March/April 2004
Hyperfix 65/70
by Gary Mroczka, Val Straumins, and Jim Pinkelman
Indiana closed a major interstate corridor
for repairs and reopened it a month ahead of schedule.
On Interstate 65 and 70 (I–65/70) in Indianapolis, IN, most people–not just the Indiana Department of
Transportation's (INDOT) maintenance crews could recognize the signs
of aging infrastructure: potholes, deteriorating joints, and rough
bridge decks. Years of service and rapidly growing traffic volumes had
taken their toll. When transportation planners review all the options for
road rehabilitation, sometimes the best choice may be the "road less
traveled," literally.
 |
| This aerial shows the north split of I–65/70 and
downtown Indianapolis after completion of the Hyperfix project.
|
On May 26, 2003, INDOT and the Federal Highway
Administration (FHWA) planned to shut down the combined sections of I–65/70 in
the heart of the city for 85 days of rehabilitation. The 5.6-kilometer
(3.5-mile)-long project, dubbed "Hyperfix 65/70," would rehabilitate 33
bridge decks and about 56 lane-kilometers (35 lane-miles) of concrete
pavement. It also would add capacity with additional travel and merge lanes.
Before the project began, The Indianapolis
Star ran an article (March 2003) warning commuters
to brace themselves for what could be the "worst construction season
ever." The article explained that the city of Indianapolis planned to begin
repairing several major downtown streets in preparation for the
Hyperfix project. The crews would conduct repair work at more than 20
locationsall at the same timepotentially increasing congestion
for downtown commuters.
On July 20, only 55 days after the Hyperfix project began, former
Indiana Governor Frank O'Bannon (who passed away September 13,
2003), United States Representative Julia Carson, and other
dignitaries proudly opened the $30 million repaired interstate 30 days ahead
of schedule. Former U.S. Congressman Andy Jacobs ceremoniously waved
a green flag as the State opened the road to cars, trucks, and other
vehicles waiting to head northbound on the interstate.
Thanks to meticulous planning and cooperation among
government agencies, the news media, the construction team, and the
traveling public, the traffic jams that the journalist from
The Indianapolis Star predicted never
materialized. "Hyperfix," says INDOT
Commissioner J. Bryan Nicol, "is an innovative model for repairing
metropolitan interstates."
The Beginning
Few questioned the necessity of rebuilding the highway and
bridges on the I–65/70 corridor. When the shared Interstate 65/70 corridor
first opened in October 1976, it was designed to handle 61,000
vehicles per day. Recent traffic counts by INDOT engineers revealed that
more than 175,000 cars and trucks drove this stretch on a daily basis.
Efficiently repairing the busy, deteriorating interstate and its
bridges, however, posed a logistical problem. In reviewing its options,
INDOT determined that rehabilitating the infrastructure using traditional
methods (that is, with partial closures) would take 180 to 200
workdays, possibly requiring two construction seasons, and cost $1 million per
day in lost productive time to the highway users. "I directed our
engineers to put together a plan to deliver the project in record time," says
Commissioner Nicol.
Eventually, INDOT leaders started discussing a total shutdown.
Despite disruptions for commuters and other road users, a shutdown would
enable the State to complete the project more quickly, safely, and at
a reduced cost. More than a year of planning followed with input
from all the stakeholders.
Prepping with City Street Repairs
In mid-summer 2002, when Indianapolis began planning for the
I–65/70 closure, the city hired traffic consultants to analyze the
project's likely impact on city streets. West Street, the local street running
parallel to the I–65/70 link, was carrying its design load of 25,000
vehicles daily. The consultant anticipated a doubling to 50,000 vehicles a
day during Hyperfix 65/70. Clearly some changes were needed to
increase capacity there and at several other chokepoints.
"We had to figure out what we needed to do," says Paul
Whitmore, public information officer for the City of Indianapolis' Department
of Public Works, "how quickly we could accomplish it, and how
we were going to pay for it."
To help Indianapolis prepare its streets for the increased traffic,
construction began mid-March 2003, at a hectic pace to finish before
Hyperfix 65/70 started at the end of May.
