Using innovative fiber-reinforced polymer repairs to correct
distress in welded joints on aluminum sign structure trusses.
In the early 1960s, State departments of transportation (DOTs) began
using aluminum trichord overhead structures to support signs along
our Nation's highways. The advantages of using aluminum were
obvious. It is lightweight, costs less than steel, and is inherently
resistant to rusting. In 1994, however, the American Association of
State Highway and Transportation Officials (AASHTO) started to include
fatigue as a design factor for overhead signs.
“This development, combined with observations of cracking
and occasional structural failures in aluminum signs,” says
Chris Pantelides, professor of civil engineering at the University
of Utah, “alerted engineers to a potential life-threatening
problem that may exist in States throughout the country.”
Over time, wind forces create stresses on an aluminum structure,
eventually causing cracks to appear in the welded joints of the truss
diagonals. If these cracks are not discovered and repaired, a welded
joint eventually could fail and cause an aluminum diagonal to fall
onto the roadway. “These problems are surfacing in large numbers
now that many of these aluminum sign structures have been in service
for 30 years or more,” says Pantelides.
 |
| After many years in service,
aluminum trichord sign structures often develop significant cracks
and event complete failures in their welded connections, as shown
in this photo of a failing joint. Redundant connections in most
cases prevent pieces of the structure from falling onto the highway,
but signs with failing joints need to be repaired or replaced.
|
The consequences of a failed welded joint could be tragic, especially
on high volume roads where traffic moves continuously and at high
speeds beneath hundreds of aluminum overhead sign structures.
Fortunately, New York State DOT (NYSDOT) engineers, working with
private industry and a research team from the University of Utah,
found an inexpensive way to repair problematic structures to increase
their safe and useful lives. Using a fiber-reinforced polymer (FRP)
composite to wrap cracked joints, workers can restore the structural
integrity of a cracked joint to virtually the same strength as the
original aluminum weld. The cost of the material is minimal, and the
repair can be conducted in the field. In sum, this solution can be
applied with minimum difficulty.
A Sizable Problem
NYSDOT engineers first became aware of a problem when maintenance
crews reported some minor failures of truss diagonals. Those small
failures alerted the engineers to a potentially larger problem.
“It was decided to inspect all of the aluminum overhead signs
on Long Island to determine the extent of the problem,” says
NYSDOT Senior Civil Engineer Harry White. “Initial inspections
in one area of the State revealed that approximately 10 percent of
all the overhead sign structures had some form of structural damage.
We then decided to inventory and inspect every overhead sign structure
in the State. If we hadn't inspected, the risk would still
have been unknown. There are more than 2,000 of these types of structures
in service in New York. Depending on the size and location, replacing
an overhead sign structure can cost as little as $50,000 or up to
$300,000 for a large structure carrying variable message signs.”
With little warning and no time to prepare for sticker shock, NYSDOT
suddenly was facing a potential $25 million problem.
Finding a Low-Cost Answer
Facing the tremendous cost and logistics of replacing hundreds of
overhead sign structures spanning some of the busiest roads in the
State, the agency needed to find a better solution. At the time, John
Neidhart was a senior civil engineer for NYSDOT and head of the overhead
sign structure unit. Neidhart recalls, “We were thinking of
all kinds of crazy repair ideas, and someone directed us to an FRP
[fiber-reinforced polymer] contractor.” At the time, these
composites already were being used to retrofit substructures in New
York.
Research on Fiber-Reinforced Plastic
Composites

