November/December 2003
Virginia Gains Public Trust
by Donna Purcell Mayes
The Virginia Department of Transportation took measures to address
project data and information problems and opened up its agency's operations
to the public.
Says author William Pollard, “Information is a source of learning.
But unless it is organized, processed, and available to the right people
in a format for decisionmaking, it is a burden, not a benefit.”
The Virginia Department of Transportation (VDOT) found itself in such
a situation; it had a big problem with data and information management,
which led to other more serious problems. On the one hand, VDOT took
pride in being known as an innovative engineering and research leader
to peers in the transportation industry. However, VDOT also discovered
that Virginia's elected officials, reporters, and citizens didn't necessarily
retain the same view and positive impression, especially when it came
to construction projects.
Within the agency, there appeared to be a disconnect between data collections
and the information that was needed, desired, and communicated internally
and externally, contributing significantly to budgetary and project
management issues, and a negative outward image. Part of the difficulty
was where information was stored, access to that information, and what
information was needed to enable managers to make proactive decisions.
Volumes of data, past and present, were stored in a variety of methods,
locations, and databases, making it onerous to gather and analyze information
about one project, much less all projects. Problems with cost estimating
also could be linked to inaccurate, incomplete, and “guesstimated”
information.
“Project management and cost estimating were our two biggest
trouble spots,” says VDOT Commissioner Philip A. Shucet. “I
asked about several major projects' costs and progress. Each person
I asked gave me different answers because each answer included different
data ... presented in such a way that it was hard to get a good handle
on what was really going on with the projects.”

|
A VDOT project manager
uses Dashboard to track progress on his projects. Local government
officials, contractors, and citizens can do the same by visiting
Dashboard at virginiadot.org. All
photos courtesy of Virginia Department of Transportation. |
He adds, “You can't do good business that way, so we developed
our project management system, Dashboard, and our Cost Estimation System
within a year, and we're already reaping the benefits ... huge leaps
from where we were.”
Through these two new Webbased systems developed in-house with off-the-shelf
software, VDOT is gaining public trust and a reputation for accountability
and openness.
| Benefits of Dashboard |
- Little additional cost
- Familiar software, such as Excel worksheets to collect data
and compute estimates, reduces demand on information technology
staff for assistance
- No need to log into multiple systems to obtain data
- More complete and timely data, no time wasted trying to locate
data, ability to access data from any employee workstation within
60 seconds and in 10 or fewer keystrokes
- Consistent results across the Commonwealth
- Both sites provide the same "business" look and feel, are
intuitive, and reduce the need for training
- Modifications can be made quickly and easily by in-house staff
|
The Mixing Bowl Catalyst The VDOT problems came to light with an improvement
project near Washington, DC, for the I-95 Springfield Interchange, known
locally as the "Mixing Bowl." According to an audit report about the
project from the U.S. Department of Transportation's (USDOT) Office
of the Inspector General (OIG), "The Springfield project, when completed,
will improve traffic flow at the junction of Interstates (I)-95, 395,
and 495 in Fairfax County, VA, which is one of the busiest and most
congested interchanges in the country." The massive interchange feeds
I-95 traffic into the District of Columbia, northern Virginia, and Maryland
through I-395 and I-495. Like sometimes happens with other complex urban
projects, this huge, seven-phase effort with its frequently changing
costs and scope was starting to pick up a negative perception.
The project's estimated cost in June 1994 was $241 million, however,
this increased by 180 percent to at least $676.5 million by June 2002,
according to the OIG's November 2002 Audit of the Springfield Interchange
Project: Federal Highway Administration Report Number (IN-2003-003).
The audit also maintained that "this 180 percent cost increase occurred
due to (1) the addition of new features after the initial estimates
were prepared, (2) consistent exclusion of certain reasonably anticipated
and known costs from earlier estimates, and (3) unanticipated cost increases."
The audit found that not only had the Springfield project cost estimates
increased, but that "construction problems have increased costs and
could delay project completion, and funding to pay for cost increases
has come at the expense of other State highway projects. We [Office
of the Inspection General] made six recommendations to improve planning,
cost-estimating, project management, and oversight. Responding to a
draft of this report, FHWA [Federal Highway Administration] agreed to
implement all six recommendations. VDOT also agreed with all of the
recommendations and committed to work with FHWA to implement them."
