March/April 2004
A Tale of Two Canyons
by Steve Moler
Colorado DOT applies
lessons learned from the Glenwood project to a similar
highway in the Snowmass valley, near the famed Aspen ski resort.
The Colorado Department of
Transportation (CDOT) knows
a thing or two about building highways through complex
terrain. In 1992, CDOT completed an award-winning project that extended
I–70 through Glenwood Canyon, finishing the last section of an interstate
that stretches from Baltimore, MD, to Cove Fort, UT. The project later
received the 1993 Outstanding Civil Engineering Achievement
Award from the American Society of Civil Engineers and is considered one
of the greatest highway engineering accomplishments in U.S.
transportation history. (See "Glenwood Canyon 12 Years Later".)
Not one to rest on its laurels, shortly after finishing
Glenwood Canyon the CDOT began planning a project in Snowmass Canyon
56 kilometers (35 miles) away. The Glenwood and Snowmass
projects are remarkably similar. Both involve upgrading overburdened
two-lane highways to four lanes through extremely narrow, ecologically
sensitive canyons to improve safety and mobility while minimizing
environmental impacts. "Both required exceptional planning, the latest in
context-sensitive design, and construction ingenuity," says Ralph Trapani, the CDOT project manager on
the Glenwood Canyon project, now a private consultant.
The project in Snowmass Canyon, which began in September
2000, applies the lessons that CDOT learned in Glenwood to upgrade
a section of highway northwest of the ski resort town of Aspen. The
$100 million project consists of widening 5.6 kilometers (3.5 miles) of
State Highway (S.H.) 82 through Snowmass Canyon, a narrow valley carved
by the Roaring Fork River. Like Glenwood Canyon, the
Snowmass Canyon project involves building two roadwaysone virtually on
top of the otheralong steep, geologically unstable slopes using a
terraced system of retaining walls and bridges to minimize environmental impacts.
|
|
(Above) While the up-valley lanes took shape in Snowmass
Canyon during the summer of 2003, the old two-lane highway to the right
carried traffic one way up the valley. The two-lane county road across the
river to the right carried westbound traffic down the valley.
Photo: Joseph J. Kracum, Kracum Resources, LLC.
|
|
Cross-Sectional View of the Snowmass Canyon Project
A. After workers install fences (yellow poles) to preserve the environment, construction begins
with vertical cuts into the hillside (upper right) for the
up-valley lanes. Soil-nail walls using
corrosion-proof steel bars are installed to stabilize the slope.
Then the construction crew members install
reinforced steel and anchor plates and spray shotcrete onto
the vertical surface to complete the reinforced system.
B. The process is repeated as the crew installs
a second set of retaining walls into the hillside.
Mass excavation is necessary to reach the bottom of
the footing elevation for the walls that support
the roadway.

C. Shafts are drilled vertically into the bedrock
and filled with reinforced concrete. The workers
then construct a reinforced concrete footing at the top
of the shaft and drill through the footing to the
bedrock to place the tieback ground anchor. This system
of compression and tension handles the extreme
forces that act on the earth retaining system.

D. An architecturally finished precast panel is
placed vertically on the footing. Reinforcing,
structural backfill and embankment then are placed on
top. Pavement, traffic signs, concrete barriers,
guardrails, and striping complete the up-valley lanes.

E. Construction on the down-valley lanes begins with excavation for the retaining wall
foundations (lower left). The crew places the precast wall
panel vertically on the footing, and reinforcement grids
are attached to the panel. Structural backfill
material placed and compacted in lifts helps form the
mechanically stabilized earth wall, and embankment material is placed next. Finally, pavement,
traffic signs, concrete barriers, guardrails, and striping
are added to complete the down-valley lanes.
To view an animated slideshow of this cross-sectional sequence, visit www.sh82.com/snowmasscanyon.html.
|
|
|
This drawing illustrates how the terraced system enables CDOT to construct
a four-lane divided highway through the narrow canyon.
|
Saving the Hardest for Last
Snowmass Canyon represents the final section of roadway in a
three-decade-long project to upgrade S.H. 82 from two to four lanes
between Glenwood Springs and the Aspen area. As with Glenwood
Canyon, which was the final segment of I–70 to be completed, the
Snowmass Canyon section of the S.H. 82 upgrade was saved for last because
it encompassed the route's most difficult environmental, engineering,
and financial challenges.
On October 14, 1992, the day CDOT cut the ribbon opening
the Glenwood Canyon project, many of the project's planners, designers,
and engineers turned their full attention to the difficult section of S.H.
