September/October
2002
Toledo's
New Signature Structure
by
Adrian Ciolko and Armin Mehrabi
A new
$220 million bridge in Toledo, OH, features a one-of-a-kind design.
Once completed, the Maumee River Crossing will be the second tallest
structure in Toledo and a stunning addition to the city's skyline.
What's more, the bridge's design integrates several unique new features
of cable-stayed technology.
The bridge
will span 373 meters (1,225 feet) with a single soaring 123-meter
(403-foot) pylon inlaid with shatter-resistant glass on each of its
four sides. During the day, the glass will reflect the skyline of
Toledo. At night, the reflective surface will be backlit with dramatic
lighting arrays capable of changing color displays.
Groundbreaking
for the span took place on June 17, 2002, and the Ohio Department
of Transportation (ODOT)the owner of the project expects construction
to be completed by June 2006. The concrete superstructure's distinctive
appearance is already developing community pride in Toledo, but it's
the stay cable technology advances that are catching the attention
of engineers.
"The
[Maumee River Crossing's] unique stay cables serve as a notable structural
design milestone," says Richard Martinko, district deputy director
of ODOT. "This is the most expensive project ever undertaken
by ODOT, and we are very pleased that testing has been so successful."
Photo
by: Figg Bridge Engineers
|
|
Rendering
for the new Maumee River Crossing bridge.
|
Overcoming
Skepticism
Since
the mid 1980s, when the construction of cable-stayed bridges in North
America accelerated, owners, designers, contractors, and the post-tensioning
industry have focused on design improvements in stay cables. Among
the innovations were non-bond socket, wedge-only anchorages; two epoxy
coating variants for seven wire strand; continuous saddle-over-pylon
cables; elimination of cementitious grout protection; incorporation
of greased and sheathed strand; individual strand-based cable stressing
procedures, and end-to-end multi-barrier corrosion protection systems.
Photo
by: Steve Lemieux-Jordon, Evanston Photographic
|
|
Full-scale
cradle test frame.
|
All the
innovations were put through full-scale fatigue tests between
1991 and 2000. The testing generated concerns about two of the innovations.
First, concern about several premature, corrosion fatigue ruptures
in tests of epoxy coated strand stays cast doubt on the advantages
of epoxy coating corrosion protection. Second, fretting fatigue failures
of grouted, uncoated strand saddle-type stay tests threatened the
potential for owner cost savings of continuous-over-pylon cables.
Considering
these findings and the needs of the Toledo community, the Ohio DOT's
bridge engineers—Figg Bridge Engineers—proposed and designed
a stay cable system for the Maumee River Crossing featuring:
- Cables
50 percent greater in diameter and strength than on any other bridge
- An
unbonded saddle (or cradle) design over the pylon
- Configuration
of a 373-meter (1,225-foot) span superstructure incorporating just
20 continuous-over-pylon cables and 40 anchorages
- Nested
corrosion protection systems using epoxy coated strand and continuous
external stainless steel sheathing over the
saddle
- A
novel cradle system that precludes strand-to-strand contact and
wear, using individual stainless steel tubes installed in the grout-filled
cradle pipe
In September
2000, the design engineers and ODOT program management consultants
HNTB/Parsons Brinckerhoff contacted Construction Technology Laboratories,
Inc., (CTL) to provide input on validating the Maumee River Crossing
stay cable design. The goals were to diminish ODOT's risk of adapting
unproven techniques, satisfy Federal Highway Administration (FHWA)
acceptance criteria, and resolve testing and constructability challenges.
The testing laboratory agreed to conclude testing within 11 months,
by the end of November 2001.
On a
parallel path, ODOT selected and contracted DSI-USA, Inc., to provide
the stay cable system components for the bridge and the prototype
cables for the testing program. The unusually complex and comprehensive
design prototype validation program encompassed four full-scale tests
of stay cables, three of which were larger than any others tested
in the world, and two of which required timely design and construction
of major new test fixtures.
The test
program goals included:
- Verifying
that the critical load transfer from stay cable to the pylon will
in fact occur during construction
and over the bridge's service life, as assumed in the engineers'
design
- Affirming
that the 82-, 119-, and 156-strand Maumee River Crossing stays can
provide appropriate fatigue endurance and strength
- Confirming
that after simulated damage resulting from a two-million-cycle cable
fatigue test, the corrosion protection system will still function
- Assuring
the full-scale fatigue performance and durability of the 119-strand
cradle design
Test
Results
The unique
design, extraordinary testing requirements, and tight schedule demanded
constant interaction among representatives of the funding agencies
and design, manufacturing, testing, and project management firms.
The importance of questions about the unprecedented design necessitated
new procedures. Challenges in the test setups and the manufacture
of test specimens were substantial, requiring constant interaction
and coordination.
Full-scale
testing was to represent actual construction as closely as possible.
The test program included material, production, and acceptance testing
for stay cable components, plus fatigue and strength testing of full-scale
cable assemblies. To better describe the performance of the cables
and cable components, the program
incorporated single-strand axial, flexural, and friction testing;
cable anchorage leak-tightness testing; and strand-coating and cable-sheathing
abrasion tests.