Because of its problems, the project served as a catalyst for VDOT
to make major changes in how the agency manages highway and bridge construction
projects. It set the stage for real change in the agency that would
be viewed as permanent instead of political. VDOT considers the changes
to be groundbreaking, because they demonstrate how a State agency can
do business openly under the unblinking public eye.
"Also significant is the fact that Virginia is now requiring finance
plans for all [its] large projects, not just the federally mandated
plans for megaprojects. The Office of Program Administration views Virginia's
'voluntary' approach to finance planning as a best practice," says Stewardship
and Oversight Leader Tom Sorel from FHWA's Office of Program Administration.
"Sound financial planning is almost always associated with good monetary
stewardship and is a key to maintaining public trust and confidence
with all large projects."
Today, the interchange improvement is under control with a single project
manager, a realistic budget of $676.3 million, and a stable completion
date in 2007.
"Dashboard" for Project Management
Upon arriving at VDOT in April 2002, Shucet, a former official in the
West Virginia and Arizona transportation departments and a Michael Baker
Corporation executive vice president, asked his new staff members if
they had any way of telling how VDOT was doing with its projects and
program deliveries. Their responses indicated that this was an area
for agency improvement.
Dr. Gary Allen, VDOT's chief of Technology, Research, and Innovation,
wondered if a simple tracking tool with colored lights, or something
similar, to show the status of every project in VDOT's Six-Year

|
| As this aerial shot suggests,
the massive Springfield Interchange Improvement Project near Washington,
DC, is a highly visible effort that motivated VDOT to change the
way it manages and estimates its projects. |
Improvement Program might do the trick. After talking through the idea
and working with a handful of people, Allen quickly-and literally-sketched
out the concept. The group also came up with an initial set of rules
to determine project statuses. Within less than 2 weeks, the group presented
a template for what became VDOT's project management tool, Dashboard.
The agency's Dashboard is an online, one-stop information source that
highlights the status of Virginia projects ready to go to construction
and those under construction. Dashboard shows the latest on a project's
progress, costs, and work orders (contract approvals to move forward
with the work). The statuses are pictured using the red, yellow, and
green lights on a traffic signal icon:
- Green means the project is on track-on time, within budget,
and has zero or few work orders.
- Yellow means the project is at risk of falling behind,
going over budget, or having too many work orders.
- Red means the project is behind, over budget, or has too
many work orders.
"Our goal is to maintain the green, manage the yellow, and deep-six
the red," says John DePasquale, P.E., northern Virginia construction
engineer. To do that requires spending resources, with "yellow" generating
the biggest cost-to-benefit ratio in moving a project to "green," he
explains. The tool earned its name because, just as an automobile's
dashboard keeps the driver informed of the car's performance, Dashboard
keeps VDOT project managers (and the public) tuned in to construction
performance. It alerts them to the projects that are on track and those
that are at risk. With this information at their fingertips, the project
managers' jobs are to get the work back on track when possible.
"It's a great tool," says Tom Hawthorne, P.E., VDOT's Richmond District
administrator. "Dashboard lets us focus on simple metrics to judge our
progress, good or bad, against our goal of managing our transportation
program more effectively."
How Dashboard Works
Dashboard graphically displays information collected from several mainframe
systems through a data warehouse. Those systems include VDOT's Program
Project Management System, showing the status of project schedules from
planning to advertisement, and Trns·port, a construction contract monitoring
system developed by the American Association of State Highway and Transportation
Officials (AASHTO). Because the systems are updated and queried daily,
the Dashboard view is always less than a day old.
"It tells me in a moment what would have required going through reams
of individual project reports to pull together before," says Connie
Sorrell, VDOT's Director of Policy and Organizational Development who
was tasked with coordinating the Dashboard effort. "Before Dashboard,
we were data rich, but information poor."
VDOT's Chatham Resident Engineer Randy Hamilton adds, "Dashboard helps
us easily track a project from advertisement through construction and
keep it moving forward. Before, we had to rely on others to go through
various information systems to pull the information together. Now we
can get it ourselves quickly and we can answer our customers' questions
on details." No special software was developed or purchased. VDOT's
information technology staff relied on Microsoft® software products
already used by the agency.