Modifying West Street to increase capacity was the most
significant project for the Indianapolis Department of Public Works. The
construction contractor added an additional travel lane in each direction by
reducing the width of the lanes and cutting into the landscaped
median. The contractor also milled the street and put down a new asphalt
surface to handle the anticipated heavy truck traffic that normally
passes through on the I–65/70 link.
 |
| Former U.S. Congressman Andy Jacobs from Indiana waves a green flag at
the opening of the I–65/70 corridor on July 20, 2003. He helped obtain
Federal money when the downtown portion of I–65 was built.
|
The city added turn lanes, restricted parking during the
morning and evening rush hours, and took steps to accommodate
additional traffic volumes on corridors connecting the northeastern part of
the county to the suburbs. Two key intersections specifically
required upgrades to handle the additional volume. One fix involved
removing an existing traffic signal to allow free-flowing traffic. The other
required removing a concrete median, installing numerous lane shifts,
and adding a second right-turn lane. To make sure motorists anticipated
the changes, the Indianapolis Department of Public Works posted
600 new signs downtown, on heavily traveled corridors, and as far away
as 11 to 13 kilometers (7 to 8 miles) northeast on the restricted left turns.
"The media was key in helping people understand the
necessary changes," Whitmore adds. "The
Indianapolis Star, for example, put together a special section on
the city street changes just weeks before the project."
Running Smooth Detours
Preparing for the project, INDOT and FHWA were determined to
minimize disruption to the traveling public. The I–65/70 corridor,
just east of downtown, is not only a major gateway to the city but also
a heavily used route for commuters and through traffic.
"The traffic pattern in Indianapolis is commuter-driven so we
looked at ways to inform the motoring public and identify alternate
routes," says INDOT Operations Engineer
Jay Wasson.
 |
| Workers prepare to place bridge deck overlays.
|
The State's Traffic Management Center, the Indiana State Police,
and INDOT's freeway service patrol operators, known as Hoosier
Helpers, collaborated to keep traffic flowing smoothly. Throughout the
project, downtown commuters could use all but one of the exits on either end
of the closure. INDOT directed national and regional traffic onto the
construction-free outer beltway (Interstate 465). Starting 16 kilometers
(10 miles) outside the I–465 beltway and at key locations downtown,
INDOT erected the distinctive Hyperfix
65/70 signage directing traffic around the construction zone.
Also, INDOT repositioned several portable message signs in conjunction
with the overhead dynamic message signs to convey real-time information
to the motoring public about possible congestion.
City officials and INDOT used demand management to
control congestion. Many businesses in the downtown area, for example,
staggered their work hours or encouraged employees to carpool. To
minimize noise concerns, INDOT met regularly with downtown
residents, businesses, and employees to advise them on the progress of the project.
As the start date approached, INDOT and its partners
implemented other precautions to ensure smooth traffic flow but soon
discovered the additional efforts were unnecessary. For example, the
State budgeted $100,000 in overtime for police, mainly to direct traffic
downtown. But after 3 days into the project, motorists had adjusted
to the detours and other factors, and the extra police presence was
no longer necessary. Similarly, the city established an emergency
communication center to handle traffic tie–ups or other difficulties but closed
the center after 48 hours when the tie-ups never materialized.
"This is a tribute," says INDOT Commissioner Nicol, "both to
the preparations of the Federal, State, and local public works team and
to the response of the area commuters."
 |
| A construction worker smoothes the concrete for the new highway during
the Hyperfix 65/70 project.
|
Coordinating Public Transit
To alleviate congestion and offer an alternative for commuters heading downtown, the local transit agency, IndyGo, established the first
park-and-ride program in Indianapolis. The FHWA Indiana
Division, IndyGo, INDOT, the Indianapolis Department of Public Works,
and the Indianapolis Metropolitan Planning Organization all
collaborated on the planning. FHWA approved the use of $1 million in funds
from the Congestion Mitigation and Air Quality (CMAQ) Improvement
Program to support the Hyperfix Park & Ride project from May
through the end of 2003.
