Prefabricated elements and systems accelerate construction
of bridges to hours or days instead of months or years.
In February 2003, more than 200 bridge professionals viewed
successful projects at the National Prefabricated Bridge Elements
and Systems Conference cosponsored by the American Association
of State Highway and Transportation Officials (AASHTO) and the
Federal Highway Administration (FHWA). The presenters shared visions
of bridges built in hours or days as opposed to months or years.
Bridge engineers from 35 States and representatives from AASHTO
and FHWA, professional associations, contractors, suppliers, and
academia listened as the speakers described projects that met
the need of State transportation agencies to “Get In, Get
Out, and Stay Out.”
 |
| Two cranes lift a
preconstructed unit into place on the James River Bridge in
Richmond, VA. Photo: URS Corporation. |
The Nation's bridges have a median age of 40 years, and
today many structures need reconstruction. But increased traffic
and urban congestion demand outside-the-box thinking to accelerate
construction. In 2001 the AASHTO Technology Implementation Group,
known as the TIG, chose prefabricated bridge elements and systems
as one of the innovative technologies that promises the highest
payoff. (Others include accelerated construction and intelligent
traffic systems in work zones.) To encourage implementation of
bridge prefabrication, the AASHTO group sponsors workshops, provides
speakers for related conferences and other meetings, and publishes
a Web site (www.aashtotig.org) that includes information on a
number of prefabricated bridge projects that have been constructed
to date.
In addition, FHWA, through its Innovative Bridge Research and
Construction program and the Resource Center, champions prefabrication
for accelerated construction. “Our vision is to get out
in front of the bridge deterioration curve with accelerated construction
such as prefabrication and stay there,” says Tom Saad,
structural design engineer, FHWA Resource Center, Chicago. “FHWA
bridge engineers will partner with States, industry, and academia
to develop and implement technologies that produce more durable
highway structures that can be constructed in a fraction of the
time of conventional structures.”
The AASHTO group and FHWA are encouraging this technology because
of the many advantages for bridge owners, engineers, builders,
and the traveling public. First, use of prefabricated elements
or systems minimizes traffic impacts. For example, contractors
can perform time-consuming formwork assembly, concrete casting,
and curing offsite in a controlled environment away from traffic.
Prefabricated bridge designs are more constructible because the
offsite work reduces time onsite dealing with constraints such
as heavy traffic, extreme elevations, long stretches over water,
and tight urban work zones.
Safety improves because prefabrication reduces the exposure time
for workers and the public who travel through construction zones.
Prefabricated elements and systems work well to accelerate both
reconstruction and new construction. Prefabrication and shipment
of components to the job site also reduce impacts on the environment.
Finally, prefabricating takes elements and systems out of the
critical path of the project schedule. The fabricator can take
as much time as needed to produce a quality component or system
in a controlled environment. Improved quality translates to lower
life-cycle costs and longer life.
With traffic control running anywhere from 20 to 40 percent of
construction costs and user delays priced at thousands of dollars
per day in heavy traffic areas, States and owners will realize
cost savings from accelerated bridge construction. Then as the
technology becomes standard practice, costs will decrease.
The conference showcased a wide range of bridges of all sizes.
Five outstanding prefabricated bridges presented here are Lake
Ray Hubbard in Dallas, TX; James River in Richmond, VA; Baldorioty
de Castro Avenue in San Juan, Puerto Rico; Mitchell Gulch in Castle
Rock, CO; and Reedy Creek Bridge in Orlando, FL.
Lake Ray Hubbard, Dallas, TX
With Texas containing one-twelfth (approximately 49,000) of the Nation's bridges, the Texas Department of Transportation
(TXDOT) has experimented with prefabricated elements for decades.
The agency now is expanding its use of prefabricated elements
to include entire systems. On the eastbound two-lane Lake Ray
Hubbard Bridge, the contractor took one look at the power lines
just 14 meters (45 feet) from the work zone and decided that the
combination of a rocking barge and a crane's mast arms
posed an unacceptable risk. Because the bridge's 43 pier
caps had repeating elements, prefabrication could be cost effective.
 |
| For this precast
bridge in Lake Ray Hubbard in Dallas, TX, prefabrication was
quick and cost-effective. |
 |
| Workers lower a precast
bent cap at Lake Ray Hubbard. |
TXDOT engineers designed the caps that extend between the supporting
columns, and the contractor built a portable trestle to construct
the 1,312-meter (4,300-foot)-long bridge. The defined work area
from the trestle placed every component in the critical path so
prefabricating the caps was crucial to maintaining the schedule,
according to Tracey Friggle, TXDOT assistant director of construction
for the Dallas District and project manager. “Without the
prefabricated pier caps, the work would have taken us an extra
year,” Friggle explains. “Instead of 8 to 9 days
to form, tie, pour, and cure each cap, we took 1 day to set each
one.”
