November/December 2004
Work Zones That Work
by Carol Keenan
With workers and motorists at jeopardy and motorists
frustrated by unexpected delays, the operational perspective
of work zone management is the present focus.
|
| This congestion is typical of approaches to work zones and is a frequent cause of motorist dissatisfaction. |
Much of the Dwight D.
Eisenhower National System
of Interstate and
Defense Highways is more than
30 years old, and new roads continue
to be built, making it a challenge
to maintain this constantly
expanding infrastructure. Add to the
mix limited budgets, more road usage
during nonpeak times, road materials
lasting only about 30 to 40
years, and the explosion of growth,
and it is easy to understand the tremendous
undertaking that faces the
transportation community in maintaining
the highway network.
Understandably, instead of concentrating
on new construction, transportation agencies increasingly
focus and spend funds on preserving,
rehabilitating, and maintaining
existing roads. About 13 percent of
the National Highway System was
under construction during the summer
of 2001, with approximately
3,110 work zones. While these work
zones are necessary to maintain and
upgrade the Nation's aging highway
infrastructure, they also reduced
capacity by 33,610 kilometers
(20,876 miles) of roadway.
At the same time, vehicle travel
continues to increase significantly
faster than the addition of new miles
of roadway. Over the last 20 years,
route miles of highway increased
approximately 5 percent, while vehicle
miles of travel grew by about
79 percent. In economic terms, the
demand far exceeds the supply.
Work zones further exacerbate the
situation because they add to the
growing congestion problem. Roadway
usage during nonpeak times
makes the window to perform roadwork
without severely affecting
traffic smaller and smaller. Transportation
agencies must perform more
roadwork under heavier traffic conditions,
often in less time.
"The transportation community
must achieve a balance between
construction needs and the safety
and mobility needs of the traveling
public," says the Federal Highway
Administration's (FHWA) Associate
Administrator for Operations Jeff
Paniati. "It is important to develop
comprehensive mitigation measures
that minimize the impacts of work
zones and ultimately improve transportation
mobility and safety."
Cause for Concern
Given the combined trends of more
highway improvement projects and
more congestion, the American
public is becoming increasingly frustrated with work zone delays.
FHWA research shows that the
traveling public is demanding
increased mobility, while showing less
tolerance for delays, increased travel
times, and inconveniences resulting
from construction-related congestion.
Unlike congestion caused by routine
heavy traffic during daily peak
travel periods, nonrecurring events
generally result in unexpected travel
delay and motorist frustration. Work
zones accounted for about 10 percent
of all delays annually, or 482
million vehicle hours in 1999. As
congestion builds approaching work
zones and within them, safety degrades,
and the crash rate increases.
The most frequent type of incidents
in work zones are rear-end crashes
due to unexpected queuing.
The public's frustration with
work zones is evident from the results
of a 2000 nationwide survey
report by FHWA titled Moving
Ahead: The American Public Speaks
on Roadways and Transportation
in Communities. The report cited
work zones as second only to poor
traffic flow in causing dissatisfaction.
In the survey results, the public
indicated that the top three roadway
and transportation improvements
that would be a "great help" relate to
repairs and work zones: 67 percent
of the respondents chose more durable
pavement materials, 66 percent
chose repairs made during nonrush
hours, and 52 percent chose reducing
repair time. Many travelers indicated
a preference for closing roads
completely for moderate durations
in exchange for long-lasting facilities.
The survey responses are a compelling
call to action for finding ways to
make transportation work zones
work better.
Statistics show that work zones,
in addition to causing delay, can be
dangerous for construction crews
and motorists. Work zone fatalities
increased nationwide by 17 percent
over the last 5 years. In 2003, there
were 1,028 fatalities and more than
41,000 injuries that resulted from
motor vehicle crashes in work
zones. Four out of five people killed
were either motorists or passengers.