Dashboard has three views: a summary level, a second level that lists
the projects, and a third with project details. The levels are on VDOT's
external Web site, but within the third is a section reserved for internal
viewing that includes some project history. To view the Dashboard system,
go to http://dashboard.virginiadot.org
on the Web. Projects can be sorted into statewide, regional, local,
or highway system listings. The system is transparent: anyone can see
the information without a password
| Technical Specifications |
Both systems:
Microsoft Windows® 2000 Server operating system
Microsoft Internet Information Server (IIS), a Web application server
Microsoft SQL ServerTM database
Microsoft SQL Server 2000 Data Transformation Services (DTS) for
Enterprise Application Integration
Rapid Application Development (RAD) tools and methodologies
Dashboard:
Microsoft Visual Basic® COM component, a dynamic link library
(DLL)
Microsoft Active Server Pages (ASP), server-side scripting environment,
Visual Basic Scripting Cost Estimation System:
Microsoft Excel for cost-estimation rules engine and data entry
Microsoft Project office project management program to display project
schedules as Gant Charts
Microsoft Exchange for up-to-date user e-mail addresses and phone
numbers |

|
| This screen shot of Dashboard
shows project details to the public, including e-mail links to people
accountable for projects. Surprisingly, VDOT managers were not flooded
with angry comments, but instead received reasonable questions and
compliments. |
Project status is reported in four categories:
- Advertisement schedule
- Construction contract deadline
- Construction contract award amounts
- Work orders
One of the major challenges in creating Dashboard was establishing
criteria that would determine whether a project was "red," "yellow,"
or "green" in each of the four categories. A project is considered "green,"
for example, if it is on schedule according to its contract; "yellow"
if it is between 1 and 9 percent behind schedule; and "red" if the contract's
completion date has passed, or if the project is 10 percent or more
behind schedule, or if 90 percent of the time for the project has lapsed
but less than 90 percent of the work is complete, or if critical data
about the schedule are missing.
Missing or out-of-date information was the other big challenge. Dashboard
tracks about 24 of the most significant project activities in VDOT's
Program Project Management System. When Dashboard went live internally,
many projects that showed up "red" really were simply missing some data.
VDOT staff spent several weeks on updating data, and additional time
testing Dashboard.
Public Reaction
Less than a year later, on March 12, 2003, and with more than a little
admitted internal squeamishness about opening itself up for public scrutiny,
VDOT launched Dashboard on its external Web site, www.virginiadot.org.
"It just made sense that if we were spending $3 billion of taxpayers'
money a year, they had a right to see how it was being used and to ask
questions of the person responsible for the project," says Shucet. "Yes,
it made some of our folks nervous, but we have to be accountable for
what we do. No excuses. No hiding." Others agreed. Instead of receiving
verbal derision for its "red light" projects, VDOT heard praise for
sharing the good, bad, and even ugly details with the public.
"I think it's the most advanced instance of a really transparent project
management system," says Jonathan Gifford, director of Master's in Transportation
Policy, Operations, and Logistics at George Mason University in northern
Virginia.
"In the public sector, it is difficult to know how a project is developing,"
says Jim Comstock, of Comstock Communications Concepts, a project management
expert who has conducted training in several State DOTs, including VDOT.
"VDOT's Dashboard is on the cutting edge in providing the needed information
to all of the project's stakeholders."
Dwight L. Farmer, deputy executive director for transportation for
the Hampton Roads (VA) Planning District Commission, adds, "The public's
as well as the (local) governments' opinion of VDOT was that progress
and budgets were a great mystery, at best. Dashboard has added enormously
to the openness and ease of availability of budget and progress information."
"Governor Warner is a firm believer in 'that which gets measured gets
done,' says Virginia Secretary of Technology George C. Newstrom. "VDOT's
Dashboard is an excellent example of how State agencies can allow our
customers, the citizens of the Commonwealth, to gauge our performance
in serving them."
Comments from news reporters and editors include: "Lots of great information,
very transparent-you don't get this a lot in government."-Lane Ranger
column, Potomac News, March 17, 2003. "Transportation Commissioner
Philip Shucet says he expects a lot of feedback because of the site.