|
| A bridge column
and bent cap is wrapped with carbon fiber-reinforced plastic
composities for seismic protection. Photo: Structures Research Laboratory, University of Utah. |
The American Society of Civil Engineers' Journal of
Composites for Construction recognized the research by Professor
Chris Pantelides and his former student Dr. Janos Gergely of
the University of Utah as the “Best Paper for Applied
Research” in 2002 for work on carbon fiber-reinforced
plastic composites. The initial ankle-wrap design for the overhead
aluminum trichord signs originated from this research.
“The ankle-wrap technique using carbon fiber-reinforced
plastic composites was designed to provide an alternative to
steel plate connectors, which are susceptible to corrosion and
difficult to implement,” says Pantelides. “We
were overseeing this technique being applied to the I-80
bridge over State Street in Salt Lake City when Larry Cercone
of Air Logistics Corporation told me about the problems that
New York was having with overhead aluminum trichord signs. He
asked me if I wanted to look into whether this technique could
be used to repair cracked welded connections, and I said yes.”
However, wrapping aluminum joints presents new problems. “The
key is to make sure you get good adhesion to the aluminum surface,”
says Pantelides. “With the proper preparation of the
aluminum surface, we found we could obtain a strong bond.”
Pantelides is planning on presenting the findings of his research
for repairing aluminum overhead trichord signs at the 2004 Transportation
Research Board annual meeting in Washington, DC, during the
week of January 12. |
Fiber-reinforced polymers have been used successfully in many transportation
applications, but this was the first time they were considered as
a wrap for welded aluminum joints on overhead signs. NYSDOT and the
Utah DOT organized a pooled-fund study to determine whether fiber-reinforced
polymers could be used to repair cracked aluminum joints. Larry Cercone,
a consultant with Air Logistics Corporation, contacted Chris Pantelides
to conduct the study.
Testing a Practical Solution
The research was designed to test cracked aluminum weld connections
that were either unwrapped or wrapped with fiber-reinforced polymers.
Researchers wanted to see whether the cracked aluminum welds could
be replaced by this composite material. The research also tested aluminum
chords that had not been previously welded but were reinforced with
fiber-reinforced polymers. For these specimens, a tack weld (for alignment)
was applied and then wrapped with the composite material.
Testing involved placing repetitive forces simulating wind on the
test specimens. A triangular load frame was built to enable the diagonal
of the specimen to be positioned vertically, directly under an actuator
(a device that converts hydraulic energy into mechanical energy).
The actuator applied loads on the joints of specimens at the same
angles that natural forces act on the structure in the field.
 |
| Professor Chris Pantelides
discusses study results with Utah DOT engineer Dan Hsiao at the
University of Utah's research lab. |
The results were promising. Cracked samples repaired with fiber-reinforced
polymers achieved strength in excess of 115 percent of the original
welded connection. In addition, samples fitted only with a tack weld
and fiber-reinforced polymers reached capacities virtually equivalent
to a newly welded aluminum connection.
New York Implements The Solution
The New York transportation agency watched the test results closely
and implemented the solutions as early as possible. Initial results
enabled NYSDOT engineers to consider the repair method effective for
2 years.
“Adding just 2 years of usable life to a structure is a tremendous
benefit,” says White. “It allows the OSS [overhead sign
structure] fabricator to work the replacement structure into the schedule,
rather than having to stop current production to fabricate an emergency
replacement structure. Having the OSS fabricated and erected under
an emergency situation significantly increases the cost over typical
construction. This repair eliminates those extra costs.”
As additional results continued to confirm the effectiveness of the
repair technique, New York engineers upgraded their confidence in
the repair. “Additional results from the study allowed us to
consider the repair effective for 5 years,” says White. As
long as the technology proves to be successful over time, estimates
of the lifespan of the repair will continue to increase. “Once
the repair is complete, we consider the overhead sign structure to
have its full load-carrying capacity,” says White.
One of the most attractive features is that the repair can be made
in place at a minimal cost and in about 3 hours' time (discounting
time for traffic control). Once the necessary work zone is set up,
trained maintenance or contractor workers can repair the structure
on the roadway using a manlift.
One of the keys to successful implementation is to make certain that
the surface is clean prior to wrapping, ensuring proper adhesion to
the aluminum surface. One approved system requires 37 simple steps
to complete the repair. “The repair itself requires care and
diligence by the workers, but it is not difficult,” says White.
 |
| Engineers complete the
final steps of a joint repair. Repairs such as this require attention
and care, but generally are not difficult for work crews. |

|
| Two welded aluminum joints
fitted with strain gauges are tested for fatigue resistance and
load-carrying capacity. Forces in the laboratory simulate thousands
of high wind events. |

|
| The original aluminum
weld becomes exposed after a wrapped sample was pulled apart by
a massive hydraulic-poered actuator. Results from the tests revealed
that a cracked joint repaired with the fiber-reinforced polymer
wrap was just as strong as a new welded joint. |
Larry Cercone says, “The application of the FRP-aluminum adhesion
is based on standard aerospace procedures. First, absorbent pads are
hung beneath the joint to capture any chemicals used.The surface
is prepared using an alkaline chemical, acid, and water to clean and
etch the surface to improve the mechanical bonding properties of the
aluminum.Primer and an adhesive are applied prior to the FRP.
Four different weaves of FRP—a fine woven wrap, a heavier weave,
a tubular braid, and unidirectional tendon wrap—are applied
strategically on the joint to achieve the needed strength characteristics.
“Water acts as the catalyst to start the chemical reaction
that hardens the material,” Cercone continues. “The
FRP achieves its strength approximately 60 to 90 minutes later. The
only byproduct from the reaction is carbon dioxide, making the repair
environmentally safe. Optionally, the cured FRP can be painted to
match the rest of the aluminum structure so the repair will be invisible
to the traveling public.”
When a contractor repairs a sign structure, NYSDOT requires an inspector
to be present, or the procedure is videotaped. The agency also requires
all repaired structures to be inspected annually.
According to White, the cost of the repair is far less than that
of replacing the structure. The repair materials include surface cleaning
supplies, an epoxy for adhesion, the composite material, and a few
other low-cost materials. In total, NYSDOT spends approximately $300
on the materials needed for each joint repair. Few tools are needed,
aside from a cordless drill and scissors.
Looking toward the Future
New York engineers continue to inspect repaired structures and watch
for additional results from the ongoing research. They are confident
in the repairs as a temporary fix until the structures can be cycled
into a replacement program. Future research and experience will determine
whether the repair can be considered more permanent.
The important thing is that the safety of the motoring public in
New York is being held to the highest standard. State DOTs around
the country strive to make highway facilities as safe as possible
in light of limited budgets. This repair accomplishes both goals.
It saves money, and, more importantly, it protects lives.
AASHTO's Technology Implementation Group (TIG) chose to support
nine technologies that are likely to yield significant economic or
qualitative benefits. The group added repairing hazardous sign structures
to their technology priority list.
For more information, contact Harry White II, P.E., senior civil engineer, NYSDOT, 518-485-1148; John Neidhart, P.E., senior civil engineer, NYSDOT, 518-485-5700; or Chris Pantelides, P.E., professor of civil engineering, University of Utah, 801-585-3991.