
|
Introduction |
 |
 |
Performance-related specifications
(PRS) have capabilities beyond traditional QA specifications. These capabilities
include clearly defining lots and sublots (for all sampling and testing), the subsequent
sampling and testing of key AQC's that relate directly to the future performance of
the constructed pavement, and predicting future LCC's used to compute contractor pay
adjustments (incentives and disincentives). Thus, the level of quality (expressed as
a mean and standard deviation) achieved for each of the key AQC's can be related
directly to rationally computed pay adjustments based on sound economic principles.
The initial ground-breaking work on PRS was done by R.M.
Weed for the New Jersey Department of Transportation.(7) This
work provided a basis for the prototype PRS developed under a previous FHWA research
study. (See references 1, 2, 3, and 8.) The prototype used an innovative approach
that considered the estimated future LCC of the pavement as the overall measure of
quality. Under the prototype, target values (means and standard deviations) must be
established for four key AQC's (concrete strength, slab thickness, entrained air
content, and initial smoothness). These AQC's are then measured from the in
situ pavement during construction. The computed as-constructed AQC lot means are
then used in established mathematical models to predict key distress indicators
(transverse joint faulting, transverse cracking, transverse joint spalling, and PSR) over
a chosen analysis period. The amount of the pay adjustment is then based on the AQC
quality-related increase or decrease in future LCC's expected to be incurred by the
agency over the chosen analysis life of the project (assuming a given rehabilitation
policy). A computer software program, PaveSpec, was developed to demonstrate the
prototype specification.
Although the prototype PRS were based on rational concepts, researchers
realized that an attempt to implement such specifications would most likely
be met with resistance. This resistance would result from the general
unfamiliarity with the current PRS concepts, the dependency of computed
pay adjustments on the PaveSpec software, the additional costs associated
with strongly emphasized in situ testing, and the need to simulate the
actual pay factor in the field. Under the current research project, a
strategy was developed to aid in the acceptance and implementation of
the revised prototype PRS. This involved the development of three different
PRS implementation levels. Each of these is described in detail in the
following section.
|
Three Levels of PRS Implementation |
 |
 |
The overall goal of PRS research is to progress toward developing ideal
PRS that incorporate all important AQC's of PCC pavements that
not only affect pavement performance, but are also under the control of
the contractor. As a means of achieving this goal, future research should
attempt to:
- Identify distress indicators that significantly affect pavement performance (these drive
the PRS).
- Identify the AQC's and other variables that directly affect each identified
distress indicator.
- Develop early age, rapid, reliable, easy, and cost-effective field tests that measure
the in situ quality level of each identified AQC.
- Develop accurate distress indicator prediction models that are dependent on the measured
quality level mean and variability of each identified AQC (none of the current models are
directly dependent upon variability).
- Develop a practical, yet comprehensive, method for the calculation
of overall lot pay adjustments using sound economic principles.
Obviously, much research is needed to develop and implement an ideal PRS. Such an
effort will take much more research and funding. Therefore, as a means of organizing
the envisioned work needed to develop these ideal PRS, three different levels
(chronological steps) of PRS implementation were proposed. These three levels are
defined as follows:
- Level 1Simplified PRS:Developed as a simplified version of the original
prototype PRS. It is believed that the current Level 1 acceptance testing would not
differ greatly from the procedures currently used by SHA's. AQC quality can be
approximately assessed using selected parts of the agency's current AQC sampling and
testing methods for core strength, entrained air content, slab thickness, percent
consolidation around dowels, and initial smoothness.
The Level 1 pay factor computation method is based on calculating independent
pay factors for each AQC (all other AQC's are assumed to be equal
to the target values). Each of these pay factors is determined from
a series of developed pay factor versus AQC mean curves. These curves,
each specific to a different as-constructed AQC standard deviation,
are created by correlating simulated lot pay factors over a range
of AQC means. Each computed pay factor is, therefore, a function
of the measured as-constructed mean and standard deviation, target
mean and standard deviation, and sample size. Final payment for
the lot is based on a chosen CPF equation (expressed as a simple
mathematical function of the independently determined AQC pay factors).
This Level 1 CPF is an estimate of the pay factor determined using
the more rigorous procedures of Level 2.
- Level 2Transitional PRS: The Level 2 specifications generally use the same
concepts and procedures developed for the original prototype PRS.(1,2,3)
The Level 2 specifications represent the dynamic transition from the original prototype
specifications presented in the final report of a previous FHWA research project to the
ultimate goal of Level 3.(1,2,3) The Level 2 PRS encourage the use of more in situ and
nondestructive sampling and testing that can be used to accept pavement lots at much
earlier ages (e.g., using 3-day core compressive strength results for the acceptance of
concrete strength). The Level 2 PRS also require more computer simulation to compute
pay adjustments.
The Level 2 pay factor computation method calculates lot pay factors by directly
comparing simulated as-designed (target) and as-constructed LCC's. Interactions
of AQC's are included in the simulations (e.g., an increase in concrete strength may
counteract a deficiency in slab thickness). The pay factor calculation is based on
the premise of liquidated damages. Final payment for the lot is based on the
simulated pay factor determined using the PaveSpec software.
- Level 3Ideal PRS: The Level 3 specifications represent the ideal
specifications that will eventually be achieved with much future research. Such
specifications would include many more AQC's that are not currently measurable.
Also, these AQC's would be measured using reliable early age methods that are
both in situ and nondestructive.
Each level may differ in the number of AQC's included, the sampling and testing
methods required for each AQC, the distress indicator prediction models used to predict
pavement performance, and the computation method for payment adjustments. The
details of the three proposed PRS levels of implementation are summarized in table 1.
The original PRS prototype and corresponding computer program (PaveSpec)
have been updated and revised under this current research project. The
revised PRS prototype addresses both Level 1 and Level 2 PRS acceptance
procedures and is included as appendix
A (in this volume).
 |
|
Table 1.
Details of the three proposed PRS implementation levels. |
|