To anchor the precast caps to the existing columns, crews used
vertical grout sleeves cast into the caps and then pumped a high-strength
grout into the sleeves to complete the connection.
James River, Richmond, VA
“Today engineering is the easy part, while traffic
is a big consideration,” says Malcolm Kerley, Virginia
DOT's chief engineer for program development. “The
I-95 bridge over the James River carries 110,000 vehicles
a day, so we wanted to open it to the public as soon as possible.”
 |
| For the James River Bridge, the
Virginia DOT post-tensioned this hammerhead pier cap to carry the construction loading. |
After considering public input, VDOT closed the lanes from 7
p.m. to 6 a.m. Sundays through Thursdays for construction. The
agency also requested A plus B bidding, with “A”
being the unit price and “B” the number of days
valued at $30,000 per day. VDOT did not consider any bids over
220 days. The winning contractor bid 179 days and ultimately finished
in 140 days. For each day under 179, the contractor received a
$30,000 bonus, and for each day over was to have been charged
$30,000. Because daytime opening was critical, VDOT established
a schedule of disincentives for time beyond 6 a.m. in restoring
all traffic lanes. Fines ranged from $5,000 for failure to open
at 6 a.m., an additional $10,000 if not open by 6:15 a.m., $35,000
if not open by 6:30 a.m., and so on to a cumulative disincentive
of $250,000 for remaining closed until 6 p.m.
For most of the 101 spans, the contractor erected preconstructed
composite units consisting of a 222-millimeter (8.75-inch) deck
over steel plate girders. A nearby casting yard precast the units.
Overnight, the work crews removed the old bridge span, prepared
the gap for the new preconstructed composite unit, set the unit
in place, sealed slab joints, and post-tensioned slabs transversely.
Baldorioty de Castro Avenue Bridges, San Juan, PR
This Puerto Rico project, which was highlighted at the
conference, demonstrated how to deliver urban bridge projects
in weeks instead of months or years using prefabrication methods.
The contractor, with exacting sequencing, pieced together the
two totally prefabricated overpasses in just two weekends.
To ease congestion on a San Juan road that carries more than
100,000 vehicles per day, the engineering contractor designed
the prefabricated overpasses at two intersections for the San
Juan Department of Transportation and Public Works. The construction
contractor erected two 275-meter (900-foot)-long and two 214-meter
(700-foot)-long totally prefabricated bridges in two stages.
On the first weekend, the crews drove piles, cast the footings
in place, and then installed asphalt over their work. The next
weekend the crews uncovered the footings and erected and post-tensioned
the prefabricated substructure components. After the crews completed
the first two substructures, they set the 30.5-meter (100-foot)-long
superstructure span in place, complete with seven box beams, wearing
surface, and parapets.
 |
| The precast bridge
structure in San Juan, Puerto Rico, shown in an illustration,
was erected from the ground up in just 21 consecutive hours.
|
Two work crews erected the remaining spans simultaneously from
the center span toward each end, post-tensioned each transversely,
and then placed an asphalt overlay. To complete the process, the
crews constructed retaining walls with select fill on the approaches.
The first 275-meter (900-foot) overpass was ready for traffic
in 36 hours, and the second overpass in just 21 hours.
“Commuters traveled at grade on Friday evening, and by
Monday morning they were traveling over the new overpasses,”
says John Dick, conference presenter and structures director for
the Precast/Prestressed Concrete Institute in Chicago.
Mitchell Gulch, Castle Rock, CO
Plans by the Colorado Department of Transportation (CDOT)
specified a cast-in-place box culvert to replace a 49-year-old
deteriorated timber structure rated as one of Colorado's
10 worst bridges. But when the Denver-based contractor examined
the long grade leading down to the Mitchell Gulch Bridge and the
resulting dangerous detour, he decided that he could replace this
12-meter (40-foot)-long bridge in a weekend instead of a couple
of months.
On a previous project with the same conditions, the driver of
an 18-wheeler coming down the hill had lost brakes on 14 of the
wheels, crashed through the barricades, and killed two employees.