Here's some: Good job."-Richmond Times-Dispatch editorial,
March 20, 2003.
"The ability to immediately review the physical and fiscal condition
of a particular project aids in communicating with my constituents regarding
VDOT projects," says Virginia State Senator Marty Williams, who, as
chair of the Virginia Senate Transportation Committee, receives many
questions about the transportation agency's work. "VDOT employees are
aware of their actions, and the quality of their projects is only a
few clicks away from their potential critics." The system makes employees
aware of accountability for their actions.
Sharing Dashboard on the Web means that users can obtain the details
at their convenience. And anyone can ask questions of the project managers
through e-mail links contained in each project's description.
"The way Dashboard is presented, anyone can pick up information without
having to get hold of someone between 9 and 5," says Young Ho Chang,
P.E., director of transportation for Fairfax County, a densely populated
area just outside Washington, DC.
VDOT to improve its relationships with local government and citizens,"
Chang observes. "I respect VDOT for saying, 'Here's what we're doing
and how we're doing it . . . You're going to see us every step of the
way.' The true benefit will come with what VDOT does with the information.
The key is to improve by using this tool."
Resulting Changes
Shucet agrees and emphasizes that seeing red lights on Dashboard can
only help VDOT project teams. "There's nothing wrong with a light being
red," he wrote to VDOT employees.
"If a light is red, and if all of the information turning the light
red is accurate, then we can learn from the experience to make the next
job better. And the one after that even better again ... That's using
knowledge to improve our business," he emphasized.
"Dashboard has been an organizational catalyst for us," adds DePasquale.
"It's making everyone focus on the same goals, and it's changing our
project management behaviors and practices."
For example, Dashboard and other reports clearly showed that VDOT was
doing a better job of keeping its projects within budget, with some
notable exceptions, than completing them on time. Three months after
Dashboard's public launch, 72 percent of the projects shown were within
budget while only 35 percent were within their contract deadlines.
Many of the projects have "calendar day" contracts, meaning that they
must be completed within a certain number of days, instead of "fixed
date" contracts, which must be completed by a certain date. Now VDOT
is transitioning to all fixed-date contracts unless there is a compelling
reason not to.
"This change will get the projects completed quicker," says Sorrell,
"help us give citizens more specific information on when the projects
will be completed, and emphasize better planning on the contractors'
part."
Cost-Estimating Challenge
The Springfield Interchange work was the most recognized of the projects
that were underestimated in terms of cost. VDOT engineers now agree
that, over the years, projects were added to Virginia's Six-Year Improvement
Program, the agency's blueprint for distributing anticipated funds to
transportation projects, with unsound cost estimates developed early
in the projects' lives. This underestimating led to public and political
criticism because, year after year, costs in the program document would
increase, sometimes dramatically.
Bill Cannell, formerly a VDOT public affairs manager for Virginia's
huge Hampton Roads urban area recalls, "It was very difficult to explain
to a savvy reporter who had covered VDOT for years why a project's cost
estimate increased 50 percent from 1 year to the next."
A month after starting Dashboard, Shucet tackled another major problem.
VDOT did not have enough money for the construction projects in its
Six-Year Improvement Program pipeline. In a sample of projects statewide,
the difference between early project estimates and the final costs was
more than 200 percent.
"In the newspapers, it seemed that you didn't see the phrase 'VDOT
project' without the term 'over budget' lurking nearby," says Stephen
Haynes, a VDOT engineer. The problem was not unique to VDOT. An AASHTO
Task Force on Project Oversight found that many State DOTs across the
country have struggled with keeping their statewide transportation improvement
programs in line with available funding. Some, such as Utah, dramatically
changed their programming to make it more realistic, says Tom Stephens,
P.E., now-retired director of the Nevada DOT and chair of the task force.
Accurate, consistent, welltimed cost estimating has become such a challenge
for many States that, in addition to the Project Oversight Task Force,
AASHTO's Standing Committee on Highways Subcommittee on Design has formed
a Cost Estimating Task Force to come up with solutions.