82 between Basalt and Aspen, which contains the Snowmass Canyon
segment. This 27-kilometer (17-mile) stretch of highway through some
of the most scenic and majestic countryside in the United States had
become one of Colorado's most dangerous two-lane highways for
many of the same reasons that Glenwood Canyon attained a similar status
a decade earlier. Undercapacity, high traffic volumes, sharp curves,
narrow lanes and shoulder widths, lack of acceleration and deceleration
lanes, and inadequate sight distances for passing eventually earned S.H.
82 the grim nickname "Killer 82."
By late 1992, CDOT had published a draft environmental
impact statement for the section starting just east of Basalt and ending
near Aspen. But CDOT and the Federal Highway Administration
(FHWA) ultimately published a final environmental impact statement in
October 1993 that covered the section from just east of Basalt to the
Buttermilk ski area just outside Aspen. Upgrading the section inside the town
of Aspen was considered in a subsequent environmental impact
statement for the entrance to Aspen.
|
|
Before (top) and after (bottom) renderings illustrate how CDOT
is constructing a four-lane divided highway through the
narrowest possible footprint to minimize environmental impacts.
Photos: CDOT. |
Finding a Preferred Alternative
The primary debate over roadway alignments focused on whether
to construct a one-way couplet for down-valley westbound traffic
on the side of Roaring Fork River opposite the existing S.H. 82
through Snowmass Canyon. The new alignment would roughly parallel an
existing railroad right-of-way. The up-valley eastbound traffic would
use the old S.H. 82 roadway. Although this alternative would have
saved millions in project costs, CDOT eventually rejected it because of
the adverse impacts on wildlife and property owners along the
proposed right-of-way.
As the preferred alternative, CDOT and FHWA selected an
alignment slightly higher up the canyon slopes from the existing highway, because
it would have the least environmental and social impacts. The chosen
alternative forced planners and designers to face the same predicament
they had experienced with Glenwood Canyon: how to cram four lanes of
roadway into an extremely narrow footprint,
bordered by a river on one side and steep canyon slopes
on another, without harming the environment.
"The solution was challenging," says Joe
Elsen, CDOT's manager for the Snowmass Canyon
project. "We were fortunate to be able to apply our knowledge
and experience from Glenwood to the Snowmass Canyon site."
During the drafting of the environmental impact statement,
local county officials and the public wanted to evaluate transit options
in addition to the four-lane highway. Five intermodal alternatives
were developed, including a no-build option that served primarily as
a baseline for evaluating the other alternatives. The preferred
alternative provides for bus and high-occupancy vehicle lanes in some
sections, bus park-and-ride facilities, a multimodal transfer station at
the Buttermilk ski area, and a future commuter rail corridor that
currently is under study.
|
Snowmass Video Facilitates Technology Transfer
"The construction of I–70 through Glenwood Canyon, CO, is a marvel
of innovation in highway design and construction," says Ron Speral, a
program delivery engineer in FHWA's Colorado Division who served as an
operations engineer during the Glenwood project. A series of videos highlighting
the project's numerous planning, design, environmental, and construction
innovations brought these achievements home to many in the profession of
civil engineering.
Joe Elsen, the CDOT manager for the Snowmass Canyon project,
previously worked as an engineer on Glenwood Canyon. Elsen's experience with
the videos of the Glenwood project provided the impetus to film the
construction in Snowmass Canyon. The video enables the Snowmass team to
share with a wider audience the technological innovations used to reconstruct
the section of S.H. 82 near Aspen.
"Being involved with the videos," Elsen says, "and knowing how
often requests came in for them made me realize just how effective this
medium is for transferring technology."
Elsen describes video as the ideal medium for encapsulating the
technology because it not only appeals to a broad audience of decisionmakers
who need the information, but it also helps viewers visualize the technologies
and their applications. Elsen imagines an engineer watching the video and
thinking: "There's our solution. Why reinvent the wheel?"
The 25-minute video focuses on how CDOT and its consultants and
contractors are using innovative construction techniques to overcome the challenges of
building a four-lane divided highway through a
narrow, environmentally sensitive corridor. Among
the techniques featured are mechanically
stabilized earth walls that combine precast panels
with geogrids and recycled structural backfill
that combines alluvial and colluvial soils to
avoid waste. Other technologies include precast, post-tensioned double-T walls, tieback and
soil-nail walls, micropiles for shoring precast L-walls, and geotechnical instrumentation
that ties all the systems together.
Viewers will see how the geotechnical designer employed innovative analysis
techniques, how the contractors planned their operations given limited access, and how
they handled value-engineering change proposals, an administrative process that allows a
contractor to bring innovative ideas and solutions
to the project beyond what was originally contracted.
Produced by a company in Glenwood Springs, CO, the video is offered in both VHS and
DVD formats and serves as a learning tool and historical record of the project's achievements.
