July/August 2003
The Road to Streamlining
by Kreig Larson
An indepth look at the NEPA process and ways to expedite it.
The National Environmental Policy Act of 1969 (NEPA) marked the beginning
of the environmental review process for all Federal actions, including
the construction of highway and bridge projects falling under the U.
S. Department of Transportation and Federal Highway Administration (USDOT/FHWA).
According to the Congressional Research Service CRS Report for Congress:
Environmental Streamlining Provisions in the Transportation Equity Act
for the 21st Century: Status of Implementation, "Numerous
stakeholders have expressed long-standing concerns about delays and
increased costs for major highway construction projects, which are often
attributed to the environmental review process required by the National
Environmental Policy Act (NEPA, P.L. 91-190). The substantial amount
of time and funding often needed to prepare such documentation for highway
projects has been an ongoing issue at the State and local level for
many years." This perception is especially the case when the process
involves an environmental impact statement (EIS), which is the most
comprehensive and time-consuming environmental documentation required
under NEPA.
 |
| This construction
work at an interchange in Las Vegas is part of an improvement of
US 95 in Nevada, a project where environmental streamlining worked
effectively. Photo courtesy of Nevada DOT. |
"Good construction projects must move forward promptly, and those
unsuited because they would be harmful to the environment, or do not
enjoy community support, should quickly and decisively be taken off
the drawing board," says FHWA Administrator Mary E. Peters. "To
ensure environmental streamlining and stewardship, efficient environmental
review processes are a priority."
To this end, Section 1309 of the Transportation Equity Act for the
21st Century (TEA-21) in 1998 directed USDOT/FHWA to "develop and
implement a coordinated environmental review process" for highway
construction projects. One of the key elements of the coordinated process
is the establishment of agreed time periods for the conduct of project
analysis, review, opinion, decision, and approval. Section 1309 instructs
that review processes be applied to projects requiring either the preparation
of an EIS or an environmental assessment under NEPA.
More recently, in September 2002, President George W. Bush signed an
Executive order requiring Federal agencies to promote environmental
stewardship in the Nation's transportation system and expedite environmental
reviews of high-priority transportation infrastructure projects. Similarly,
both bodies of Congress have introduced bills designed to streamline
the environmental process and expedite project delivery.
But amid the effort to streamline the NEPA process, one critical piece
of the puzzle had been missing. The direct effects of NEPA on transportation
projects—in terms of time and cost—had not been explored
in depth. Without knowing the impacts of NEPA on overall project delivery,
there is no yardstick to measure the success or failure of past and
future streamlining efforts. Without understanding what has served historically
to expedite or slow the NEPA process, effective means of streamlining
cannot be identified.
To remedy this lack, FHWA's Office of Project Development and Environmental
Review initiated a series of studies to determine how NEPA integrates
into the overall process of project delivery and to assess the impacts
of the NEPA process on the timing and cost of project delivery. The
answers now are becoming clear.
Defining the NEPA Baseline
One of the studies, undertaken in 2000, provides a better understanding
of the impacts of the NEPA process on the total time involved in completing
a Federal-aid highway or bridge project. Previously, the portion of
time and cost attributed to NEPA requirements versus other potential
sources of delay within the overall project delivery process—such
as funding shortages, changes in design, contractor delays, lawsuits,
and injunctions—had not been well understood. Ultimately, the
study aimed to provide a baseline for comparing current and future environmental
streamlining efforts within the NEPA process.
The baseline study focused on projects that have been constructed and
are fully operating. In total, 100 constructed surface transportation
projects with environmental impact statements completed in the 1970s,
1980s, and early 1990s were selected for analysis.
"Compared to previous studies of its kind, the baseline study
offered a more comprehensive and less subjective approach to assessing
the NEPA process," says Ken Hess, general manager at The Louis
Berger Group, Inc., which conducted the study with FHWA. "The NEPA
baseline study was designed to be reflective of real data that are as
temporally and geographically diverse as possible."
Key Findings of the Baseline Study
A number of conclusions came to light. The study confirmed a positive
relationship between the length of the NEPA process and the length of
the total project development process:
- The completion of the NEPA process accounted for approximately 28
percent of the overall time for the project development process.
- The average time to complete an EIS for a transportation project
was about 3.6 years.
- The mean length of time for the completion of a project was approximately
13.1 years.
- The average time to prepare an EIS under NEPA ranged from a low
of 2.2 years in the 1970s to a high of 5.0 years in the early 1990s.
