July/August
2001
Moveable
Barrier Solves Work-Zone Dilemma
by Cathy Satterfield
The
Illinois Department of Transportation (IDOT) District Four had a
major challenge. The eastbound McClugage Bridge, which carries U.S.
routes 24 and 150 over the Illinois River in Peoria, needed major
rehabilitation. This meant that the newer westbound bridge would
have to carry two-way traffic while the older bridge was repaired.
However, several construction and maintenance projects on these
routes over the past 10 years, including a very recent project on
the westbound McClugage Bridge, had just about exhausted the patience
of commuters.
 |
| Map
of Peoria, showing the McClugage Bridge. |
|
Nevertheless,
there wasn't any choice. The monumental steel through-truss bridge,
built in 1949, needed the complete replacement of the floor beams
and stringers (which span the beams and support the deck) and repairs
to the trusses above and below. This work could not be done with
traffic on the structure.
To
place both eastbound and westbound traffic on the adjacent, newer
structure would require a positive separation of traffic, which
would provide a maximum of three lanes. So the question became:
"How can we best accommodate traffic?" Do we accommodate the morning
or afternoon rush hour? Or try a scheme with reversible lanes? There
were pros and cons to each option examined.
The
final decision was made to use the Quickchange® Moveable Barrier
(QMB), a product of Barrier Systems Inc. QMB can be moved
laterally by a transfer machine without disrupting traffic to allow
for two lanes in the direction of the rush-hour traffic. QMB consists
of connected 1-meter sections of safety-shaped concrete barrier
with a T-shaped top to accommodate the lifting rollers on the barrier
transfer machine.
The
Alternatives
One of the key pieces of information needed to determine the best
alternative was the traffic data. In addition to the data gathered
through the normal planning process, the district did a five-day,
24-hour-a-day count to get more accurate volume, speed, and truck
data. They performed a capacity analysis and traffic movement studies
to evaluate the current and expected traffic flow. They did not
use the modeling program that they would typically use, QUEWZ, because
it cannot handle merge points that are close together.
Using
the data they gathered, they looked at the following alternatives
and considered the positive (+) and negative (-) aspects of each
alternative:
One
Lane for Each Direction
+ Leaves shoulders for emergency vehicles.
- Creates congested traffic both morning and evening.
Two
Lanes Inbound, One Outbound
+ Accommodates morning rush-hour traffic.
- Creates congested traffic in the evening.
Reversible
Center Lane With Temporary Barriers on Either Side
+ Accommodates both morning and evening traffic.
- Decreases capacity in the two-lane direction because drivers would
be forced to choose their lane prior to reaching the bridge and
they would not be able to change lanes while crossing to adjust
for the lane volumes.
- Requires closure of some roadway ramps that are very close to
the bridge, and does not permit entering traffic to choose a lane,
contributing to the capacity/lane-use issue.
- Makes signing for lane selection especially critical because all
traffic exiting the highway at the far side of the bridge would
need to get into the right lane prior to getting onto the bridge.
This would also contribute to the problem of capacity in the right
lane.
- Restricts access for incident response.
- Reduces lane and shoulder width.
Reversible
Lanes With a Moveable Barrier
+ Accommodates both morning and evening traffic.
+ Eliminates the capacity and lane-assignment problems mentioned
above.
- Costs more.
- Poses potential problems in case of difficulties with the equipment/technology.
- Reduces shoulder width.
The
Decision-Making Process
The district decided to pursue the project with a reversible lane
using a moveable barrier because that alternative satisfied the
most significant operational and safety needs. From an operational
standpoint, two westbound lanes were needed during the morning rush
period and two eastbound lanes during the evening rush period to
prevent the same congestion problems that were experienced the previous
year during the work on the westbound bridge. From a safety perspective,
QMB provided a reversible-lane solution with minimal worker exposure
to traffic while permitting access for emergency vehicles.
In
addition, the district was interested in evaluating the technology
to determine its potential usefulness on an upcoming project - the
reconstruction of I-74 through Peoria.
Potential
Problems
The district looked into some issues based on the previous experiences
of IDOT. Many of the issues were related to QMB, but there were
also some challenges with geometrics, public information, and emergency
services.
The
decision about whether to buy or lease the equipment was based on
an analysis of the need for specialized maintenance and storage
and the possibilities for future use. The maintenance issue was
important because the district was concerned about delays to the
project. The bid proposals required the contractor to lease or purchase
the machine directly from the supplier so that IDOT would not be
liable for delays caused by equipment problems. If QMB was successful,
it was quite likely IDOT would use it on future projects in the
area, but by then, an improved version would probably be available.
In addition, because the district had a concern about the need to
continue to store and maintain the equipment, district officials
decided to go with the lease option.
This
technology was tried in the East St. Louis area when it was new,
and some problems with the equipment were encountered. In light
of this, the district took a few precautions to ensure that the
equipment used on this project would work as needed. Because several
variations of the transfer machine are available around the world,
the district developed a generic specification indicating the required
capabilities to ensure that a newer version would be used. The specification
also required that a minimum number of spare sections of barrier
be available on site in case replacements were needed after a crash
or other incident.
