activities to be applied in response to predicted distress conditions. |
|
9.
|
Define the included costs |
The SHA must identify the particular
costs to be included in the overall lot LCC. These decisions
include identifying the M & R unit costs associated with the
chosen M & R activities, defining an appropriate percentage
of user costs to be included, and determining an appropriate discount
rate. |
|
10.
|
Define the simulation parameters |
In order to conduct LCC simulations
for the as-designed target or as-constructed pavement, the SHA
must define the required simulation parameters (e.g., the number
of simulation lots required to simulate a representative lot LCC
and the number of sublots per lot). |
|
11.
|
Develop individual AQC pay factor charts
and corresponding equations |
Individual AQC pay factor charts are
developed specific to those AQCs included in the specification.
Each chart is made up of a series of pay factor curves
(each specific to a different AQC standard deviation) plotted
over a chosen range of AQC mean (see figure 2). Pay factor
regression equations are fit through simulated data points making
up each pay factor curve. Individual AQC pay factors are
determined using the developed regression equations by knowing
the as-constructed AQC lot means and standard deviations. |
|
12.
|
Define the composite pay factor equation |
The overall lot pay factor is computed
using a defined composite pay factor (CPF) equation. The
CPF equation is a simple mathematical function of the individual
AQC pay factors determined using the pay factor charts and equations
developed in step 11. |
|
13.
|
Define practical pay factor limits |
The SHA must define practical pay factor
limits to the computed individual AQC pay factors and the lot
CPF. |
|
14.
|
Develop and analyze expected
payment curves |
Expected payment (EP) curves
should be developed and analyzed to make sure the expected payment
at the target values is at or near 100 percent with the step 13
limits in effect. |
|
Impacts of this Study |
 |
 |
Some of the recognized benefits of PRS to SHAs and contractors
are the following:
- PRS require the establishment of clear AQC target values (means and
standard deviations) that define the pavement quality for which the
SHA is willing to pay 100 percent of the contractor bid price.
- PRS provide a straightforward method for determining rational (LCC-driven)
pay adjustments (incentives and disincentives) that are applied when
a higher or lower level of quality (as compared to the chosen AQC target
values) is produced by the contractor. Potential contractors
are made fully aware of the pay adjustments prior to bidding a project
and can also utilize the PaveSpec 2.0 software to evaluate the consequences
and risks of providing different levels of quality and the risks involved
in sampling and testing.
- PRS relate the quality of pavement construction to the performance
and subsequent LCCs of a given pavement lot. This ability
provides the opportunity to identify optimum levels of AQC construction
quality that would minimize LCCs while maintaining desired performance.
|
References |
 |
 |
- Darter, M.I., M. Abdelrahman, P.A. Okamoto, and K.D. Smith. Performance-Related
Specifications for Concrete Pavements: Volume IDevelopment of
a Prototype Performance-Related Specification. FHWA-RD-93-042. Washington,
DC: Federal Highway Administration, 1993.
- Darter, M.I., M. Abdelrahman, T. Hoerner, M. Phillips, K.D.
Smith, and P.A. Okamoto. Performance-Related Specifications for Concrete
Pavements: Volume IIAppendix A, B, and C. FHWA-RD-93-043.
Washington, DC: Federal Highway Administration, 1993.
- Okamoto, P.A., C.L. Wu, S.M. Tarr, M.I. Darter, and K.D.
Smith. Performance-Related Specifications for Concrete Pavements:
Volume IIIAppendix D and E. FHWA-RD-93-044. Washington, DC:
Federal Highway Administration, 1993.
|