"Work zone crashes pose tremendous
costs to society," says Administrator
Mary E. Peters of the Federal
Highway Administration (FHWA). "The human cost is the most tragic
and the most critical. But there is
also the economic cost that results
from congestion, unexpected delays,
and delayed freight deliveries. One
FHWA commitment is to make work
zones safer and improve mobility in
and around them."
Real-Time Communications For Work Zones
The traveling public has shown substantial
capacity for planning around
work zones—if they know about
them. Motorists want information
they can trust, and they want it far
enough in advance to make reasonable
travel decisions. The challenge
for the transportation community is
to increase the use of innovative
strategies and a policy-driven focus
to mitigate the impacts caused by
work zones. Current strategies include
providing general construction
information on Web sites, using innovative
construction and contracting
strategies, and applying intelligent
transportation system (ITS)
technologies to improve the performance
of work zones.
Accurate, real-time travel information
on work zones is essential for
time-starved motorists, freight haulers,
and tourists. ITS technology
provides the underpinning infrastructure
for delivering that information
continuously and automatically.
"Real-time traffic management
and travel information should be an
integral part of highway construction,"
says Paniati. "It should be unacceptable
to operate work zones
without regard to the customer's
need for information and guidance."
As the 511 traveler information
telephone service is implemented
and becomes more available across
the country, detailed information
will be accessible for anyone with a
phone, enabling motorists to plan
for the inconvenience of delays and
remain in control of their own
schedules. Increasingly, the 511 service is providing the real-time
information necessary to choose
alternate routes, times of day for
travel, or the option to telecommute.
Final Rule on Work Zone Safety and Mobility
The Federal Highway Administration (FHWA) recently updated its regulation that governs
traffic safety and mobility in work zones on highways and streets (23 CFR 630 Subpart J).
The final rule was published in the Federal Register (69 FR 54562) on September 9, 2004.
The purpose of the update is to address the challenges of more work zones and increased
congestion, while ensuring the safety of motorists and construction workers. The
changes to the regulation will facilitate comprehensive consideration of the broader safety
and mobility impacts of work zones through a project's life cycle and the implementation of
strategies that help manage these impacts.
"The new provisions will help State departments of transportation meet current and
future challenges in work zone safety and mobility, and serve the needs of the American
people," says Scott Battles, FHWA's Work Zone Mobility and Safety Team Leader.
Overview of the New Rule
FHWA broadened the regulation to include the following key features:
- A State-driven focus that will institutionalize work zone policy, processes, and procedures
at the State level.
- Emphasis on addressing the broader impacts of work zones on travelers and workers by
developing transportation management strategies that address traffic safety and control
through work zones, and by effective transportation operations and public information
and outreach.
- Emphasis on a partner-driven approach, whereby transportation agencies and FHWA
work together improving safety and mobility in and around work zones.
Learn More
The effective date for the new rule is October 12, 2007. For more information, visit
www.ops.fhwa.dot.gov/wz/resources/policy.htm or contact a member of the Work Zone
Mobility and Safety Team at 202-366-6993 or WorkZoneFeedback@fhwa.dot.gov.
|

 |
| This traffic flow indicators map from the Arkansas I–40 Web site provides real-time information to the traveling public. |
Another method for communicating
information is Web sites, which
also can provide traffic flow maps
with the location of congestion in
real time so motorists can better plan
their trips. A review of State road
closure and construction Web sites
reveals that project location, purpose,
and overall duration are likely to be
posted early in the planning process,
but the posting is unlikely to be updated
often. A current shortcoming:
information of greatest interest to the
traveling public, such as number of
lanes closed, times of closure, and
estimated delay, is reported only
about 6 percent of the time.
States are refining their use of
information posted to project Web
sites. "We learned that people are
interested in the most updated information,"
says New Jersey Commissioner
of Transportation John F.