For more information about the Snowmass Canyon project or video, contact Joe Elsen
at joseph.elsen@dot.state.co.us.
|
|
A precast concrete panel with attached geogrid forms one of the project's mechanically stabilized earth walls. |
|
Geotechnical Complexities
Although Glenwood Canyon is almost four times longer,
Snowmass Canyon arguably is more complicated, at least from a
geotechnical standpoint. After more than 2 years of geotechnical studies and
analysis, CDOT decided to construct more elaborate and complex soil-nail,
tieback, and double-T walls using various types of post-tensioned
ground anchors embedded in the bedrock to stabilize the hillsides. The
department is building these earth retaining systemssome as long as
1,200 meters (4,000 feet)on both the up-valley and down-valley lanes.
In all, the project includes 6 bridges and some 42 earth retaining systems.
"Anything that's considered state-of-the art from a
geotechnical standpoint we're doing on this project," says CDOT project
engineer Pete Mertes. "We have a great team of experts making
this project a success."
|
|
A precast architectural panel covers a soil-nail wall.
|
|
|
A double-T retaining wall takes shape in
September 2002 at the approach to Bridge No. 2, one of
the project's two 290-meter (950-foot) bridges.
|
Environmental Protection
The project's strategies to protect the environment rival and in
some cases exceedthose employed in Glenwood Canyon. "CDOT has
gone to great lengths to align the new highway based on established
deer and elk migration routes," says Elsen.
Two of the project's six bridges are designed strictly as game
crossings, allowing deer and elk to pass underneath the highway at
ground level. An elaborate management system for storm water and a
plan for controlling erosion are among the many measures CDOT is
employing to help maintain the integrity and health of the Roaring Fork
River and preserve its riparian zones.
"In Glenwood Canyon, the reconstruction required that we fix
the banks of the Colorado River that were denuded or constructed
hastily using rip-and-tear techniques," Elsen says. "But with Snowmass, we
were able to avoid touching the Roaring Fork River."
Tree preservation is a major component of environmental
preservation, as it was in Glenwood Canyon. CDOT designed much of the
up-valley alignment to avoid as many stands of larger, more mature
trees as possible. The space between the up-valley and down-valley
lanes stands as an environmental island of untouched trees and
vegetation. Disturbed areas will be replanted with native vegetation to return
the canyon to its original condition.
With respect to recreation, CDOT took a page out of
Glenwood Canyon's playbook, providing bicyclists with 2.5-meter
(8-foot)-wide shoulders along the roadway for safe cycling. CDOT also
created pedestrian access to the river at various points.
|
|
In August 2003, the up-valley lanes were near completion. Since
this photo was taken, traffic has been diverted to the now-completed
up-valley lanes. |
Traffic Mitigation
One advantage at Snowmass Canyon that CDOT did not enjoy
in Glenwood was access to an alternate route to detour traffic during
construction. In Glenwood, traffic had to be stopped for 30 minutes
on average to allow construction crews to work because there was
simply nowhere to divert traffic.
In Snowmass Canyon, during construction of the up-valley
lanes (those at higher elevations), CDOT could divert one lane of traffic
from S.H. 82 onto a county road located on the other side of the
Roaring Fork River. Traffic going in the opposite direction could use one lane of
S.H. 82. This arrangement not only reduced the number and length
of traffic delays but also gave construction crews more room and
flexibility to work.
With the up-valley lanes now complete and handling all
two-way traffic, the detour is no longer necessary. Construction of the
down-valley lanes is in full swing. When CDOT completes the project as
early as fall 2004, 1 year ahead of the original contract completion
date, perhaps the improvements in Snowmass Canyon will lead
motorists to consider changing the highway's nickname from "Killer
82" to "Son of Glenwood Canyon."
|
|
Bridge No. 2 is shown under construction in September
2002. Traffic passes by the new bridge traveling on the old S.H. 82 on
the right.
|
Steve Moler is the public affairs specialist at FHWA's Resource
Center office in San Francisco.
Susanna Hughes Reck, the technology deployment specialist
at FHWA's Lakewood, CO, satellite office of the Resource Center office
in San Francisco, assisted with the sidebar on the video project
for Snowmass Canyon.
For more information about the project in Snowmass Canyon,
visit www.sh82.com/snowmasscanyon.html.itates Technology Transfer
Other Articles in this issue:
Hyperfix 65/70
Coordinating Incident Response
Erosion Control with Recycled Materials
Glenwood Canyon 12 Years Later
A Tale of Two Canyons
Spotlight on the South
The AIRS Approach to Analyzing Intersection Crashes
Resource Center Goes National