January/February
2002
ARTICLES:
Lessons
Learned About Bridges From Earthquake in Taiwan
by Wen-Huei
(Phillip) Yen
Introduction
On Sept. 21, 1999, at 1:47 a.m. (local time), central Taiwan experienced
a destructive earthquake. As a result of this earthquake, more than
2,400 lives were lost, and more than 10,000 people were injured, according
to the Taiwanese official report. Approximately 10,000 buildings and
homes collapsed, and about 7,000 were severely damaged.
Highway
bridges, including those constructed under modern seismic design codes,
were severe damaged. According to the Taiwanese Highway Bureau's preliminary
report, at least nine bridges were severely damaged, including three
bridges that were under construction. Five bridges collapsed due to
fault rupture, and seven bridges were moderately damaged.
This
earthquake, called the Chi-chi Earthquake, measured 7.6 on the moment
magnitude (Mw) scale. Moment magnitude is based on the concept of
seismic movement, and although it is more difficult to compute than
other magnitude scales, it is more uniformly applicable to all sizes
of earthquakes. In particular, for very large earthquakes, moment
magnitude gives the most reliable estimate of earthquake size. However,
all magnitude scales should yield approximately the same value for
any given earthquake.
The U.S.
Federal Highway Administration (FHWA) and the Ministry of Transportation
and Communication (MOTC) of Taiwan formed an investigative team to
evaluate Taiwanese highway bridge performance under the Chi-chi earthquake.
The team members came from FHWA, the Taiwanese Highway Bureau (THB),
and the National Expressway Engineering Bureau (NEEB) of MOTC. The
team visited 10 bridge sites, including two NEEB bridge sites and
eight THB bridge sites.
This
paper presents the preliminary findings and lessons learned from the
team's investigation, which was conducted Nov. 15-17, 1999.
Fault
Rupture Type
Taiwan is located at the junction of the Manila and Ryukyu trenches
in the Western Philippine Sea, where the Philippine plate is being
forced under the Eurasia plate. The Philippine plate is moving northwest,
which causes a significant strike-slip component along the northern
portion of the Manila Trench and essentially creates a "transpressional"
effect that has popped up the island of Taiwan microplate relative
to its larger tectonic neighbors. This "thrust fault" -
also called a reverse-slip fault - pushed up the ground at several
locations, and some bridge sites were lifted as much as nine meters
(30 feet).
Bridge
Design Codes
|
|
|
A pot bearing on this pier sheared and resulted in the displacement
of the structure. |
Bridge
design specifications used in Taiwan have been revised three times
since 1960. Prior to 1960, several design guide specifications were
used for practical design. Some of them were based on Japanese design
codes. In 1960, MOTC issued standard specifications titled "Highway
Bridge Engineering Design Specifications" for the design and
construction of highway bridges. These design specifications were
based on the American Association of State Highway and Transportation
Officials (AASHTO) bridge design specifications issued in 1953. In
1987, MOTC revised this design code based on the 1977 AASHTO bridge
design specifications. Although this code was revised again in 1995
based the 1992 AASHTO specifications, the seismic design part of the
code was not changed much.
The bridges
in the epicenter area were designed to accommodate seismic design
forces of about 0.15 g to 0.2 g. (G or g is the force of gravity -
an acceleration of 9.78 meters/second2. In an earthquake, the forces
caused by the shaking can be measured as a percentage of the force
of gravity.) With the largest peak ground acceleration of the Chi-chi
Earthquake measuring greater than 1.0 g, damage to the bridge structures
was inevitable.
Bridge
Damages
The team first visited two NEEB bridge sites, Neotsou-si and Neotsopu
Kenshi bridges. These two bridges are continuous spans with a pre-stressed
box girder superstructure. They are about 60 to 70 kilometers (37
to 43 miles) away from the epicenter. They were still under construction
and suffered similar damage. In general, both bridges performed well.
However, the pot bearings of both bridges were severely damaged, and
superstructures were offset 2 to 30 centimeters (0.8 to 12 inches).
These bridges are parallel to the direction of the fault, and this
may have mitigated the effect of this large earthquake. Some concrete
bridge foundations and piers were poured one or two days before the
earthquake, and extensive nondestructive evaluation (NDE) examinations
are needed to investigate bonding issues between reinforced steel
bars and concrete.
The team
visited eight THB bridge sites, including the site of a new bridge.
