Introduction |
 |
 |
When developing a PRS for use in the
field, the agency must make some important pay adjustment-related decisions. One of
these decisions involves deciding whether to use Level 1 or Level 2 pay adjustment
procedures. If the agency chooses to accept as-constructed pavement using Level 1
pay adjustment procedures, an appropriate lot composite pay factor (CPF) equation must be
determined. Finally, the agency must determine how pay factors are to be limited
when making final contractor pay adjustments. This chapter is designed to provide
the agency with the information required to make these decisions.
Selecting a Pay Adjustment Procedure (Level 1 or Level 2) |
 |
 |
The current revised PRS prototype specification allows the
agency to choose from two different pay adjustment procedures (representing the two
different PRS implementation levels). Level 1 is offered as a simplified (and,
therefore, more immediately implementable) method of estimating the results obtained from
Level 2. Table 9 reiterates some of the main differences between the two PRS
implementation levels.
Table
9. Key differences between PRS Level 1 and Level 2 pay adjustment procedures.
Characteristic |
Level 1 |
Level 2 |
Primary Method of Acceptance Testing |
Current acceptance tests used by the agency. |
In situ acceptance testing is recommended. |
Included Acceptance AQC's |
Only those AQC's (of the available five) historically measured by the agency for acceptance. |
Any or all of the five AQC's available for inclusion in the PRS. |
Preconstruction Output |
Individual pay factor charts for each AQC. Each is developed assuming that the other AQC's are held constant at their target values. |
One simulated overall as-designed lot LCC (reflecting the interactions between AQC's). |
Overall Lot Pay Factor Method |
Determined as a simple mathematical function of the individual AQC pay factors (CPF equation). This CPF estimates the pay factor obtained from the Level 2 direct simulation. |
Determined directly through simulation of all AQC's. The closest simulation of actual field conditions. |
It is strongly recommended that an agency gain experience
with the current PRS approach using Level 1. Although the Level 1 pay factor is only
an estimate of the computed Level 2 pay factor, at this time, the Level 1 approach is by
far the most practical of the two approaches as it provides important preconstruction
output desired by both the agency and the contractor. After gaining experience with
the Level 1 approach, an agency may begin using the Level 2 approach or a combination of
Level 1 and Level 2.
Defining a Level 1 Composite Pay Factor Equation
It is recommended that the governing CPF equation be a
simple mathematical relationship of the independently determined AQC pay factors. A
number of different simple equation forms are currently used by agencies to determine CPF
equations. These same concepts may be used to determine CPF's using the Level 1
PRS approach. Four specific CPF equation forms are discussed in more detail in the
following sections.
Weighted Average
The weighted average CPF method involves multiplying
each calculated individual AQC pay factor by agency-chosen AQC weighting factors.
Each of the AQC weighting factors is "determined through empirical observation or
other engineering considerations," as stated in the AASHTO Implementation Manual
for Quality Assurance.(28) Using this method, the resulting lot CPF is determined using
equation 18.
CPFLOT =
å(PFn*Wn) /
å(Wn)
(18)
where
CPFLOT = Calculated Level 1 lot CPF.
n = Total number of AQC's included in the Level 1 specification (e.g., if the agency chooses to only include concrete strength and slab thickness, then n =2).
PFn = Independently determined Level 1 pay factors for each of the n AQC's included in the Level 1 specification.
Wn = Respective weighting factors for each of the n AQC's included in the Level 1 specification.
An example illustrating the weighted average method is as follows:
Let's assume that the AQC's included in the specification consist of concrete
strength, slab thickness, entrained air content, and initial smoothness. Therefore,
the relevant calculation results are shown in table 10. Substituting the appropriate
calculated values into equation 18 gives the following:
CPFLOT = [å(PFn* Wn) / å(Wn)]
= [543.5 / 5.3]
= 102.5 percent
Therefore, for this example, the contractor would receive a pay incentive equal to 2.5
percent of the submitted bid price.
Table
10. Example calculations demonstrating the weighted average CPF method.
AQC |
AQC number (n) |
Individual AQC PF (PFn) |
AQC PF Weighting Factor (Wn) |
PFn* Wn |
Concrete Strength |
1 |
106.5 |
1.3 |
138.5 |
Slab Thickness |
2 |
102.3 |
1.5 |
153.5 |
Entrained Air Content |
3 |
98.5 |
1.0 |
98.5 |
Initial Smoothness |
4 |
102.0 |
1.5 |
153.0 |
|
|
|
å(Wn) = 5.3 |
å(PFn*Wn) = 543.5 |
Note: PF = pay factor.
Simple Average Method
The simple average CPF method involves computing the
average of the calculated individual AQC pay factors. The resulting lot CPF equation
is computed using equation 19.
CPFLOT = å(PFn) / n
(19)
where
CPFLOT = Calculated Level 1 lot CPF.
n = Total number of AQC's included in the Level 1 specification.
PFn = Independently determined Level 1 pay factors for each of the n AQC's included in the Level 1 specification.