One week before construction began on Hyperfix 65/70,
IndyGo launched the park-and-ride program. The transit company turned to
a private vendor to supply 18 buses seating 45 to 55 passengers each
to transport commuters from three locations in the northeast
quadrant the area most affected by the closure to three downtown
drop points. The touring buses featured reclining seats, onboard
restrooms, mini-tables for laptops, and cup holders for coffee. Buses ran
from 6a.m. to 7 p.m. weekdays and every 15 minutes during rush hours.
According to Gilbert Holmes, IndyGo's chief executive officer, between
550 and 600 riders were using the bus service at peak ridership.
 |
| A worker sets up a form for concrete placement on a bridge
deck approach.
|
"This transit project is a marvelous example of partnership with
FHWA, INDOT, the Indianapolis Department of Public Works, and the
Indianapolis Metropolitan Planning
Organization," Holmes says. "We all joined
hands and said, 'Let's make this happen.'"
The spirit of cooperation also extended to the private sector,
including a transportation vendor who supplied buses on short notice
and parking facility owners who allowed commuters to park in their lots.
Two shopping centers and Fort Harrison, a former military establishment
that is now a private community, permitted commuters to use their
parking facilities so that IndyGo did not have to acquire and prepare
additional property for parking.
"This is an incredible community project demonstrating the value
of public transit and that people want it to happen," Holmes adds.
 |
| Another worker gathers rebar for an approach slab for a bridge deck.
|
Closing for Construction
The schedule was ambitious. The combined I–65 and I–70
highway closed for construction on May 26, 2003. Repairs took place 24 hours
a day, 7 days a week. For the first half of the job, the contractor
performed pavement removal. Then, after preparing the base for the
northbound lanes, the contractor began pouring concrete and flipped over to
the southbound side. During the demolition stage, the contractor
employed up to 100 people on the payroll, plus the subcontractors' laborers
onsite. The paving required 73,600 square meters (88,000 square yards) of
concrete pavement and 31,700 metric tons (35,000 tons) of asphalt.
Because the full section was closed, the contractor was able to work on up to
20 bridge structures simultaneously.
"The oversight was challenging for our staff," says Tim
Conarroe, INDOT project engineer. Twenty-four oversight people covered
the two 12-hour shifts. The oversight personnel worked 6 days;
then INDOT pulled in employees from the outlying areas to cover
the seventh day. In total, Conarroe counted 43 INDOT
employees sharing the work of overseeing the project. INDOT oversight
totaled 31,680 hours for the 55-day, 1,320-hour project.
The contractor earned a $3 million incentive ($100,000 per
day) for the 30-day early finish. "Our contractor achieved the early finish
date by the tremendous human resources and excellent organization of
work activity," Conarroe says. "Another key was the
excellent working relationships between INDOT, our
general contractor, and all the subcontractors. Everything
went smoothly without delays or hang-ups for decisionmaking."
Hyperfix 65/70 actually was Phase 2 of the total project. In Phase 1,
the contractor assured reliable access to downtown by rehabilitating the
interchanges on either end of the project in the traditional way,
one lane at a time. This work lasted from March 28 to May 2, 2003. Phase
3, adding an additional lane on the connecting ramp from eastbound
I–70 to southbound I–65 and pavement patching on the
collector ramps, began on July 30 and continued through August 30.
Generating Community Outreach
Early on, INDOT educated the news media about the repair work, why
it was necessary, how it was going to be done, and what the
motoring public needed to know to minimize the negative impact of the
closure. Acting on guidance from a public relations firm, INDOT decided
to "brand" the project by developing a name, logo, and other easily
identifiable markings to use on highway signs, public transit, and
printed materials.
In January 2003 the public relations agency began a
community outreach campaign involving media interviews and notices, public
meetings, advertising, displays at local rest stops, and distribution of 5,000
map pads and 250,000 maps showing recommended alternative routes.
And, on April 10 State workers began erecting posts to display the
Hyperfix 65/70 signage, which shows a running construction worker.
