September/October 2003
A New Solution for an Old Problem
by James K. Stangenburg, Thomas E. Shifflett, and Jeffrey A. Schmidt
An innovative use of anchor blocks and tiebacks may solve a landslide
condition on a steep roadside slope in Tennessee.
Much of the historic road over the Cumberland Gap in the tristate area
of Tennessee, Virginia, and Kentucky follows the original wagon road
blazed by Daniel Boone in 1775. As the population of the region grew,
the demand for road improvements became a constant. By 1973, relocation
of the road was authorized through a tunnel. The connection to US 25E
through the new tunnel required a cloverleaf with ramp to US 58. Construction
of the ramp began in May 1990. Planned excavation was to cut as deep
as 24 meters (80 feet) into Poor Valley ridge, creating a significant
potential for landslides.
 |
| This view of the construction site
from the interchange shows the concrete barriers and fence that
were installed to prevent debris from entering the roadway below.
|
The Federal Highway Administration's Eastern Federal Lands Highway
Division (EFLHD) designed a solution for this slope failure condition
by reviewing data from past slides and obtaining supplemental subsurface
information. "The result was an innovative solution that conformed to
stringent aesthetic requirements," says Acting Superintendent Mary Collier
of the Cumberland Gap National Historical Park.
Past Slide History
When originally designing the ramp, the highway planners reduced the cut
slopes for the US 58 ramp from 1:1 (horizontal to vertical) to 2:1. Prior
to the start of construction, the engineers installed slope indicator
devices and groundwater monitoring wells to monitor the potential for
slides as the excavation progressed.
When the cut was nearly 18 meters (60 feet) deep, a heavy rainfall
caused a small slide near the base of the excavated slope. The monitoring
data indicated a relatively shallow slide involving the soil overburden
and the brown shale strata (the Upper Rockwood Formation) just beneath
the soil layer. A few months later, in 1991, EFLHD decided to flatten
the slope further to 3:1 and continue the cut. Further flattening of
the slope to negate the sliding potential was not possible because of
right-of-way restrictions.
In January 1992, after another extended rainfall, a much larger slide
occurred, near the base of the excavated slope and midway along the
proposed ramp. This slide was estimated at 53,550-plus cubic meters
(70,000-plus cubic yards).
After a review of several options, EFLHD decided to install a 290-meter
(950-foot)-long soil nail wall consisting of a 305-centimeter (12-inch)-thick
shotcrete wall with internal drainage and high-strength steel anchor
bars drilled and grouted into rock for lateral support. Shotcrete is
a sprayed-on concrete layer that can be applied to near-vertical surfaces
to act as a supporting wall in conjunction with rockbolt reinforcement.
The engineers designed the shotcrete wall to bear on the stable gray
shale (Lower Rockwood). They also modified the slopes above and below
the wall. The shotcrete wall supported the soil and the Upper Rockwood
strata, which were cut on a 2.5:1 slope. Below the wall, EFLHD excavated
the slope down to the Lower Rockwood. Construction of the soil nail
wall was completed in October 1992, and it effectively eliminated the
problem of the unstable lower slides.
EFLHD performed annual inspections after installation of the soil nail
wall. An inspection in April 1997, after very heavy rainfall, revealed
the beginnings of a new slide near the top of the cut slope. As a result,
EFLHD began monitoring the slope and soil nail wall at a number of locations.
This new slide developed over an area extending from the top of the
cut slope down to the north end of the soil nail wall, affecting a portion
of the upper (nonstructural) soil nail wall. The slide extended northward
over to the US 25E cut slope, representing a section of the cut slope
not supported by the soil nail wall.
Movement of the slide at the intersection of the US 25E and US 58 cut
slopes caused sandstone boulders to spill continually onto the US 25E
eastbound roadway. EFLHD quickly protected against falling boulders
by installing Jersey barriers along the roadway shoulder and partway
up the slope along a bench.
The New Slide Was Moving In Two Directions
During subsequent monitoring from 1997-1999, a scarp face (a cliff caused
by soil displacement) developed at an elevation of 493 meters (1,615 feet),
facing toward the US 58 ramp. The scarp face was 76 meters (250 feet)
long and up to 2.4 meters (8 feet) high. A similar but shorter scarp face
developed along the toe of the slide at US 25E, caused by soil and boulders
pushed over the steep slope.
In addition, an earth ripple 0.9 meters (3 feet) high was prominent
along the US 58 ramp and the US 25E toe of the slide at an elevation
479 meters (1,570 feet). The earth ripple also affected a nonstructural
section of the soil nail wall by spalling off a large portion of shotcrete.
Slope monitoring data revealed continuous slide movements accelerating
during the spring, tapering off in the drier late summer and fall months.