"Jack" Lettiere. New Jersey plans
to update a Web site for a project
extending Route 18 into New
Brunswick, NJ. The department of
transportation (DOT) and the New
Jersey Turnpike Authority Traffic
Operations Center plan to post realtime,
current information within 4
minutes of any change. Commenting
on the use of real-time information,
Lettiere says, "We've done it on
other projects, but this one is much
more complex." The Web site and
real-time traffic information would
help commuters and students at
nearby Rutgers, The State University
of New Jersey, deal with this construction
project.
Similarly, the North Carolina DOT
used ITS technologies in a number
of interstate work zones to manage
traffic. Sensors were used to calculate
either delay or travel time. That
information then was used to display
messages on variable message signs
(VMS) and/or Web sites. For example,
on I-95 outside Fayetteville,
when delay was greater than a preset
threshold, estimated delay and an
alternate route were displayed on
VMS. This allowed motorists to
choose to use the alternate route
and reduce congestion and queuing.
In 2000, the Arkansas State Highway
and Transportation Department
(AHTD) reconstructed 5 kilometers
(3 miles) of concrete
pavement on I-40 near its intersection
with I-55 in West Memphis,
AR. The work zone area began near
a bridge across the Mississippi
River to Memphis, TN, and abutted
a Tennessee work zone on the
bridge. Officials from AHTD believed
they needed to go beyond
traditional traffic control in addressing
the impact of the reconstruction
project and looked for
ways to communicate with the
public in both Arkansas and Tennessee about specific delays to
expect from the construction.
According to AHTD Chief Engineer
Robert Walters in FHWA's Intelligent
Transportation Systems in
Work Zones: A Cross-Cutting Study
report, "Prior to reaching the construction
area, motorists have a
choice of routes to take, either I-40
or I-55." An automated information
system acquired data on traffic conditions
approaching the work zone
and processed that information to
inform travelers of the length of any
queues ahead as they approached
the work zone on I-40. To enable
drivers to choose alternate routes
that would reduce delay, real-time
information was displayed on dynamic
message signs strategically
placed before key alternate routes
and updated automatically by the
system as conditions changed.
"The ITS advised travelers of any
problems on the routes and helped
them make the most informed decision
possible at the time," says
Walters. "Local residents are familiar
with alternate routes, and the ITS
information helped them readily
decide which route to take. Motorists
traveling cross-county, however,
may not readily know alternate route
options, but the ITS [communicated]
what to expect in terms of traffic
backups and delays."
Highway advisory radio was another
communications tool, which
broadcast current traffic condition
information to listeners. Not only did
this project enhance relationships
with residents by keeping them
informed, but also it helped improve
the interstate relationship with
neighboring Tennessee and residents
who were affected by the work
zone west of Memphis just over the
border in Arkansas.
The planning in Arkansas for
traveler information may be the
exception to the rule when it comes
to ITS use. Minor applications of ITS
technologies to improve work zone
performance are typical. As in
Arkansas, however, ITS use in work
zones can go well beyond dynamic
message signs. It can integrate a
variety of traffic monitoring,
reporting, and management systems
to improve system operations.
ITS also provides a unique solution
to controlling traffic at merge
points. State-of-the-art dynamic lane
merge systems are becoming increasingly
popular because they provide a
real-time solution to aggressive driving
and safety problems at work
zone tapers. Industry is making
strides in packaging and tailoring
technologies to work zone situations,
and ITS is becoming more
widely accepted as providing real,
sometimes off-the-shelf, solutions
to mitigate work zone impacts.
Road Closure Strategies
Growth in the number of improvement
projects on roadways that are
open to traffic is a concern to highway
professionals. Increasingly
high traffic
volumes on many highways
make it difficult to
perform work operations
in or near travel
lanes during much of
the day because of the
risk for workers and the
traveling public. In response,
scheduling
highway work for
offpeak periods has
become commonplace.