In VDOT's case, Virginia reduced the allocations in its program in
2002 by nearly a third from the previous year. Many early project cost
estimates included too much guesswork and were far off the mark, usually
on the low side. Many estimates were based on employees' judgment, expertise,
and experience rather than a sound, consistent, methodological approach.
The estimates often were created at differing points in a project cycle
or in differing ways. Inflation was rarely factored in. Certain environmental
treatments and unusual construction cost items were not always considered
early in the projects' development, which resulted in costly work orders
when those items came up after construction began.

|
| The Cost Estimation System's
Intranet opening screen lists the most essential details for thousands
of projects. From this screen, users can click down to more detailed
pages. |
VDOT needed a method for accurately estimating project costs early
on that considered the many different factors that can change costs.
The method had to be something that VDOT's nine districts would use
uniformly in a State where the topography ranges from beaches and swamps
to mountains and valleys.
And it had to be user-friendly. Commissioner Shucet tasked Allen to
lead an effort to develop a definitive, consistent, well-documented
approach for estimating construction projects. A task force that included
VDOT engineers and researchers, two Commonwealth Transportation Board
members, and a metropolitan planning organization member either had
to locate the best available early project estimating system or develop
one.
Through research, the task force found that many State DOTs were attempting
to address the problem, but none had a "silver bullet." Washington State
DOT was using a range of estimates for risk factors. California's transportation
agency, Caltrans, was using three estimates: optimistic, pessimistic,
and realistic. Although these approaches had merit, the task group did
not think that they would help VDOT.
The method with the most potential revealed itself in VDOT's own backyard.
Haynes, a member of the task force, had developed a project scoping
estimation method 3 years earlier. The method, a feature-based system
using Microsoft® Excel software, was estimating the district's road
costs accurately using historical data. Estimation errors were lower
in his district than the statewide average. The Haynes method included
an annually compounded inflation factor. It was applicable for primary,
secondary, and urban highways. Although the method did not take into
account all project attributes, it did include a comprehensive list
of the higher cost items and showed more promise than anything else
the task force had seen. VDOT found the beginning of a solution from
within the organization.
Using the Haynes method as the foundation, the task force collected
extensive project data and evaluations from VDOT project management
staff to build a project information center that includes:
- A structured scoping system to provide early and complete input
- An estimating system that is thorough and simple to use
- A Web-based database serving as a project information repository
Scoping and Estimating
"We learned early on that an incomplete or inaccurate estimate in the
early life of a project was only going to get worse by the time we were
ready to advertise it," says task force member Harry Lee, Fredericksburg
District location and design engineer and Haynes' boss. "We had to develop
some methods for 'doing it right' on the front end-at the scoping stage."
VDOT had no consistent, uniform method to define a project's need,
or how it could best be built-and by whom. This led to serious scope
creep during the life of a project, so estimates did not hold up over
time. The scope and the cost crept, yet often the original estimate
was never adjusted to allow for those changes.
For uniformity and accuracy in the scoping process, part of the solution
was to migrate all projects to a Web-based Intranet site that includes
the project description, purpose, need, project narrative, team structure,
schedule, basic project information, cost estimates, project tracking,
documentation, approvals, and other details about the project. Each
element is essential to the success of the estimating system. Each project
has a site that serves as a repository for all information about that
project-and only that project, Lee says.
"We call it the Cost Estimation System, but it is 10 times more than
that," says Mike Branscome, assistant location and design engineer in
VDOT's Staunton District. "It's a project information clearinghouse.
Our contract administrators love it because they can go to one place,
and within 10 clicks or 60 seconds, they can get all the details they
need without having to run reports." The district's preliminary engineering
staff uses the system for project information to help prepare for scoping
meetings, he notes.
The estimating part of the system includes spreadsheets that prompt
users to enter details that can affect project costs, helping ensure
that nothing is overlooked. While considering the usual features-road
length, lanes, curbs, gutters, and the like-the possibility of landscaping,
lighting, retaining walls, hazmat removals, and wetland or cultural
mitigation also is considered.
Other worksheets require details for estimating bridge costs, right-of
way transactions, and utility relocations. Costs associated with inflation,
construction engineering and inspection, and preliminary engineering
are computed automatically and added to the estimate for a total project
cost.