The monitoring performed during the 2-year period indicated that the
soil nail wall was functioning satisfactorily and was not affected (other
than superficially) by the upper slide. However, EFLHD was concerned
that a potentially catastrophic slide could occur in the weak Upper
Rockwood Formation. EFLHD engaged a consultant to provide a solution.
The consultant's team plotted groundwater and inclinometer records
to estimate the slide geometry and contributing factors. They performed
laboratory direct shear tests on soil and rock samples to estimate the
shear strengths. Then they defined the sliding surface using slope monitoring,
topographic, and boring data.
The next step was estimating slope stability using a computer program
developed by Purdue University for wedge, circular, and noncircular
analyses. In all cases, the factors of safety were at or less than 1.0
when saturated groundwater conditions existed at the site. The factors
of safety were substantially greater than 1.0 when conditions were dry.
The plotted slope data confirmed these results since the slide was
active during periods of wet weather, gradually slowing and ceasing
during dry periods. With the mechanics of the slide ascertained, the
next step was to examine various support options for stabilizing the
slope.
 |
| This closeup shows the damage to
the existing soil nail wall caused by the slide. |
Earth Support Options
Strategies for repair came under a number
of constraints imposed by the National Park Service, owner of the site.
Most important were maintenance of the visual aesthetics and minimal
disturbance of the tree line above the scarp. The goal was to preserve
the viewscape from The Pinnacle, a prominent observation point overlooking
the Cumberland Gap. Another constraint was limited access to the site
since the Park Service would not allow cutting of access roads up the
slope to the slide area, necessitating using an existing unpaved haul
road along the tree line.
EFLHD reviewed various options. One was multiple concrete-filled caissons
either cantilevered into the rock or held by tieback anchors (steel
rods or cables grouted into rock). Other options included another soil
nail wall or a rock buttress. A fourth possibility was concrete anchor
blocks placed on the slope with tieback anchors drilled into the Lower
Rockwood. "The first three alternatives, although viable, would have
resulted in either a changed landscape or substantial spoil removal
and disposal," says Don Miller, project delivery engineer.
The fourth alternative had significant advantages. The anchor blocks
could be buried below the ground surface so they would not be visible.
Installation would require relatively light equipment, and the anchor
blocks could be precast offsite to minimize the onsite storage and work
area. The cost would be comparable with other methods, the anchor blocks
could be placed in several rows to distribute the resisting force more
evenly, and groundwater flow would not be impeded. Finally, the work
could be performed in stages, minimizing the potential to trigger the
still-active slide.
 |
| Workers are spraying
shotcrete for one of the pads. |
Design of the Anchor Block System
Computer wedge analyses determined the optimum block size and anchor capacities
that would provide a minimum factor of safety of 1.50. The engineers planned
a grid of 84 anchor blocks, each 2.4 by 2.4 meters (8 by 8 feet), positioned
parallel to the slope with a spacing of approximately two times the width
of the anchor blocks in each direction.
The plan called for tiebacks to be drilled into the rock at an incline
of 30 degrees from the horizontal. The anchor loads planned for would
be able to withstand a worst-case scenario involving the water table
at the ground surface, the tiebacks skewed off their planned inclinations,
and a wedge of unstable earth.
 |
| The contractor is drilling
for the ground anchors. Note the anchor block set prior to drilling.
|
 |
| Proof loading an installed
ground anchor. |
A 45-degree increase in the force component for those anchors located
on the northeast (US 25E) side was due to the change in slope direction.
However, the anchor forces on that side generally carried less load
due to the shallower depth of the slide surface.
As mentioned, EFLHD specified that the anchor blocks should be precast
rigid footings fabricated offsite. The need to haul them into position
on the slope using a temporary access road imposed a size and weight
limitation. To permit easiest handling, EFLHD selected a 136-megapascal
(300-kip) load capacity anchor block and tieback arrangement.
The engineers estimated that the anchor should develop load capacity
when the tiebacks were drilled 9 meters (30 feet) into the Lower Rockwood.
The intent also was to seat the blocks on a 152-millimeter (6-inch)-thick
shotcrete leveling surface to minimize disturbance to the possibly uneven
bearing surface.
Constructability and the Bidding
Process
When bidding the contract, EFLHD considered a number of constructability
issues. One was site access for equipment and materials, given the steepness
of the slope, the length of the temporary access road, and the weight
of the prefabricated anchor blocks. Another issue was safety while working
on a slope with an active slide mass. A third concern was whether the
contractor would be able to stabilize the slide within a single season,
given the number of anchors that could be placed at any one time. To
continue work into the winter and spring (the wettest times of year)
risked failure before completion.
As a result of these concerns, EFLHD used a two-step process to advertise
the project. First, EFLHD asked prospective contractors to provide a
history of their experience with this type of construction, how they
would meet the National Park Service's aesthetic criteria, and whether
they would use the anchor block strategy or submit their own design
that would meet all of the salient requirements.