Nighttime construction
reduces the impact to
peak-period traffic,
while accomplishing
necessary roadway improvements.
 |
| Crews work without interruption on a closed section of I–84 (Banfield Freeway) in Portland, OR. |
Nighttime construction
techniques are
fairly common in the
United States and
abroad, with more than
one-quarter of work
zones primarily active
at night. This scheduling
option can be
adopted by agencies as
a means to increase the
efficiency of peak hour
travel. However, emphasis
should be placed on special
considerations for worker and traveler
safety in nighttime work zones
such as enhanced traffic control
devices, visibility of works, visibility
of work vehicles, controlling speed,
increasing driver awareness, providing
glare-free illumination; and accommodating
pedestrians. (See
"Improving Traffic Control for Night
Work Zones" for
information about how to set up a
safe nighttime work zone.)
Other States such as Delaware,
Indiana, Kentucky, Michigan, Ohio,
Oregon, and Washington are using
a different strategy that was once
considered unthinkable—closing
roads completely. Full road closure
alleviates the potential for long-term
traffic congestion and improves
safety by reducing crashes and other
incidents. In the full-closure strategy,
the roadway is closed, traffic
rerouted, and the contractor given
full access to the roadway. Full closure
strategies are used to help
reduce the construction period,
improve quality, increase safety by
reducing traveler exposure to complex work zones, and separate
the road worker from the hazard of
freeway traffic.
Although closing a road completely
may appear to be a drastic
measure, the benefits may outweigh
the possible inconvenience and complications
when used in appropriate
situations. "Under the appropriate
conditions," says Ohio DOT Director
Gordon Proctor, "a full closure can
be an effective way to complete
projects faster and improve safety
for highway workers and motorists."
In an applicable situation with
adequate alternate routes available, a solid traffic management plan, and a
public outreach campaign, full closure
can reduce overall project duration
significantly and is a viable alternative
to traditional part-width
reconstruction. ODOT recently completed
a full-closure project on I-670
in Columbus. Originally, ODOT allocated
4 years for the project. Full
closure enabled the contractor to
finish the project in 18 months, a
63-percent time reduction over predicted
duration. ODOT realized an
estimated $8 to $10 million cost
savings, greater workspace, increased
productivity, and positive
public sentiment.
In a project dubbed "Hyperfix 65/
70," the Indiana DOT successfully
used full closure in 2003 to expedite
rehabilitation of I-65/70 in Indianapolis.
(See PUBLIC ROADS March/
April 2004.) What INDOT estimated
would take 180 days using traditional
part-width construction was
completed in 55 days using full closure.
INDOT estimated that traditional
construction would have
added $1 million per day in lost
productive time to highway users.
Full closure is not the solution to
every problem, but in a 2003 report
Full Road Closure for Work Zone
Operations, FHWA concluded that
full road closures have become a
successful tool on deteriorating
roads for reducing the overall impact
of work zones. The full-closure
methodology is one that many agencies
are considering for required
road maintenance and rehabilitation.
In many cases, the benefits far outweigh
the costs as many full-closure
projects have resulted in increased
productivity, reduced project duration,
enhanced safety, and lowered
costs. The study found that for the
six projects examined, project duration
was reduced by an average of
76 percent compared with traditional,
part-width construction.
In addition to full road closures, a
number of other alternate closure
strategies are possible. For example,
some agencies and contractors use a
full-closure approach for an extended
period but not for the entire project,
while others perform full-closure
operations on weekends or at night
when traffic levels are lower.
Several agencies have adopted the
transportation community's popular
slogan, "Get in! Get out! Stay Out!" as a reminder of what needs to be
done to meet the expectations of
today's public.
Full-Closure Tips
The following guidance is from Full Road Closure for Work Zone Operations: A Cross-Cutting
Study published in August 2003. Additional information is available online at: http://www.ops.fhwa.dot.gov/wz/resources/publications/FullClosure/CrossCutting/its.htm#summary.
State highway agencies have used full road closure successfully on a variety of project types
ranging from full-depth reconstruction to bridge joint replacement with guardrail enhancements.