An example illustrating the simple average method is as follows:
Assuming the same included AQC's and measured individual AQC pay factors used in
the weighted average method example, equation 19 then becomes the following:
CPFLOT = å(106.5 + 102.3 + 98.5 + 102.0) / 4
= (409.3) / 4
= 102.3 percent
Therefore, using the simple average method for this example, the contractor would
receive a pay incentive equal to 2.3 percent of the submitted bid price.
Summation Method
The summation CPF method involves summing the
individual AQC pay adjustments (difference between the computed AQC pay factor and 100
percent). The resulting lot CPF equation is computed using equation 20.
CPFLOT = å(PFn 100) + 100
(20)
where
CPFLOT = Calculated Level 1 lot CPF.
n = Total number of AQC's included in the Level 1 specification.
PFn = Independently determined Level 1 pay factors for each of the n AQC's included in the Level 1 specification.
An example illustrating the summation method is as follows:
Assuming the same included AQC's and measured individual AQC pay factors used in
the previous examples, equation 20 then becomes the following:
CPFLOT = å(PFn 100) + 100
= (106.5 100) + (102.3
100) + (98.5 100) + (102.0 100) + 100
= 6.5 + 2.3 1.5 + 2.0 + 100
= 109.3 percent
Therefore, using the summation method for this example, the contractor would receive a
pay incentive equal to 9.3 percent of the submitted bid price.
Product Method
The product CPF method involves multiplying the
individual AQC pay factors (expressed as decimals, e.g., 103 percent = 1.03). The
resulting lot CPF equation is expressed in equation 21.
CPFLOT = (PF1
* PF2*
*PFn) /(100)n-1
(21)
where
n = Total number of AQC's included in the Level 1 specification.
PF1 to PFn = 1 to n independently determined Level 1 AQC pay factors.
An example illustrating the product method is as follows:
Assuming the same included AQC's and measured individual AQC pay factors used in
the previous examples, equation 21 then becomes the following:
CPFLOT = (PF1
* PF2*
*PFn) /(100)n-1
= (106.5 * 102.3 * 98.5 * 102.0) /1003
= 109.5 percent.
Therefore, using the product method for this example, the
contractor would receive a pay incentive equal to 9.5 percent of the submitted bid price.
Selecting an Appropriate CPF Method
The goal is to determine the overall lot CPF that represents
the performance that actually occurs over time. The Level 2 PRS simulation gives the
best available estimate of the true pay factor. Of the four CPF methods presented in
this section, the product method has typically been found to most closely approximate this
Level 2 pay factor. However, agencies are encouraged to choose an appropriate CPF
method after conducting comparisons of the available CPF methods using the sensitivity
analysis portion of the PaveSpec 2.0 software.
|
Selecting Pay Factor Limits |
 |
 |
Although the agency indirectly limits pay factors by
defining appropriate MQL's for the quality of each AQC (see the section titled Retesting Procedures in chapter
5), an agency should also apply direct limits to the calculated individual AQC pay
factors, the overall lot pay factor, or both. This pay factor limiting process is
best explained using examples.
Let's use the product method for illustration purposes.
For the chosen example, all five AQC's are included in the specification.
The assumed AQC pay factors for use in the example consist of the following:
- Concrete Strength: PFSTR = 108.5
- Slab Thickness: PFTHK= 105.3
- Entrained Air Content: PFAIR = 99.5
- Initial Smoothness: PFSM = 96.4
- Percent Consolidation: PFCON = 102.4
The CPF for the lot (without applying any pay factor limits) is calculated as the
following, using equation 21:
CPFLOT = (PF1
* PF2*
*PFn) /(100)n-1
= (108.5 * 105.3 * 99.5 * 96.4 * 102.4) /1004
= 112.2 percent
The following sections show the different methods by which this calculated CPF of 112.2
percent may be limited.
Limiting the Overall Lot CPF
The agency may choose to limit the overall lot pay factor to
an agency-chosen subjective value. For our example, let's assume the agency
feels that it cannot pay more than 106 percent of the bid price due to budgetary limits.
Therefore, the calculated lot CPF of 112.2 percent would be limited to the
agency-chosen 106-percent value. For this case, the contractor would then receive a
6-percent incentive payment for the project.
Limiting Individual AQC Pay Factors
Another approach for limiting pay factors for budgetary
purposes is to apply limits to the individual AQC pay factors. For our example,
let's assume that each of the individual AQC pay factors is limited to 103
percent. Table 11 shows a comparison of the individual AQC pay factors and resulting
overall lot CPF's for both cases of with and without applied AQC limits.
Table
11. Example of limiting individual AQC pay factors (CPF calculated using the product
method).
AQC |
Individual AQC Pay Factors |
Without Limits |
All Limited to 103% |
Concrete Strength |
108.5 |
103.0 |
Slab Thickness |
105.3 |
103.0 |
Entrained Air Content |
99.5 |
99.5 |
Initial Smoothness |
96.4 |
96.4 |
Percent Consolidation |
102.4 |
102.4 |
Calculated Lot CPF |
112.2 |
104.2 |
Using the 103-percent individual AQC limits, the overall lot CPF is then calculated to
be 104.2 percent. For this case, the contractor would then receive a 4.2-percent
incentive payment for the project.
|