Most of the contractors who expressed interest chose EFLHD's plans
for the anchor block system. Two contractors submitted their own designs,
which were slight modifications of the same anchor block strategy. The
National Park Service and EFLHD selected five contractors to submit
final bids.
The second step was the actual bidding. The contractor that won the
bid would perform the drilling for the tieback anchors and install them,
place the shotcrete leveling pads for the anchor blocks, and repair
the existing soil nail wall. Several subcontractors would construct
the haul road, do the excavation and backfill, seat the anchor blocks,
and place the topsoil after final grading.
 |
| The contractor placed
fill material over the anchors and is shown restoring the site to
its original contours. |
Construction
A staging area along the shoulder and ditch of the US 58 ramp followed
an existing logging road along the tree line to the slide location. For
transporting materials, a track excavator was used to carry the anchor
blocks from the staging area to the slide. A track loader also hauled
water, aggregate, and cement bags for a portable shotcrete plant. A boom
fork transported all of the other materials.
Prior to the start of construction, EFLHD installed concrete Jersey
barriers on the affected slope along US 25E. As an additional precaution,
the contractor installed a high chain-link fence on top of the barriers.
The fence prevented the numerous boulders that were dislodged during
construction from overtopping the Jersey barriers and falling onto the
road below.
The contractor began work on July 2, 2001, by clearing and grubbing
the site. The crew installed erosion-control silt fences and brush barriers
around the perimeter of the slide and installed temporary piezometers
to measure the water pressure and inclinometers to monitor the slope
for movement during construction. Read weekly, the monitors indicated
some movement of the slope at times, but the movement was not significant
enough to alter the construction process.
Then the crew laid out a grid of 13 columns of anchor blocks in 10
rows on the slope. Using an excavator, the crew cut a bench into the
slope and immediately placed the shotcrete leveling pads against the
slope. After a shotcrete leveling pad had cured for at least 12 hours,
the contractor used an excavator to carry a concrete anchor block up
the mountain from the staging area and placed it on its shotcrete pad.
A compressed-air rig drilled holes for the tiebacks, which varied in
length from 26 to 32 meters (85 to 105 feet). An excavator and boom
fork lowered the tieback tendons into the holes, and the contractor
then grouted the tendons and cast grout cubes. After the grout cubes
reached the required strength (usually 3 days), the contractor stressed
the tiebacks to 100 percent of design load. Typically, little to no
movement of the anchor blocks was observed during stressing.
An average of two anchor blocks per day (shotcreting, drilling, grouting,
stressing) were completed. Once several of the top rows of tiebacks
were stressed, excavation of the row below could begin. This procedure
enabled the contractor to work on multiple rows of tiebacks at a time,
stair-stepping down the slope.
Due to the unusually dry summer, all the tiebacks were completed by
early October 2001. An excavator and a bulldozer recontoured the slope
and added topsoil prior to seeding. Three permanent piezometers and
inclinometers were installed, and the access road was restored to the
original contours—well ahead of schedule.
Postscript
Four months after the construction was complete, a heavy storm dropped
116 millimeters (7 inches) of rain during a 48-hour period. The inclinometers
recorded no appreciable movement of the slope. The only visible damage
was two minor slides of topsoil, which were quickly repaired.
EFLHD anticipated that construction would be difficult, since the work
would be performed on an active slide, near the top of a barely accessible
slope, several hundred feet away from level ground, and in a location
where any additional loading on the slope could cause catastrophic failure.
For these reasons the sequence of placement and installation of the
anchor blocks had to be accomplished in a controlled manner. In addition,
since the direction of the tieback installation varied with the direction
of the slope, the tieback geometry was monitored carefully to ensure
that there would be no interference from adjacent installed anchors.
"All of this appears to have been accomplished successfully," says
Miller, "judging by the subsequent heavy rainfall and thanks to EFLHD's
innovative planning and the contractor's successful carrying out of
the plan. The result is a new strategy for stabilizing steep roadside
slopes."
James K. Stangenberg, P.E., is a senior associate
with The Robert B. Balter Company. He has 40 years experience in landslide
and geotechnical investigations.
Thomas E. Shifflett, P.E., L.S., is a project manager
with FHWA's Eastern Federal Lands Highway Division.
Jeffrey A. Schmidt, P.E., is a construction project
engineer with FHWA's Eastern Federal Lands Highway Division.
For more information, contact Thomas Shifflett at 703-404-6323
or jerry.baldwin@dot.state.mn.us.
Other Articles in this issue:
State-of-the-Art Toll Road
CPTP Update
Getting Traffic Moving Again
Fighting Fatigue
A New Solution for an Old Problem
Rumbling Toward Safety
Rebuilding a Community Link
A Study in Environmental Justice
Paying the Value Price