Photo
by: Teymour Manzouri, CTI
|
|
Entry
points for epoxy coated strands at cradle pipe. Concern for
excess bending and fretting damage at the entry points created
a need for the cradle test.
|
The new
cable system design relies on the friction between the strands and
the stainless steel sleeves within each cradle to transfer differential
forces in two legs of each cable during and after construction. A
minimum coefficient of friction of 0.5 was needed to satisfy this
condition. Uncertainty on this issue was considerable, and the whole
project would have been in jeopardy if this design parameter could
not be verified successfully. Therefore, rigorous measurement of the
coefficient of friction between epoxy coated strands and stainless
steel sleeves was essential.
To that
end, the laboratory designed a new strand-friction testing procedure
and a new test setup. A minicradle-based test system was constructed
using a concrete block and five stainless steel sleeves formed to
specific radii and exit angles. Friction of the tensioned strands
with respect to the sleeves was measured before, during, and after
two million cycles of stress variation. Once the tests verified the
existence of an adequate coefficient of friction, the four full-scale
tests commenced.
Photo
by: Steve Lemieux-Jordon, Evanston Photographic
|
|
New
49-mega-Newton (11-million-pound) capacity stay cable test fixture
(cradle fixture in background).
|
New
Axial Fixture
The Post-Tensioning
Institute's (PTI) Recommendation for Stay Cable Design, Installation,
and Testing, 2000 edition, served as the basis for the full-scale
tests. Three full-size cables with 82, 119, and 156 strands needed
to be tested in axial tension for fatigue and maximum-strength requirements.
Acceptance criteria encompassed limiting wire breakage to 2 percent
of the wire in the cable at the culmination of fatigue testing, followed
by the cable successfully withstanding a proof load of 95 percent
of nominal strength. One of the cables also needed to undergo water
leakage or dunk testing after completion of the fatigue cycling to
prove the water tightness of the anchorage zone. A full-scale, axial-flexure
(cradle) test also had to be conducted on one of the cable sizes.
The testing
laboratory's existing axial test fixture was used for fatigue and
strength testing of an 82-strand cable and fatigue testing of a 119-strand
cable. These tests met acceptance criteria set forth by PTI.
The 119-strand
cable underwent leakage testing. The procedure was first introduced
in the PTI Recommendations in the year 2000. The testing laboratory's
team designed and assembled a test setup consisting of a standing
tank and accessories for applying a 3-meter (9.8-foot) head of red-dye
solution on an anchorage zone of the 119-strand cable after it had
gone through the fatigue testing cycles. The leakage test indicated
the satisfactory performance of the sealing system used in the cable
anchorage zones.
Photo
by: Teymour Manzouri, CTI
|
|
The
156-strand stay cable anchorage required new test fixture design
and installation.
|
The demands
of the axial testing for the 156-strand cable were, however, far above
and beyond the existing testing resources. Strength testing this cable
required a loading capacity of 40.5 mega Newtons (9.1 million pounds).
The project team designed and manufactured a new testing fixture capable
of applying repeated (fatigue) loads of up to 22 mega Newtons (4.9
million pounds) and static loads of 49 mega Newtons (11 million pounds).
The custom-made, center-hole hydraulic ram for this new fixture alone
weighed 125 kN (28,000 pounds). The extraordinary hydraulic demand
of this system was met by an independent dual pump with a maximum
flow rating of 530 liters (140 gallons) per minute combined with an
oil accumulation system.
The new
test fixture was supplemented by another testing frame for applying
lateral contact force between a stainless steel cover (sheathing)
pipe and the perimeter strands in the cable. This procedure was intended
to assess the potential occurrence of epoxy coating damage in the
perimeter strands where they come into contact with weld beads joining
stainless steel cover pipe segments. The 156-strand cable prototype
also successfully met the fatigue and static test criteria of the
PTI Recommendations as well as the State's requirements for epoxy
coating abrasion.
Photo
by: Teymour Manzouri, CTI
|
|
The
45-ton cradle block is hoisted onto the test fixture.
|
Photo
by: Teymour Manzouri, CTI
|
|
The
119-strand cable anchorage shown with 3-million-pound capacity
test-control load cell.
|
Full-Size
Cradle Test Frame
The biggest
challenge in the testing program was the axial-flexural testing
of a 119-strand cable, incorporating a full-scale prototype of a new
cradle design, encased in a post-tensioned
concrete segment representing
the bridge pylon. The outcome of this test will contribute the most
to future advances in stay cable design.
The test
is to simulate the fatigue performance of the curved portion of a
cable in the pylon. Major concerns about the new cradle design included
fatigue due to the bending stress induced in the strands near the
exit point from the cradle and potential damage to strand epoxy coating
due to fretting action.
