One-of-a-Kind
Bridge Project Protects National Bird
by Dena M. Gray-Fisher
 |
| Bridge
piers peering out above the Iowa River Valley tree line.
(photo courtesy of Iowa DOT) |
|
The
Iowa Department of Transportation (DOT) and its construction and
design partners are taking extreme measures to protect the environment
and our national symbol, the bald eagle, during the relocation of
a 40-mile (64-kilometer) segment of U.S. Route 20.
Some may say the U.S. 20 project has had more than its share of
environmental issues to address. Located in Hardin and Grundy counties
in north central Iowa, the corridor is characterized as a rural
agricultural area punctuated by several small communities and containing
an environmentally sensitive greenbelt area in the Iowa River valley.
The Iowa River Greenbelt is a rare, remaining fragment of old-growth
woodland that has survived the age of agriculture. The region features
a steep river valley rich with traces of prehistoric cultures and
remnants of 19th century farmsteads. It is also a roosting and wintering
area for bald eagles, and it is a home for the rare northern monkshood
plant and three endangered or threatened species of freshwater mussels.
 |
| Artistic
rendering of the completed U.S. 20 bridge and river valley
area. (rendering courtesy of HNTB) |
|
Residents
of the communities along the greenbelt value this precious natural
resource and strongly support its preservation. Finding a way to
build a modern, safe, and efficient highway facility through such
an area, while minimizing construction impacts and highway intrusion
at the Iowa River crossing in Hardin County, proved to be very challenging.
This project addressed some major issues of environmental impact,
including:
Advancing the U.S. 20 highway project to the construction stage,
after nearly four decades of study and controversy, has been a major
accomplishment for the Iowa DOT. It took some of the nation's most
innovative design and construction methods to achieve the project's
main objective of treading as gently as possible through this sensitive
area.
 |
| Special
bridge pier design with softer contours for a more natural
setting. (photo
courtesy of Iowa DOT) |
|
Project
Partners
The Iowa River bridge segment of the 40-mile highway relocation
project was let in 2000, and site preparation work began in late
July 2000. The total construction process will take less than three
years; the bridge is scheduled to open to traffic in November 2002.
Site cleanup and replanting will continue until July 2003.
The cost for design and construction of the bridge is approximately
$20 million. Of this amount, 15 to 20 percent of the costs can be
directly attributed to design and detailing considerations added
to accommodate the environmental concerns and site accessibility
challenges.
 |
| Steel
bridge spans under construction in the "launching
pit". (photo courtesy of Iowa DOT) |
|
The team making this project possible includes the Iowa DOT, which
is responsible for overall project management; the Federal Highway
Administration (FHWA), serving as technical consultant and providing
financial support; HNTB Corp. of Kansas City, Mo., serving as the
design and construction consultant; Jensen Construction of Des Moines,
Iowa, the general contractor; A-Seeding of Colfax, Iowa, a subcontractor
providing the specialized erosion-control services; and several other
subcontractors affiliated with Jensen's parent company, The Rassmussen
Group.
Norm McDonald, director of Iowa DOT's Office of Bridges and Structures,
has been working on the project, in one capacity or another, for years.
He said, "I started on the project while I was the department's
chief structural engineer. The department had been looking for volunteers
to work on the project, and I spoke right up thinking this would be
a very interesting project. It has been that and more. The best part
may be the fact that my office is only an hour away from the project
site so I've been able to visit the site frequently to monitor its
progress."
In all, nearly 40 Iowa DOT staff members have been involved in some
aspect of the U.S. 20 bridge project. Planners, designers, environmental
specialists, contracts and specifications staff, materials technicians,
and construction personnel all have played an important role in the
project.
Since taking office a few years ago, FHWA Iowa Division Administrator
Bobby Blackmon has been involved in the project's design and permitting
processes. FHWA Division Bridge Engineer Curtis Monk has also been
a valuable contributor to the project. Monk's geotechnical expertise
helped resolve several complicated engineering issues associated with
the bridge pilings and drilled shafts.
 |
| Bridge
constructed in area with stringent equipment-access restrictions.