The projects examined during this research effort had varying characteristics and reasons for
using full road closure, while achieving similar positive results. Project personnel interviewed felt
that full road closure was able to improve the road rehabilitation process, creating efficiencies
that reduced project duration and in some cases overall costs, while improving safety. A consistent
theme, heard during interviews with project personnel, was the positive public sentiment that
resulted from the use of full road closure.
Why Use Full Road Closure?
Full road closure has the potential to:
- Expedite project completion
- Reduce the impact of construction on
travelers
- Maximize workspace available to the
contractor and increase productivity
- Reduce overall congestion resulting from
construction
- Improve safety for workers and travelers
- Reduce crashes in some cases
- Result in a smoother roadway
- Improve public sentiment
Benefits of Full Road Closure
The six projects examined for this study
experienced numerous benefits as a result of
using a full-closure approach.
- All projects in this study reported a
reduction in project duration.
- Two projects realized significant estimated
cost savings.
- For five projects, project personnel cited
traveler and worker safety as a benefit.
- Three projects reported a better quality
product.
- All projects reported that public sentiment
was positive.
- The increased workspace and flexibility in
project staging that are offered by full
closures often led to greater efficiency.
- Project personnel felt that worker productivity
improved due to less distraction
from traffic.
- All project sites noted that the impact of
construction on travelers was reduced.
Considerations Associated With Full Road Closure
- City/county agencies and personnel often
need to be convinced of the feasibility of
implementing a full closure strategy and the
potential benefits that can be realized.
- Full-closure projects typically are done
on an accelerated schedule. Contractor
and supplier ability to provide adequate
amounts of resources should be assessed
prior to letting the project.
- Meeting the project completion deadline is
particularly important when using full-closure
since this is often highly publicized as the
date when the road will reopen. Therefore
full-closure projects may carry additional
deadline pressure for those involved.
- Full-closure impacts on businesses can be
a factor and need to be considered in the
planning process.
- Full-closure projects often are scheduled on
a 24-hour work basis, so there is potential
for impacts to local residents, including
noise and light pollution.
- Increases to traffic densities on alternate
routes must be assessed, planned for, and
managed. Improvements or operational
enhancements to alternate routes may be
required.
Lessons Learned
- The public outreach component was a key
factor in the success of these projects.
- Lead-time is needed for increased planning
and outreach to stakeholders with regard to
the potential effects of road closures.
- Adequate alternate routes are a critical
factor in pursuing a full road closure approach.
For the study sites, congestion was
often less than expected, as a result of
good information dissemination. Two sites
related that after about 2 weeks traffic
redistributed on its own and balanced the
increased load on the network, at which
time a fair assessment of overall traffic flow
could be made.
- A solid traffic management plan, including
adequate signage about alternate routes,
is vital.
|
Worker Protection Strategies
On the morning of May 9, 2003, a
five-person work crew was filling
potholes on the Duke Street Bridge
over I-395 in Virginia. A motorist
struck the rear of another vehicle
slowing in the work zone, lost control,
and entered a right lane work
zone. A member of the crew was hit
and thrown off the overpass onto
I-395 northbound, where several
vehicles fatally struck him.
 |
| A movable barrier system like this one can separate traffic from workers and allow for enough capacity during peak periods. |
Incidents like this one in Virginia
indicate the importance of balancing
the need for traveler mobility
through work zones and the need
for adequate space, lighting, and the
work environment required to get
the job done safely for the public
and construction workers. Positive
protection—the use of devices such
as barrier separations that contain
and redirect vehicles—can reduce
the risk to workers and travelers
from vehicle intrusions. Use of truck mounted
intrusion alarms for the
work site can help as well.