A new
self-supporting testing frame capable of transferring about 13 mega
Newtons (2.9 million pounds) of force to the cable specimen during
two million cycles of loading was needed. The new frame was designed
of steel sections in a double-truss structure. This frame supported
two ends of the cable specimen. It was used as a reaction for hydraulic
rams that push vertically against a 45-ton concrete block. The block
represents a segment of the pylon structure at the cradle pipe on
the bridge. Fifty tons of steel and 100 tons of concrete were used
to construct the test fixture. The steel truss frame was fabricated
in segments and shipped to the testing laboratory for assembly and
erection. Two load cells at the ends of the cable specimen and several
displacement transducers were used to control loading and collect
data.
The test
cable assembly and installation provided insights into cable
erection for the bridge construction. In particular, the stay cable
supplier's proposed individual strand stressing procedure was evaluated.
The process encompasses simultaneous stressing at both ends hydraulically,
using coupled "monostrand" jack arrays. The procedure was
evaluated
and compared against the
testing laboratory's load cells located at the opposing anchorages
of the 17-meter (56-foot)-long stay
prototype.
Once
stay installation was completed, the fatigue test began and lasted
for 2 months. At its conclusion, the strands were extracted from the
cradle and inspected thoroughly. No wire breaks were observed, and
no major damage to the strand and the cradle pipe was detected.
In a
footnote to the lessons from the 119-strand full-scale cradle test,
the results of the strand-by-strand cable stressing in the laboratory
prompted enhancements in the construction techniques for the Maumee
River Crossing. Also, ODOT selected a new technique for measuring
cable force to monitor stay cables tensioning on site to supplement
the strand-by-strand cable stressing technique and assure the proper
development of forces in stay cables. For the first time in the United
States, a new laser technique for cable force measurement was written
into bridge construction specifications, offering an alternative to
monitoring hydraulic pressures or the lift-off method.
A non-contacting
laser-based method developed with FHWA Broad Agency Announcement funding
in 1997 will be used during construction in lieu of liftoff tests
using large, heavy, center-hole jacks. Utilization of the lower-cost
and more accurate method of force measurement will not only reduce
the cost and duration of construction, but also will provide accurate
and timely measurements.
Photo
by: Teymour Manzouri, CTI
|
|
Strand
installation before 119-strand full-scale cradle test.
|
Milestones
and Achievements
The contract
bidding schedule for stay cable delivery and the bridge construction
was contingent on the progress and success of the test program. Delays
created by a need to repeat tests, shortages in materials for the
stay cable vendor, or difficulties with the laboratory equipment would
directly and substantially impair schedules for contract letting.
In fact, the tests were completed December 2, 2001.
In January
2002, bids were accepted for the bridge construction and soon thereafter
FruCon Construction Company was awarded the contract to construct
the bridge.
Lessons
Learned
Because
of the testing, ODOT and FHWA lessened their level of functional,
public safety, and contractual uncertainty related to using an innovative,
first-of-its-kind stay cable system. In addition, the bridge designer,
project management consultant, and stay cable supplier derived practical
insights from the full-scale cable fabrication process in the laboratory,
influencing their preparedness for managing stay cable supply and
bridge construction well before construction commenced.
Furthermore,
the bridge builder and stay cable erection subcontractor gleaned lessons
from the cable fabrication associated with the cradle pipe fabrication,
grouting, cable installation, and stressing systems. They also reaped
the benefits of a new cost-saving tool for cable stay alignment and
load monitoring. The stay cable testing consultant enhanced its technical
resources in the area of cable stayed design and construction, improving
its ability to assist future clients and the industry.
Adrian
Ciolko is vice president of the Structural Laboratory Division
of Construction Technology Laboratories, Inc., in Skokie, IL. Among
the many professional achievements of his 25-year technical and management
career, he directed the design and development of the CTL center for
studying and improving the fatigue performance of large-diameter bridge
cables. Since 1991, the center has validated design of stay cables
for 20 bridges constructed around the world. Additionally, he conceived
and oversaw adaptation of advanced laser-based nondestructive test
systems for structural evaluation of cable stayed and suspension bridges.
Ciolko collaborated with the FHWA and ODOT Maumee River Crossing Bridge
team leaders to conceive suitable validation criteria and methods
for the innovative cable stayed structure.
Armin
Mehrabi is a senior principal engineer with CTL and was the project
principal for the Maumee River Crossing Bridge Cable Testing Program.
He leads the company's long-span bridge engineering activities with
a focus on the use of innovative techniques for bridge evaluation
and inspection. In 1997, Mehrabi was chosen as one of Engineering
News-Record magazine's Top 25 Newsmakers for his contribution
to the development of nondestructive techniques for cable stayed bridge
evaluation. He received his master's degree and doctorate in civil
engineering from the University of Tehran and the University of Colorado
at Boulder, respectively.
Other
Articles in this issue:
Walking
the Safety Walk
The
Bridges That Good Planning and Execution Rebuilt
War
on Weeds
Red
Lights Mean Stop
Bridge
Rebuilt on the Fast Track
Stop.
You're Going the Wrong Way!
Toledo's
New Signature Structure
Spotlight
on Safety
Take
Me Home, Country Roads
Superpave
Comes of Age