Six bridges had collapsed due to a fault rupture underneath or adjacent
to the bridges. The average ground movement was more than 2 meters
(6.5 feet).
|
|
|
The Shi-wei Bridge collapsed due to piers tilting and large ground
offsets. The fault rupture was directly underneath the south abutment
area. |
Shi-wei
Bridge
It is located on Route 3, which was constructed in September 1994.
It consists of northbound and southbound twin bridges. The total length
of the bridge is 75 meters (246 feet) and was divided into three simply
supported spans of 25 meters (82 feet) each. It is a curved bridge
with a width of 24 meters (78 feet) and is supported by five Precast/Prestressed
Concrete Institute-certified (PCI) girders. Each girder is supported
on elastomeric bearing pads with shear keys to provide transverse
constraints. The second pier of both bridges was tilting, and the
first pier of the northbound bridge revealed shear cracks. The second
and third spans of the southbound bridge and the third span of the
northbound bridge collapsed due to piers tilting and large ground
offsets. The fault rupture was directly underneath the south abutment
area. Because the bridge is skewed and curved, large ground motion
might have caused the bridge deck to rotate and damage the substructures.
The bridges, designed with a simple support beam, almost certainly
would not be able to accommodate ground movements as large as the
Chi-chi Earthquake.
Tong-feng
Bridge
This bridge is also on Route 3, about five kilometers (three miles)
from the Shi-wei Bridge. The Tong-feng Bridge is 573 meters (1,880
feet) long and consists of three parts. The middle part was completed
in 1966, and in 1988, the bridge was widened on both sides. The original
section has 22 spans with four PCI girders to support the 9.5-meter-
(31-foot-) wide bridge deck. The substructure is a pier-wall-type
construction. The later additions widened the bridge deck to 30 meters
(98 feet) with PCI-girder support. However, the substructure used
single-column bridge piers. After the earthquake, the bridge had large
vertical displacements of 10 to 20 centimeters (4 to 8 inches) and
offsets of 30 to 50centimeters (12 to 20 inches) in the transverse
direction. The PCI girders dislodged from the bearings because of
the large transverse movements. One girder was cracked and was temporarily
supported by a steel truss. Although the bridge was severely damaged,
it was reopened to traffic with restricted lane use after the bearings
were replaced with elastomeric pads.
Bei-feng
Bridge
This bridge, completed in 1991, has multiple spans simply supported
by a PCI girder. The superstructure collapsed because the fault ruptured
underneath the bridge. The fault rupture lifted the upper stream by
5 to 6 meters (15 to 20 feet) and created a new waterfall. This reverse-slip
fault also shortened the bridge length and might have caused the second
pier to fail.
|
|
|
| The
Bei-fung Bridge collapsed because the fault ruptured underneath
the bridge. |
The fault rupture under the Bei-fung Bridge lifted the upper stream
by 5 to 6 meters (15 to 20 feet) and created a new waterfall. |
Wu-shi
Bridge
Also
on Route 3, this bridge has 18 spans with a total length of 624.5
meters (2,049 feet) and a width of 25 meters (82 feet). This bridge
is two parallel structures that were constructed during two different
periods. The superstructure of the northbound bridge was constructed
in 1981, but it used the original substructure (pier-wall type) that
was constructed in the 1950s. The southbound bridge was completed
in 1983. Both structures use PCI girders in their simply supported
superstructures, and both have pier-wall-type substructures. The fault
rupture occurred behind and under the northern abutments of both bridges.
Although the two bridges suffered similar ground motions, they failed
in different ways. The first and second spans of the older bridge
(northbound) collapsed. This failure was due to the fault rupture,
which caused a large ground movement, pushing the superstructure back
and forth until it fell down from the "seats" atop the piers.
The bearings also failed due to large compression forces. The third
pier of the northbound bridge was uplifted also. Both superstructures
may have collided during the earthquake, causing some damage to the
substructures. The piers of the northbound bridge suffered tension
cracking and fractured, and the southbound bridge piers had severe
shear cracks and failures.
|
|
|
| Damage
to the Wu-shi Bridge was caused by pier shearing and tension failure. |
This pier of the Wu-shi Bridge was sheared. |
Mao-luo-shi
Bridge
|
|
|
The Mao-lui-shi Bridge did not collapse, but it had concrete spalling
and shear cracks. Most eccentric connections showed distress in
the concrete columns. Some severely damaged locations were temporarily
supported by steel truss. |
This
bridge on Route 3 is a horizontal, curved viaduct with a steel superstructure.