|
| Virginia's new cost-estimating
tool requires estimators to consider nonroutine items, such as bikeways
like this one, when developing early project estimates. |
Every spreadsheet component must be completed, which requires collaboration
among staff members representing all aspects of a project, from the
local office to VDOT's central office. Although Virginia's diverse geography
can create variations in project costs across the Commonwealth, the
system accounts for the variations by using district-specific adjusters.
A 3 percent interest rate rate is factored into the estimates.

|
| The Cost Estimation System's
project schedule screen outlines all the task milestones in a project's
development and quickly shows what has been completed. |
"Communications is the key here," says Lee. "And everyone has to do
their homework on the project before that communication can happen.
Much more work will be done prior to the scoping meeting than ever before,
which should save significant time and money later in a project's development."
The goal is for estimates to be as close as possible to the final project
cost. Applied to projects within VDOT's current Six-Year Improvement
Program, the system is helping create a more realistic, credible, achievable
program than in the past. And how is it working so far? Early analysis
of the system's performance indicates that cost estimates tend to be
much closer to final project costs than ever before. "The foundation
of our business is getting the estimate right," says John H. Neal, Jr.,
VDOT's Hampton Roads District construction engineer. "Now we have one
official source to go to for cost information. It's pretty explicit
about what went into the estimate. It's producing realistic estimates."
Richard Caywood, P.E., VDOT's Petersburg resident engineer, adds, "It's
given us a repeatable process framework that will increase our estimating
precision every time we use it. It's taken something that was an art
and made it into a science."
Next Steps
Dashboard's technical team plans to add several improvements before
the system's first anniversary. Users will have a better picture of
the projects-literally. A "Map It" feature will provide a geographic
information system (GIS) map of the project area, "Picture It" will
supply aerial photos of the project site, and "Drive It" will create
a virtual drive of the project.
The Cost Estimation System will include major revisions to the right-of-way
and utilities worksheets, details to address additional lanes and varying
terrains, plus statewide training on using the system. A preliminary
engineering tracking system module lets users tailor inquiries about
schedules and budgets spanning the life of the projects.
A new plan sheet module to enable users to view and print design plan
sheets-a time-saving feature- soon will be added. The agency also has
plans to integrate the project documentation feature (for videos, photographs,
e-mails, memos, and the like) with VDOT's Falcon, a repository for road
designs and other project documentation.
Is all the hard work paying off? It appears so.
"Your technology linking independent databases and allowing public
access and oversight through that technology is the best financial watchdog
ever created," wrote Virginia's Deputy Secretary of Transportation Pierce
Homer, in a memo to employees involved with Dashboard and the new Six-Year
Improvement Program. "It simply will not be possible to create a $10
billion plan with only $7 billion of revenues. While I admire the technical
elegance of these efforts, I admire even more their impact on responsible,
democratic governance."
Shucet adds, "Dashboard and the Cost Estimation System changed our
problems into opportunities to build on. With these tools, we will never
go back to the way we did business before them. We owe it to ourselves
and to our customers to only go forward-and to do it openly."
Finally, in their efforts to be good stewards of taxpayer investment
in transportation, VDOT would like to offer other State and local transportation
agencies the opportunity to use and adapt their project management and
cost-estimating systems to their own agencies.
Donna Purcell Mayes is an assistant public affairs
director for VDOT, a position she has held since 1990. She joined the
agency as an editorial assistant in 1977. She is a member of the Public
Relations Society of America and the Virginia Government Communicators.
For more information on Dashboard, contact Connie Sorrell, chief
of Policy and Organizational Development, VDOT, connie.sorrell
@virginiadot.org, 804-786-1476. For the Cost Estimation System,
contact Gary R. Allen, Ph.D., chief of Technology, Research, and Innovation,
VDOT, gary.allen@virginiadot.org,
434-293-1938.
Other Articles in this issue:
Getting Ahead of the Curve
Laying the Groundwork for Fast Bridge Construction
Cracked Girders
CAD and ITS Working in Concert
Responding to an Earthquake
A Fix for Aluminum Overheads
Composites Add Longevity to Bridges
The Public: Key to Successful Projects
511 — It's Happening!
Virginia Gains Public Trust
Low-Cost Solutions Yield Big Savings
Improving Bridge Inspections