November/December 2000
Practical Research Answers Real-Life Questions
by: Sybil Hatch
The
Federal Highway Administration (FHWA) often develops collaborative partnerships
with professional and trade organizations to serve the highway community's
best interests. Such is the case with FHWA's long-standing relationship
with ADSC: The International Association of Foundation Drilling.
Through this partnership, drilled shaft technology has advanced by leaps
and bounds. Drilled shaft use in highways has doubled over the past
decade. Departments of transportation and other public and private sector
owners are reaping the benefits.
Drilled shafts often make superlative bridge foundations. They can carry
huge vertical loads. They effectively carry large lateral and seismic
loads. For many soil conditions, they are easier to install than driven
piles and do not create ground vibrations. They can be readily installed
offshore and can be made highly resistant to scour. And they are economical.
One perceived disadvantage of drilled shafts is that because the shaft
is built in-place (as opposed to formed in a casting yard as with piles),
it is difficult to monitor the shaft's constructed integrity. But as
the level of comfort in using drilled shafts as foundations has increased
over the years, so has the sophistication in testing their properties.
"In the early 1990s, states started routinely performing nondestructive
testing on their drilled shafts and noticed some anomalies such as potential
voids or discontinuities in the concrete," explains Albert DiMillio,
head of the FHWA Geotechnical Research Team.
"As testing has become more commonplace," says DiMillio, "databases
of observations have grown, leading to more questions about their performance.
That's one of the main areas on which we're focusing our research efforts."
What
Causes Anomalies?
Anomalies can be caused by any number of reasons, but to understand
anomalies, one needs to understand the basics of drilled shaft installation.
First, a hole is drilled into the ground. If the hole cannot stand open
on its own, either steel casing or slurry is used to keep the sidewalls
from collapsing into the hole.
A steel reinforcing cage is lowered into the hole, and the concrete
is placed. If the hole is filled with slurry, the concrete is placed
by using a "tremie" pipe or by pumping from the bottom of
the hole upward, thereby displacing the slurry.
In an open or cased hole, free-fall of concrete is the preferred placement
method. If the hole is cased, the casing is then pulled out before the
concrete hardens.
Despite care and skill in construction, voids or gaps in the concrete
can occur for many reasons. For example, even when using slurry, soil
can cave into the concrete. Sediment can be caught in the slurry as
the concrete is placed. The reinforcing cage can be out-of-plumb. When
extracting the casing, the concrete can adhere to the casing and cause
gaps.
How
Well Can We Detect Anomalies?
Two concurrent research programs funded by FHWA, ADSC, and others are
being conducted to answer this question. One program is at Polytechnic
University in Brooklyn, N.Y., and the other is at the University of
Houston.
In research led by Dr. Magued Iskander, licensed professional engineer
and professor at Polytechnic University, artificial anomalies were installed
in six full-scale drilled shafts installed at the National Geotechnical
Experimentation Site (NGES) located at the University of Massachusetts
at Amherst.
Items such as 1- to 10-gallon (3.78- to 37.8-liter) plastic pails, foam
insulation, 9- to 13-inch- (230- to 330-millimeter-) diameter cardboard
construction tubes, and 4-inch (102-millimeter) flexible drain pipe
were secured to the reinforcing cage of 3-foot- (0.91-meter-) diameter
drilled shafts. FHWA provided funding for instrumenting the shafts and
helped facilitate the work. Seven testing organizations, including two
universities, tried their hand at detecting these anomalies using various
nondestructive testing techniques in a Class-A prediction symposium.
"Although the data are still being analyzed, preliminary results
indicate that most large anomalies were located by all detectors,"
says Iskander, "but there were also a number of 'false positives'
showing an anomaly where none actually existed.
Similar research conducted by Dr. Michael O'Neill and others at the
University of Houston, also funded by FHWA and ADSC, indicates that the
largest void that would go undetected by a well-conceived testing program
is one that occupies about 15 percent of the gross cross-sectional area
of the shaft. For a 3-foot-diameter shaft, this equates to a void the
size of a 1-gallon paint can. The results were consistent with earlier
studies conducted for and by FHWA.
 |
|
At
FHWA's Turner-Fairbank Highway Research Center, researchers map
the cracks caused by incremental loads applied to this
0.76-meter (30-inch)
diameter drilled shaft with a built-in anomaly.
|
How
Do Anomalies Impact Performance?
Finding anomalies is important, but the compelling question is how these
anomalies affect the vertical and lateral load-carrying capacity of
the drilled shaft. The two current FHWA/ADSC research projects mentioned
above are exploring this issue.
Research at the Polytechnic University involves axial load tests on
the shafts used for the prediction symposium. The research is ongoing,
so data are not yet available.
The
University of Houston load-testing program is further along and results
are providing good insight into the structural performance of drilled
shafts with anomalies. At the NGES at the University of Houston, six
full-scale drilled shafts, each three feet in diameter, were constructed.