The superstructure consists of four plate girders supported by concrete,
single-column bents. Some of these bents are "C-bent," where
the column is eccentrically connected to the cross-girder. The bridge
did not collapse, but it had shear cracks. Most eccentric connections
showed distress in the concrete columns. Some severely damaged locations
were temporarily supported by steel truss.
Ji-lu
Bridge
The cable-stayed Ji-lu Bridge is on Route 152. Approach spans at both
ends are simply supported, and they lead up to the two-span, single-tower
structure that is approximately 240 meters (787 feet) long. The concrete
superstructure is symmetrically supported by 17 pairs of parallel
cables from each side of the tower. All but one section under the
tower and guardrail was completed at the time of the earthquake. Damage
included one snapped cable, tower structure cracking and concrete
spalling, failure of the pot bearings due to the structure pounding
up and down, and approach spans offset in transverse directions. Unbalanced
loading of the uncompleted bridge might have caused the vertical and
lateral pounding.
Tong-tou
Bridge
This structure on Route 149 is 160 meters (525 feet) long and 9 meters
(30 feet) wide. The bridge's superstructure is PCI-girder supported
by single-column bents. The first and fourth spans collapsed. The
second span tilted and rotated in a transverse direction. The substructures
had severe shear failure and column bents sheared out. Large movements
due to the fault rupture underneath the bridge caused it to fail.
|
|
|
| The
first and fourth spans of the Tong-tou Bridge collapsed. The second
span tilted and rotated in a transverse direction. |
The substructures of the Tong-tou Bridge had severe shear failure
and column bents sheared out.. |
E-Jiang
and Min-Tsu Bridges
The E-Jiang and Min-Tsu bridges had been demolished by the time that
the team visited.
Lessons
Learned
Through the extensive visits and evaluations of damaged and undamaged
bridge sites, the following is a preliminary set of lessons learned
from this investigation:
- Fault
rupture, directly crossing or adjacent to the bridge, is a catastrophic
event, and span collapse is inevitable if the dislocations are large.
- Long-span
bridges are vulnerable in the near-fault sites, especially those
still under construction.
- Large
ground movement and soil failure may cause structural failure.
- Shear
failure must be avoided in piers.
- Shear
key and bearing design need to be consistent with pier design capacity.
- Engineered
abutment backwalls and backfills are essential to prevent span collapse,
even for continuous bridges
- Near-fault
ground motions are intense and extremely punishing to older structures
that are not designed according to modern codes.
Summary
The Chi-chi Earthquake severely damaged highway bridges as a result
of large ground motion and fault rupture directly underneath or adjacent
to bridge sites. Even with the modern design codes, a bridge cannot
resist such huge displacements or offsets of either the superstructure
or substructure. The challenge left for engineers is to develop a
better strategy for constructing bridges across or nearby a known
fault.
Reference
Ian Buckle and Jenn-Shin Hwang. " Bridge Performance in the 921
Earthquake, Chi-Chi, Taiwan," Proceedings of the 15th US-Japan
Bridge Engineering Workshop, Tsukuba, Japan, November 1999.
Dr.
Wen-Huei (Phillip) Yen is a research structural engineer in FHWA's
Office of Infrastructure Research and Development at the Turner-Fairbank
Highway Research Center in McLean, Va. He is FHWA's representative
in the National Earthquake Loss Reduction Program, and he is a technical
committee member of the National Seismic Conference on Highways and
Bridges. He received his bachelor's degree in civil engineering from
the National Taipei Institute of Technology in Taiwan and his master's
degree and doctorate in applied mechanics and civil engineering from
the University of Virginia. He is a registered professional engineer
in Virginia.
For
more information about the work and findings of the evaluation team,
contact Wen-Huei (Phillip) Yen at wen-huei.yen@fhwa.dot.gov
or by telephone at (202) 493-3056
Other
Articles in this issue:
A
Report of the National Highway R&T Partnership Initiative
Managing
Traffic Flow Through Signal Timing
Lessons
Learned About Bridges From Earthquake in Taiwan
An
Olympic Event: Handling Transportation During the Olympics
A
Legacy in Art in a New Exhibition
FHWA
and Nevada DOT Create a Wetland in Nevada
It's
the Ride That Count$