With proper planning and adequate
specifications, other mitigation
strategies also provide dramatic
benefits. The continually changing
nature of work zones and the fact
that safe speed depends on roadway conditions make variable
speed limits (VSL)
in work zones particularly
useful. A field demonstration
was conducted
in Michigan with
promising results. An
additional field test is
planned for a Maryland
work zone. The projects
analyze variations in
speed and accompanying
driver behavior
(such as abruptly hitting
the brakes). The VSL
technology is used to
determine appropriate
speeds for work zones
and changes the speed
limits when conditions
change, such as traffic
flow, traffic speed,
weather, and the nature
of the roadwork. The
technology communicates
the speed change to drivers
using dynamic speed signs mounted
on trailers. Varying the posted speed
limits as the conditions in the work
zone change should result in increased
credibility of speed limits,
greater speed compliance, improved
safety, and improved compliance.
Quick Construction
On March 26, 2004, a tanker truck
carrying 45,420 liters (12,000 gallons)
of fuel oil crashed in Connecticut
and ignited a ferocious fire. A bridge on I-95 melted, threatening
to cripple one of the Northeast's
most important transportation corridors.
Tens of thousands of lives were
affected. Motorists needed to find
alternatives. New technologies and a
great deal of hard work by the Connecticut
DOT and contractors enabled
traffic to roll again in only a
few days. ConnDOT used the latest
in "quick construction" technology
to fast-track repairs. In this case, a
prefabricated steel bridge was assembled
and shipped to the site,
then lifted into place by crews working
overtime.
 |
| Not only is work zone safety a concern in the United States, the United Kingdom used this photo of a worker in a public campaign to increase awareness of work zone safety. |
Workers using precast pavements
that fit together, quick-curing concretes,
and machines that ensure
pavement is smooth before it dries
are additional examples of ways to
shorten highway construction times.
(See the May/June 2004 issue of
PUBLIC ROADS for more details about
precast concrete and other methods
for shortening the construction cycle.)
Innovative Contracting
Since the 1990s, FHWA has been
supporting the use of innovative
contracting methods. No longer is
cost the sole criterion that determines
the winning bid. FHWA research
indicates that construction
projects once tolerated as a fact of
life must now provide timely delivery
of a quality project with limited
road user and social impact costs.
Contracting procedures are used to reduce highway construction project
times. Benefits from reduced project
times include reduced traffic delays
and associated costs, fewer crashes
and injuries in and around work
zones, and lower capital costs for
maintaining traffic.
Innovative contracting techniques
such as A+B bidding is a cost-plus time bidding procedure that selects
the low bidder based on a monetary
combination of contract bid items
(A) and the time (B) needed to complete
the project or a critical portion
of the project. The intent of this
kind of bidding is to provide an
incentive for the contractor to minimize
delivery time for high-priority
and congested roadways by offering
incentives for early completion and
disincentives for late completion.
This strategy is best used when traffic
inconvenience and delays need to be
held to a minimum. The New York
State DOT found that contractors
bid, on average, 32 percent below
NYSDOT's estimated time and completed
the work ahead of schedule.
 |
| When variable speed limit signs such as this one are used to alert motorists to slowed or stopped traffic, the incidence of rear-end collisions occurring in work zones is reduced. |
Incentive/disincentive contracting
provides an opportunity for an
agency to enhance delivery through
improved accountability. Lane rental,
another form of innovative contracting
by which a contractor is charged
a fee for occupying lanes or the
shoulder to do contract work provides an incentive to minimize the
duration of a lane closure and keep
traffic moving.
Work Zone Analysis Tool—QuickZone
Providing transportation partners
with an analytical tool to assess
and manage work zone impacts is
another means of
fostering improvements.