The press releases stressed the lower costs associated with an
accelerated timetable and noted the safety advantages of a shutdown
to both commuters and workers. The press releases also promoted
the long-term benefits such as improvements in traffic flow and
patterns that would serve the needs of Indianapolis residents for many years
to come. The Indianapolis Star
polled area residents asking their opinions on a complete shutdown of
the facility to permit quick repairs versus a longer project with
partial closures. By a 2–1 margin, residents indicated a preference for closure.
"Because we partnered with the news media throughout the
process," Commissioner Nicol says, "that first day we did not have
the gloom and doom gridlock with the whole city shut down.
People changed their travel behaviors, and it was a huge success."
Project Timeline
INDOT's Hyperfix Web site featured a project timeline to keep
the public notified of progress at a glance. With each new stage,
INDOT moved the arrow indicating completed stages in green, and stages
to be completed in red.

The site also included an explanation of the activities that
would occur at each stage and projected calendar dates for completion:
- Planning—Evaluating the best possible solution to
achieve efficiency and effectiveness.
- Design—Developing the working plans that will constitute
the scopeor magnitudeof the project.
- Letting—Preparing all the necessary paperwork and
awarding the contract to the lowest qualified bidder. This project was let
on January 22, 2003.
- Pre-Closure—Preparing to close I–65/70. All lanes were to
remain open to normal traffic between the hours of 6:00 a.m. and
9:00 p.m., though some lane restrictions might be necessary. All
work was completed by May 21, 2003.
- Closure—Closing the mainline I–70 and I–65 roadways
between the north and south splits from May 26 through July 20, 2003.
- Post-Closure—Completing work such as pavement
patching, shoulder reconstruction, and ramp resurfacing of northbound
and southbound I–65 and eastbound and westbound I–70 in the
south split interchange area. The project was completed on
September 3, 2003.
|
Permanent Changes
"Hyperfix has been a catalyst for many good things," Nicol says.
Indianapolis retained the street improvements, for example, that added
capacity to West Street. Many of the restrictions on left turns and
parking have improved the traffic flow so well that they remained in
force even after completion of the Hyperfix 65/70 project, and
the public works department is evaluating making them permanent.
Buses still use the software that changes traffic signals to extend green
lights. And IndyGo and city leaders are encouraged by the increased
bus ridership, which continues above preproject levels.
"We have demonstrated the popularity of the park-and-ride
program, so we're seeking funding to continue it and extend it to other
areas of Indianapolis," Holmes says.
According to Whitmore, the word "Hyperfix" has become
a household term for Indianapolis residents, conveying the notion
of an efficient fix or repair. Because the public responded so
well, INDOT may use the name again for future projects of this
magnitude. "Hyperfix has become part of the local language as our residents
apply it to different situations," he says. "I saw a sign in a sports
shop the other day noting, 'Let [us] Hyperfix your
game.' "
Gerard (Gary) Mroczka, P.E., manager of special projects at
INDOT, worked on planning the Hyperfix 65/70 project from the start.
He currently serves as INDOT's division chief of design. Mroczka can
be reached at 317–232–5226 or gmroczka@indot.state.in.us.
Valdis (Val) Straumins is the field operations engineer with the
FHWA Indiana Division and the FHWA liaison for the Hyperfix 65/70
project. He participated in all aspects of the project. Straumins can be reached
at 317–226–7479 or valdis.straumins@fhwa.dot.gov.
Jim Pinkelman was formerly
senior public affairs officer in the FHWA Office of Public Affairs. He
is now deputy director for communications in the U.S. Department
of Justice's Office of Justice Programs in Washington, DC.
INDOT's Division of Research, in collaboration with Purdue
University, prepared a report on Hyperfix that will be available to
other States by early 2004. For more information, visit the Hyperfix
Web site at www.in.gov/dot/div/specialprojects/hyperfix.
Other Articles in this issue:
Hyperfix 65/70
Coordinating Incident Response
Erosion Control with Recycled Materials
Glenwood Canyon 12 Years Later
A Tale of Two Canyons
Spotlight on the South
The AIRS Approach to Analyzing Intersection Crashes
Resource Center Goes National