The project also identified a number of requirements found to influence
the length of time required to prepare an EIS. Requirements include
Section 404 permits for impacts on wetlands and Section 4(f) provisions
pertaining to public parks, recreation lands, wildlife and waterfowl
refuges, and historic sites. Two of the requirements appeared to have
a statistical relationship to time required to prepare an EIS. It should
be noted, however, that another factor—the number of agency meetings
held—likely does not have a causal relationship with the time
required to prepare an EIS, but rather is more indicative of the complexity
of the project.
The full report, Evaluating the Performance of Environmental Streamlining:
Development of a NEPA Baseline for Measuring Continuous Performance,
is available at www.fhwa.dot.gov/environment/strmlng/baseline/index.htm.
One Step Further: The NEPA Baseline Phase II
The success of the NEPA baseline study in describing the factors influencing
the duration of the NEPA process prompted another investigation building
on the conclusions of the initial study. The aim of the followup research,
Evaluating the Performance of Environmental Streamlining: Development
of a NEPA Baseline for Measuring Continuous Performance Phase II,
known as the NEPA Baseline Phase II study, was to determine if the initial
study results were repeatable, or if a comparative assessment could
be made between the two sets of results.
"The Phase II research expands the development of the baseline
NEPA condition to include the more recent past," says Hess. "In
this way, a comparison can be made between the earlier and later periods
under study."
Although the purpose of the study was the same as its Phase I predecessor,
Phase II differed in several important ways:
- Phase II focused only on the NEPA process itself instead of the
relationship of NEPA to the overall project delivery process.
- Phase II focused on the two factors identified in Phase I as having
a statistical relationship with the length of time of the NEPA process.
- Phase II eliminated the earlier requirement that a project must
be completed and open for use in order to be considered and instead
included all 244 highway projects requiring environmental impact statements
completed between 1995 and 2001.
- Phase II improved upon the "start" date of the project
development process, defining it by the Notice of Intent publishing
date and thus minimizing subjectivity in the discernment of the dates.
"In combination, the two phases of research essentially tell the
whole story since the inception of NEPA," says Hess. "The
studies provide a benchmark and a means to identify whether FHWA streamlining
efforts are making a difference—today and in future."
Primary Requirements Affecting the Length of Time for the NEPA
Process (1970s-1990s)
| Requirements and Other Factors |
Average Years Required
To Complete EIS |
Section 404 Permit (Wetlands) |
Needed |
4.3 |
Not needed |
2.4 |
Section 4(f) Approval
(Public Lands) |
Needed |
4.7 |
Not needed |
2.8 |
Number of Agency Meetings |
< 3 |
4.5 |
| >3 |
2.4 |
Preliminary Findings of The Phase II Study
Although the NEPA Baseline Phase II study currently is undergoing final
review, preliminary results are available. Based on the sample projects
analyzed, the Phase II study identified the following trends during
the 1995-2001 period:
- The average time for preparation and completion of an EIS was 5.1
years, while the median length of time was 4.7 years.
- Projects undertaken in the former FHWA Region 4 (Southeastern States)
exhibited the highest mean value (5.6 years of actual NEPA process
time) related to the time to complete the EIS process.
- Former Regions 8 (Rocky Mountain States) and 6 (South Central) exhibited
the lowest mean values of time (3.8 years) during the study period.
- Although not found to be statistically significant, the requirement
of performing a Section 4(f) evaluation for a project may extend the
length of the NEPA process by 5 to 7 months, depending on the set
of mean values used.
- FHWA's Office of Project Development and Environmental Review expects
to post the final study on its Web site by June or July 2003. The
study will be available at www.fhwa.dot.gov/environment/strmlng/baseline/index.htm.
Successful Examples of Environmental
Streamlining
Durations of Environmental Impact Statements in Months |
 |
Case Studies: Lessons Learned
To assist in future environmental streamlining efforts, FHWA identified
eight examples of highway projects that demonstrate successful measures
in expedited environmental reviews. The Records of Decision for these
eight case studies were approved between 1998 and 2000.
The case studies illustrate that the EIS process can flow at an expedited
rate for a variety of project types and diverse settings. What is most
interesting about these procedures and techniques is that they are commonsense
approaches and do not involve any cutting-edge technologies.
One tip is to capitalize on the extensive project development and analysis
performed in studies prepared prior to initiating the NEPA process.
Another is to initiate NEPA-type studies in advance of the formal NEPA
process. A third technique is to promote interagency coordination and
cooperation via formal or informal memoranda of understanding. Implement
early and continuous public involvement programs in an aggressive fashion.
Pursue high-level political support for the project. Develop and use
State-initiated streamlining programs, and develop procedures for facilitating
document preparation and review.
"If properly implemented, the completion of a NEPA EIS does not
have to be overly lengthy," says Dr. Tianjia Tang, former project
manager for the John Young Parkway project and currently highway engineer
and air quality specialist at FHWA's Southern Resource Center. "It
can be expedited for all transportation projects by using various procedures
and techniques." (See "Lessons Learned"
in Public Roads May/June 2003 issue for an article about streamlining
the John Young Parkway.)