(photo courtesy of Iowa DOT) |
|
The
Bridge
The
U.S. 20 bridge over the Iowa River is a 1,510-foot (460-meter) weathering
steel I-girder structure, consisting of five 302-foot (92-meter)
spans supported on four concrete piers and two end abutments. Two
66-foot (20-meter) precast concrete spans connect the bridge to
the roadway approaches.
The
two central piers are supported on 8-foot- (2.4-meter-) diameter
concrete drilled shafts extending 82 to 91 feet (25 to 28 meters)
to bedrock. The two outer piers and two end abutments are supported
by 100-ton (890-kilonewton) piles driven to bedrock. To protect
the Iowa River, none of the bridge piers is located in the waterway.
 |
| First
steel arriving on site in "launching pit". (photo
courtesy of Iowa DOT) |
|
The
bridge deck will eventually carry traffic approximately 137 feet
(42 meters) above the Iowa River. Each deck structure consists of
a nine-inch (230-millimeter) concrete slab with a 1.5-inch (38-millimeter)
low-slump concrete wearing course, supported by a system of four
136-inch- (3,450-millimeter-) deep I-girders spaced at 142-inch
(3,600-millimeter) centers. The deck structures are supported on
cast-in-place reinforced-concrete substructure units consisting
of two column bents ranging in height from 66 to 125 feet (20 to
38 meters) and founded on the drilled shafts or driven H-piles.
David
Rogowski, project engineer and construction consultant with HNTB
Corp. said, "I have been involved with this project for the
last five years, and as you can imagine, I am very excited about
seeing this one finally built. It is amazing to see numbers generated
with computer models come to life during the actual construction
of the bridge."
Atypical
Bridge-Building Technique
To minimize
the impact of construction on the floor of the greenbelt valley,
an atypical bridge-construction technique called "launching"
is being used on this project. Although this technique has been
widely used in Europe with concrete box structures, it is not commonly
used for the erection of steel I-girder bridges. It has never been
used on a project of this magnitude in the United States.
 |
| First
two eastbound spans under construction in "launching
pit". (photo courtesy of Iowa DOT) |
|
"This
bridge will be a record span for a launched set of highway girders
in both the category of longest total launched steel bridge and
longest free cantilever," said Rogowski.
The
only other project in the United States known to have used a similar
construction technique involved a railroad bridge in Redland, Okla.
The Redland bridge has a longer main span (350 feet or 107 meters);
however, it was launched from both ends of the bridge. (The U.S.
20 bridge is being launched from one end of the bridge.) The maximum
free cantilever was 250 feet (76 meters), which was the span length
of the approach spans. The total bridge length was 2,100 feet (640
meters); therefore, each launched half was 1,055 feet (322 meters).
 |
| Launching
process begins as nose skid begins ascent over second
pier. (photo courtesy of Iowa DOT) |
|
The
following principles and methods of the launching process were applied
to the U.S. 20 project.
The
contractor began by assembling the first two steel spans of the
eastbound bridge superstructure in a "launching pit" located
above the river valley and behind the east abutment. The pit was
dug in-line with what will eventually be the roadway approach.
A temporary
"launching skid" or steel nose was then attached to the
front of the first span. During launching, the girders deflect downward
to such a degree that they are actually at a level below the top
of the pier and would hit the side of the pier without the skid.
The launching skid is tapered, allowing the skid to land on top
of the pier and guide the girders upward into place.
 |
| Nose
skid extends over pier during launching process. (photo
courtesy of Iowa DOT) |
|
The
connected spans were then launched from the edge of the valley onto
the first pier and out toward the second by means of hydraulic rams
and Dwidag bars and temporary 275-ton (2,446 kilonewton) roller
bearings. The bearings are placed at each girder centerline under
the steel bridge spans as they are constructed in the pit and on
each of the bridge piers. They serve an important function in the
process of rolling the lines the entire distance across the valley.