Two contractors approached CDOT with a value design/construction
engineering proposal to replace this bridge in a weekend within
the same cost parameters as a conventional project. Plus this
plan would minimize inconvenience to the 12,000 daily commuters,
who had no reasonable alternative route.
 |
| The contractor installed
the precast components for the Mitchell Gulch Bridge in one
weekend. |
The prefabrication manufacturer from Littleton precast 90 percent
of the new bridge, including substructure units such as wing walls
and abutment walls, along with the more common precast deck units
to enable rapid assembly. The contractor prepared steel piles
to support the precast substructure units ahead of time. The contractor
and engineering manager orchestrated every minute of the weekend
with contingency plans such as backup equipment servicing, leaving
little to chance. The contractor made field adjustments on several
prefabricated elements.
At 7 p.m. on a Friday, the contractor rerouted traffic and began
dismantling the old structure. By Saturday at 1 a.m., crews had
placed abutments and wing walls, and welded them to the steel
piles and to each other. When a fiber-optic line was encountered,
the construction team adjusted the angle of the wing walls to
accommodate the line. At the same time, crews rehabilitated the
streambed with riprap. On Saturday afternoon, after placing the
flowable fill behind the abutment walls, the team lowered, grouted,
and post-tensioned the precast girders. Work stopped at 11 p.m.
so the crew could rest and then resumed Sunday at 7 a.m. The crew
completed the earthwork, backfilling, and asphalt paving on the
bridge and approach, opening the structure by 5 p.m. in a record
37 hours of actual construction.
Reedy Creek Bridge, Orlando, FL
To mitigate the environmental impacts of heavy equipment on the Reedy Creek wetlands at the Animal Kingdom Entrance to
Disney World, Walt Disney Imagineering committed to a top-down
construction process using precast pile caps, prefabricated deck
planks, and steel pipe piles. The Reedy Creek Bridge has two parallel
305-meter (1,000-foot)-long bridges widening from 13-meters (43
feet) for the first 73 meters (240 feet) to 16 meters (53 feet)
wide for the remainder. Utilities cross Reedy Creek in a 4.3-meter
(14-foot) gap between the two bridges.
 |
| The precast pile caps and deck panels at the Reedy Creek Bridge site. |
The selected contractor won the project with a design that resulted
in net savings of $950,000 on the $8.3 million project. The design
met Florida Department of Transportation standards, maintained
the bridge span and roadway deck configuration, reduced the number
of support piles, and simplified the precast pile caps. In addition,
the design used 2-meter (6-foot)-wide deck panels that are 381
millimeters (15 inches) thick at the center and 610 millimeters
(24 inches) thick at the ends instead of 457-millimeter (18-inch)
constant depth panels.
The contractor drove the steel piles and erected precast components
from a traveling erection platform. The 104 pile caps are identical
except for the length and number of conical holes (two or three)
for integration with the steel pipe piles. Shear keys between
panels and the reinforced concrete overlay are the only cast-in-place
concrete. Traffic barriers were slip-formed.
What Needs to Change?
These accelerated prefabricated bridge projects illustrate a
change in thinking from the traditional approach to a systems
approach that considers traffic impacts during the planning stage.
“Contracting procedures need to change to provide incentives
for contractors to build bridges rapidly,” Dick observes.
“Whether it's A plus B bidding or other incentive/disincentive
programs, the system has to change to encourage innovation.”
“To be cost-effective,” Rick Lawrence, president
of Lawrence Construction Co. from the Colorado project, adds,
“I need to build at least 10 bridges at a time, but the
State awards projects one at a time.” By grouping single-span
bridges, both the contractor and the State would realize volume
savings in materials and labor. Another option is the design/build
approach enabling the contractor to contribute practical ideas
for accelerating construction.
Although the States have reaped the rewards of accelerated construction
and superior quality with components produced in a controlled
environment, some details of this technology can still be improved.
Kerley cautions, “My concern is not with the quality of
the components but with the quality of the connections.”
Saad agrees, “We still need research on developing the
best practices for delivering this technology.”
Ian Friedland, FHWA bridge technology engineer adds, “Some
standards and specifications need to be evaluated for accelerated
construction.”
Looking to the future, Kerley says, “Through the AASHTO
TIG we're establishing a network in which one State shares
its success, and another State takes the idea and tweaks it for
its project.”
With the variety of prefabricated systems available, bridges
need not be “cookie-cutter” designs, but FHWA and
the States are developing standardized designs with modular systems
to replace the typical 50-year-old “bread-and-butter”
bridges that need replacing nationwide. FHWA's Bridges
of the Future initiative envisions a bridge with accelerated construction
time, adaptability to widening and other demands, and lower life-cycle
costs. Prefabricated bridge elements and systems are a step toward
this vision.