A traffic impact
analysis tool
called QuickZone
enables practitioners
to quantify the
queue length and
user delay caused
by work zones. After
experiencing
significant delays
and frustrations at
work zones on I-80,
Pennsylvania DOT
District 10 engineers
used QuickZone to model future
work zone
configurations before
implementing
them. The
PENNDOT engineers
were able to
select work zone
configurations and
construction schedules
that met project needs while
minimizing impacts to the traveling
public. They identified the delay impacts
of alternate phasing plans
and alternate project staging (day
versus night, peak versus offpeak,
summer versus winter). QuickZone,
which supports tradeoff analyses
between the costs of construction
versus delays, can be used to help
establish work completion incentives
and to assess the impacts of
travel demand measures and other
mitigation strategies.
 |
| This warning sign alerts motorists to a work zone ahead. |
From the reduced number of
complaints and the comparatively
shorter length of time motorists
experienced delays in the work
zone, PENNDOT believes the effort
was a success. "Based on what we
saw occur on the interstate last year
and compared to this year," says
PENNDOT District 10 Executive
Richard H. Hogg, P.E., describing the
State's before-and-after experiences
with QuickZone, "the improvements
for our customers—the traveling
public—are significant."
In early 2005, a new version of
QuickZone is planned for release
(see "Resources"). Improvements
to this analysis tool will
include a graphical user interface for
network building; improved two-way,
one-lane operations modeling (for
example, flagger operations); improved
flexibility to model more
complex projects; enhanced detour
modeling; and the ability to track,
graph, and analyze a wider variety of
performance measures than was
previously possible.
 |
| The use of night construction, as shown here, is one measure to reduce travel delays from work zones. |
Making Work Zones Work Better
Business as usual is not acceptable
to motorists. The problems are growing
and are costly in terms of lives,
time, and money. Real solutions will come from a fundamental change in
the way projects are planned, estimated,
designed, bid, and finally
constructed. Communicating to the
traveler, reducing traveler exposure,
and influencing traveler behavior are major actions that, if implemented,
could result in reduced congestion
and crashes in and around work
zones. Agencies are moving toward
real-time traffic management and
travel information as an integral part
of highway operations, in addition to
incorporating the customer need for
information and guidance.
As successful new technologies
are deployed, communities will see
the benefits of roads that open
faster, require less repair work in the
future, and provide safer, smoother
rides at less cost.
Resources
Some of the resources available to help customers and partners make work zones work better
include the following:
- The Accelerated Construction Technology Transfer (ACTT) program promotes the use of innovative
technologies and techniques to accelerate the construction of major highway projects or
corridor improvements using a multidisciplinary team approach. Information on this program is
available at www.fhwa.dot.gov/construction/accelerated/index.cfm or by contacting Jim
Sorenson at 202–366–1333 or Dan Sanayi at 202–493–0551.
- The Making Work Zones Work Better Workshops Series shares information on new and emerging
technologies and highlights operational opportunities and constraints by local agencies.
This practitioner tool provides an open forum for discussion and information sharing to enhance
the body of work zone knowledge and improve future work zone programs. Information
on the workshops is available at www.ops.fhwa.dot.gov/wz/workshops/workshops.htm or by
contacting Daniel Grate, Jr. at 404–562–3912.
- QuickZone is a traffic impact analysis tool that enables practitioners to quantify the queue
length and user delay caused by work zones. Additional information on QuickZone is available
at www.tfhrc.gov/its/quickzon.htm or by contacting Deborah Curtis at 202–493–3267.
QuickZone 2.0 is planned to be released in early 2005 and will be a free update for users with
a valid license for QuickZone 1.0.
|
Carol Keenan is a transportation
specialist in FHWA's Office of Transportation
Operations in Washington,
DC. As a member of the Work Zone
Mobility and Safety Team, she is
responsible for work zone outreach
and education. Keenan holds a
bachelor's degree in logistics from
Penn State and has 18 years of experience
with USDOT. Prior to joining
FHWA, she worked in both the
Federal Aviation Administration and
the Federal Motor Carrier Safety
Administration.
Other Articles in this issue:
Operational Solutions to Traffic Congestion
Regional Collaboration to Improve Safety, Reliability, and
Security
Traffic Incident Management
Work Zones That Work by Carol Keenan
Another Rain Delay
Putting Travelers in the Know
Red Light, Green Light
Managed Lanes
Reliability: Critical to Freight Transportation