After
reaching the second pier and achieving a major milestone in the
project, the launching procedure was temporarily halted as the next
spans were constructed in the pit and attached to the first two.
Each new section that is added to the line serves as a counterweight
for the cantilevered portion.
This
process of constructing a span, launching it, adding a new section,
and launching will continue until all five spans of the bridge are
in position.
Then,
the contractor will remove the launching skid from the eastbound
lane and attach it to the first span of the westbound lane. The
entire process will be repeated until all spans of the westbound
lane are in position. Then the full-length, steel superstructure
will be permanently attached to the piers.
 |
| First
eastbound span reaches second pier. (photo courtesy of
Iowa DOT) |
|
Construction
Challenges
The environmental
concerns associated with the bridge site posed many construction challenges
for both the designers and the contractor.
Environmental
mitigation measures included: Prohibiting construction activity on the west slope of the river
valley (near the bald eagles' roost) between Nov. 1 and April 15.
Monitoring construction activity on the east slope from Nov.
1 to April 15 with the possibility of shutdown at any time if it
were determined that the noise and/or construction activities caused
disruption to the roosting habits of the bald eagles.
Constructing
a sound barrier/visual buffer — an earthen berm and plantings
that will effectively provide a visual screen and noise barrier
between the roost site and traffic — adjacent to the right-of-way.
Constructing
a containment system to prevent potential equipment fluid spills
(fuel, oil, etc.) from reaching the river.
Monitoring
and protecting the known monkshood plant site from construction
disturbance.
Preserving
existing vegetation through tailored construction activities that
limit construction equipment access into the river valley.
Creating
a drainage system and sediment basin to direct rainwater and melted
snow (and ice-control materials) on each side of the river. (Runoff
from the new bridge and portions of the approach will travel through
pipes embedded in the bridge structure and will be diverted to silt
basins off each side of the bridge and away from the river channel.)
Saving
large stones and natural rock for landscaping.
Saving
cleared, woody vegetation for future landscaping.
Removing
all excavated materials, including drilling material and spoils
from the drilled shaft operations, to prescribed disposal sites
above the limits of the river valley.
In
addition to these construction mitigation measures, a biologist
is required to be present throughout construction to monitor the
impacts to the Iowa River and associated aquatic communities and
to ensure that construction activities do not present a threat to
the three species of threatened freshwater mussel populations.
Following
construction, any disturbed areas must be restored to preconstruction
contours and be seeded or replanted. Project impacts will also be
monitored for three to five years after completion. Annual monitoring
of the wintering bald eagle population is also required for a minimum
of two years after project completion.
Construction
Project Manager Dan Timmons of Jensen Construction said this project
has generated a range of emotions. "First, there was anxiety
over all of the unknowns associated with use of the new launching
method. Then, there was a sense of relief as major milestones were
achieved. Finally, great pride in all of our accomplishments."
"Jim
Rasmussen, the president of The Rasmussen Group and owner of Jensen
Construction, has spent 40 years building this company so that it
could become a self-sufficient organization. This project has allowed
us to exploit that expertise," said Timmons. Besides Jensen's
bridge construction crew, various subsidiary companies of The Rasmussen
Group have been involved in the project, including companies who
made the steel, hauled materials and equipment, fabricated the roller
bearings, and provided the ready-mix cement.
Building
Iowa's Future
Iowans
have had a long history of meeting extraordinary challenges through
the development and use of innovative approaches in the field of
highway transportation. The U.S. 20 project is just another example
of the ingenuity and tenacity that it takes to provide highway users
with the benefits of an excellent transportation system, while respecting
the ecological, historical, and archaeological treasures of the
state.
Dena
M. Gray-Fisher is the director of Iowa DOT's Office of Media
and Marketing Services. She has held the position since 1996. She
is also the secretary-treasurer of the American Association of State
Highway and Transportation Officials (AASHTO) Administrative Subcommittee
on Public Affairs.
For
more information on the technical aspects of this project, contact
Norm McDonald, director of Iowa DOT's Office of Bridges and Structures,
at (515) 239-1206.