Five shafts had pre-installed minor anomalies, while a sixth shaft that
had no anomalies served as a reference. The shafts were loaded laterally
until they approached structural failure.
Initial results showed that the ultimate lateral load capacity was reduced
by a maximum of 10 percent. However, after the test shafts were exhumed,
inspected, and measured, researchers factored in the reduction in shear
strength caused by shaft geometry.
"We
found that the maximum reduction in capacity was actually 23 percent,"
says O'Neill. "But we still weren't satisfied that we fully understood
the whole picture. For example, we believed that the anomaly's position
within the shaft may also impact its load-carrying capacity."
How
Can We Be Sure?
Rather than performing full-scale testing, O'Neill's team set out to
determine whether small-scale laboratory shafts adequately simulated
large-scale drilled shafts. Lab-size shafts can be built more economically
to study the various factors influencing shaft behavior.
O'Neill's team tested 19 scaled shafts to simulate nine or 10 anomalies
that can be caused by normal construction techniques.
"We determined that an anomaly outside of the reinforcing cage
has much less impact than one inside the cage," says O'Neill.
Two full-scale tests were conducted at the Structures Laboratory at
FHWA's Turner-Fairbank Highway Research Center on specimens that were
identical to the small-scale specimens to evaluate further the effects
of scale.
"At the outset, we thought that the lab tests would not be representative
because the lab shaft is not confined by the soil," explains O'Neill.
"It turns out that the soil-confining pressure was not important
after all when compared with the confinement afforded by the transverse
steel in the reinforcing cage."
From the laboratory testing, O'Neill's team could then develop and calibrate
a computer model to evaluate other anomaly sizes, geometries, and combinations.
What's
the Bottom Line?
In designing drilled shafts, engineers typically use capacity-reduction
factors to account for anomalies and other uncertainties. The computer
model was used to develop capacity-reduction factors for various combinations
of anomalies.
The computer model showed that for the unlikely case of three simultaneous
anomalies occurring in a critical section of a drilled shaft, the pure
axial capacity would be reduced by approximately 33 percent and the
pure flexural capacity would be reduced by 47 percent from the theoretical
values for a perfect section.
Intuitively,
one expects that the occurrence of three simultaneous anomalies at the
critical section along the shaft has a very small probability. Therefore,
the next step in the research will be to apply probabilistic studies
to refine the deterministic capacity-reduction factors previously calculated.
"The results of our research," says FHWA's DiMillio, "will
give designers, owners, and contractors confidence that they are building
safe economical drilled shafts that take into consideration the imperfect
state of even the most carefully constructed shafts."
|
Workshop
Teaches Real-Life Curriculum
The
drilled shaft research sponsored by FHWA, ADSC, and others is
focused on practical solutions that have a direct benefit on the
way structures are designed and constructed. ADSC recently sponsored
another event that has a direct benefit to those who design drilled
shafts and anchored earth-retention structures now and for generations
to come.
ADSC's week-long Faculty Workshop 2000, held in July, provided
nearly 60 of the nation's leading civil engineering educators
with the knowledge and resources to teach their students the most
up-to-date design and construction technologies.
Faculty
Workshop 2000 consisted of a combination of hands-on classroom
instruction and field construction observation and testing. On
the first day of the workshop, ADSC members demonstrated how drilled
shafts are constructed in soil and rock.
One
of the shafts was built with anomalies, similar to the FHWA-sponsored
research. The final day of the workshop included a demonstration
of the latest nondestructive evaluation and load-testing techniques
- again, many of the same as were used in the FHWA-sponsored research.
A similar workshop conducted by ADSC in 1987 is regarded by the
geotechnical engineering community as an ideal model for collaboration
between industry and academia. ADSC estimates that nearly 39,000
students have been exposed to the constructibility message from
the 1987 workshop.
Being able to visualize first hand how structures are built and
tested allows civil engineering faculty to teach their students
how to create more constructible designs. In this way, the entire
industry benefits.
|
Sybil
Hatch is a technical and marketing communications consultant, specializing
in the engineering and construction industry. She has a bachelor's degree
in civil engineering and a master's degree in geotechnical engineering,
both from Virginia Tech. She is a registered professional engineer in
California and has been practicing civil and geoenvironmental engineering
for 14 years.
Other Articles in this Issue:
Using Monte Carlo Simulation for Pavement Cost Analysis
ITS Peer-to-Peer Program
Design Evaluation and Model of Attention Demand (DEMAnD): A Tool for In-Vehicle Information System Designers
Studying the Reliability of Bridge Inspection
Ultrasonic Inspection of Bridge Hanger Pins
The Northwest Transportation Technology Exposition
Faster, Easier, Cheaper - Pyrotechnical Anchoring
Practical Research Answers Real-Life Questions
A Nondestructive Impulse Radar Tomography Imaging System for Timber Structures
Strategic Work-Zone Analysis Tools