The major findings of the research will be presented in a lessons learned
section of the final report, which will describe the procedures and
techniques that have streamlined the EIS process in one or more of the
cases studied. The report of the eight case studies of successful environmental
streamlining is scheduled to be available on the FHWA "Environmental
Streamlining" Web site (www.fhwa.dot.gov/environment/strmlng/index.htm)
in July 2003.
 |
| FHWA selected the US
95 improvement project in Nevada as one of eight case studies identifying
effective means of streamlining the NEPA process. In this photo,
a crane is drilling holes for pilings and laying the foundation
work for a new interchange. |
National Survey: Measuring Performance Of the NEPA Process
As part of its response to the Section 1309 charge to implement a streamlined
environmental process, FHWA contracted with The Gallup Organization
to conduct a survey of personnel in transportation and resource agencies
to ascertain the perceptions of key participants in the transportation
project development process nationwide. The survey will be available
in summer 2003. Specifically, the survey will explore how stakeholders
in the NEPA process view the duration of the process, the quality of
the environmental work and services performed by their counterparts,
and areas where improvement may be needed.
Based on a pilot survey, preliminary results suggest that respondents
exhibit high rates of satisfaction with the collaborative aspects of
the process. The pilot also found that survey participants generally
are satisfied with the level of participation by agencies, timely response
to requests, and communications. However, a relatively small number
of respondents felt that interagency communications are characterized
by the provision of timely updates on progress or a willingness to compromise,
indicating that these may be problem areas. Whether these trends will
be confirmed in the national survey remains to be seen.
 |
| The NEPA project development
process ensures that efforts are made to preserve and enhance cultural
and historic resources near transportation projects, such as this
historic structure in Atlanta. |
 |
| Environmental streamlining
is not only about achieving timely decisions for transportation
facilities; it is also about environmental stewardship, as demonstrated
by this bridge in Chicago, which incorporates environmental landscaping
into its design. |
 |
| Transportation projects
have the potential to improve the quality of the natural, social,
and built environments, as shown by this parking lot in Chicago,
which integrates grass, flowers, and other types of vegetation for
aesthetic sensitivity. |
Moving Forward
The concept of streamlining the NEPA environmental review procedures
is not new. As part of its implementing regulations for NEPA prepared
in 1978, the Council on Environmental Quality directed agencies to engage
in cooperative consultation, integrate the NEPA process into early project
planning and review activities, identify significant issues early in
the process, and place appropriate time limits on the EIS process.
Yet, after more than 30 years of NEPA compliance, environmental streamlining
procedures for federally funded highway projects are applied and implemented
on an ad hoc basis. Procedures used to advance projects through the
NEPA process vary, to some extent, by FHWA division office or even on
a project-by-project basis. The need for a more systematic and efficient
approach for environmental review is apparent.
Thanks to public will and government action, environmental streamlining
has come to the forefront. Quantitative analyses of the NEPA project
development process and practical applications of practices to facilitate
a more streamlined process provide useful contributions to further understanding
of the time involved in the NEPA process and how it can be reduced.
These studies also help with evaluating the performance of streamlining
efforts, refining that evaluation, and determining whether opportunities
exist to improve the overall process, in spite of other non-NEPA-related
factors that may slow project delivery. With a firmer understanding
of where we stand today, the NEPA project development process can and
will be more effectively streamlined tomorrow.
 |
| Cecil Vick of FHWA
(left) and Claiborne Barnwell of the Mississippi DOT (center) discuss
proposed roadway alignments with local business owners during public
hearings held prior to construction of the Airport Parkway and MS
25 connectors—one of the eight FHWA case studies that illustrates
how the EIS process can move at an expedited rate. |
Kreig Larson is a project development specialist with
the FHWA Office of Project Development and Environmental Review in Washington,
DC. He is the technical representative overseeing a number of research
projects on environmental streamlining for that office and also is engaged
in other FHWA streamlining activities. Prior to joining the FHWA headquarters,
Larson was employed as an environmental planner for the California Department
of Transportation. He holds a bachelor's degree in soil and water science
from the University of California, Davis, and a master's in urban planning
from the University of Southern California.
For more information, contact Kreig Larson at 202-366-2056.
Other Articles in this issue:
A Natural Balance
Nurturing an Environmental Perspective
The Road to Streamlining
Executing the Executive Order
A New Approach to Road Building
Living with Noise
Bikeways and Pathways
Centering on Environmental Excellence
New Life for Brownsfields
Air Quality and Transportation
Solutions from the Sunbelt
Reviews on the Fast Track