IDOT
also had to consider the alignment of the roadway, which is offset
from the bridge on the Peoria side. This required that the barrier
must accommodate the appropriate curvature and must be capable of
holding the correct alignment along the curve during the twice-daily
transfers. To meet these requirements, the transfer machine had
to accommodate an approximate 1,000-foot (300-meter) radius.
 |
|
The
eastbound approach to the McClugage Bridge.
[Charleen
Boudreu, Illinois DOT]
|
|
U.S.
24 runs parallel to the river in Peoria and joins U.S. 150 very
close to the bridge. On the other side of the river, U.S. 150 breaks
off from U.S. 24 just past the bridge and heads south. A significant
portion of the bridge traffic enters and exits on these ramps that
are very close to the structures. Typically, traffic on the entering
ramps must merge with through traffic. After analyzing the traffic
data, IDOT engineers thought they could increase the capacity in
the direction with two lanes by eliminating this merge maneuver,
giving on-ramp traffic their own through lane. On the east side,
this was managed by funneling the westbound traffic on the through
route (U.S. 24) down to one lane prior to the entrance ramp (U.S.
150), which then had its own lane when two lanes were open westbound.
When only one lane of traffic was westbound, the merge still had
to occur, but at least, it was separated from the lane closure merge
of the U.S. 24 traffic.
On
the west side (in Peoria), a similar system was used when two lanes
were eastbound, but when only one lane was eastbound, the on-ramp
was closed, and a detour for this traffic was provided. Another
concern about the use of QMB was the load that it would place on
the structure. When the transfer machine is holding 50 feet (15
meters) of barrier as it makes the transfer, it is above the legal
load limit on the McClugage Bridge. The bridge engineer leading
the project design checked the integrity of the structure to ensure
it would not be compromised, and appropriate permits were secured.
The
lane-changing process took about 30 minutes. The transfer machine
moves at about five miles per hour (eight kilometers per hour),
and after the barrier was moved, some drums had to be moved to complete
the process.
 |
| The
barrier-moving machine has just completed moving the barrier
and is now moving toward its parking space between the
permanent barrier and the moveable barrier on the west
side of the McClugage Bridge. [Charleen Boudreu, Illinois
DOT] |
|
So
that regular users of the bridge could anticipate whether one or
two lanes would be open in their direction of travel, the district
decided that the lane changes would take place at specific times
each day. A $1000 per hour penalty was levied against the contractor
whenever the change was not completed within the specified one-hour
window.
Based
on the history of public input from projects in the area over the
previous decade, IDOT knew that congestion would be a prominent
issue. Even with QMB providing two lanes in the rush-hour direction,
IDOT was concerned that excessive congestion would create a need
to reroute traffic at certain times. To deal with this, the district
decided to implement two other new technologies. One was a real-time
traffic control system called ADAPTIR that uses both Doppler radar
to detect reduced traffic speeds and strategically placed variable
message signs to display delay or diversion messages. The second
technology was a surveillance system.
Emergency
service agencies were very helpful in anticipating potential problems
and in taking steps to alleviate or eliminate them. For example,
the police stated publicly that they would be enforcing the no U-turn
regulation. Tow trucks were on site, one on each side of the bridge,
during rush hour. Sites were built nearby to which disabled vehicles
could be quickly towed to minimize any disruption of traffic.
Results
The use of QMB on the project was a tremendous success. The transfer
equipment worked well without any significant interruption to traffic.
There was some minor kinking of the barrier rail and some longitudinal
creep, but the operator of the equipment quickly learned how to
avoid these problems. Actual traffic counts during the project showed
that about 20 percent of the preconstruction traffic was not using
the bridge. The backups that did occur were less than anticipated.
In fact, there were so few problems that the automated real-time
traffic control system was never put to full use.
One of IDOT's goals was to minimize workers' exposure to traffic. The
QMB transfer machine does most of the work during the lane change,
but at the ends of the barrier, some drums had to be moved. Also,
the eastbound on-ramp had to be closed for the morning lane configuration
and opened for the evening lane configuration. The inspectors and
the work-zone crew worked out a system to make the daily changes
quickly, orderly, and accurately by painting orange circles around
the drum location for the morning configuration and white circles
for the evening configuration. This allowed the entire lane-change
process to be done in approximately 30 minutes.
Moving
the transfer machine across the outside traffic lanes to get it
out of the way when not in use would have required stopping traffic.
However, this problem was eliminated by safely storing the machine
in the median. When parked on the east end of the bridge, the machine
was shielded from traffic by the moveable barrier on one side and
a line of temporary barriers on the other side. On the west end
of the bridge, the moveable barrier on one side and an existing
permanent concrete barrier on the other side separate the machine
and traffic.
IDOT
aggressively informed the public about work-zone conditions. The
department held a press conference prior to closing the bridge and
provided news releases and articles to the media to keep the public
properly informed during the project. IDOT provided a safe vantage
point from which media could film and photograph the bridge and
traffic. In addition, the local newspaper mounted a video camera
on its nearby high-rise building, and the video was webcast for
anyone who wanted to check the traffic situation at the bridge site.
Because the project went so smoothly, virtually all the press was
positive.
Lessons
Learned